Interest
29 Judge Curtis explained the award of interest in the following terms:
9. If Mr Parlby is to be placed by money in the same situation in which he would have stood had Mrs Palasty completed the contract on 23 May 2000, he must be compensated for having been kept out of his money between that date and 16 [sic] March 2001 when the subsequent purchase was completed. The plaintiff claims interest on $2,771,600, (being the sale price of $3,150,000 less deposit, agent's commission and legal fees), at the rates of interest set out in Schedule 5 to the Uniform Civil Procedure Rules 2005. I regard this approach as reasonable and allow the claim in the amount of $243,748.93.
30 His Honour thereby implicitly adopted the reasoning and calculations presented by the vendor's counsel at trial in final submissions (see Black 77-8). Unfortunately, as the Judge himself acknowledged when granting a stay of execution:
However, in relation to the claim for interest, my reasons, comprised in para 9 of my judgment, egregiously omitted to canvass the arguments submitted by the defendant as to why an order should not be made. It is the duty of a judge to give reasons. It is quite patent that this I failed to do. The effect of that failure is that the appeal in my opinion must certainly succeed.
31 On appeal, the parties sensibly agreed that this Court could and should determine the matter of interest on the evidence at first instance.
32 After judgment was reserved the Court invited and received further submissions relevant to the award of interest.
33 It was clarified that this component of the award had been claimed as damages in the nature of interest ("interest damages"). This was the way that the claim was framed by way of Particulars in the Further Amended Statement of Claim. Such damages are recoverable in accordance with the principles in Hadley v Baxendale if the evidence demonstrates that those principles apply in the particular case (Hungerfords v Walker (1989) 171 CLR 125; Sempra Metals Ltd v Inland Revenue Commissioners [2007] UKHL 34, [2007] 3 WLR 354).
34 Interest damages are not to be confused with an award of statutory interest under s100(1) of the Civil Procedure Act 2005 on the whole or any part of a sum of money recoverable as debt or damages. Interest on the balance of purchase money under the contract during the period of delay cannot be awarded under this section because the Court cannot give judgment in debt or damages for the principal.
35 It is, however, commonplace for the Court to calculate an interest damages award by reference to the rates of interest set out in Schedule 5 to the Uniform Civil Procedure Rules 2005 (see Hexiva Pty Ltd v Lederer (No 2) [2007] NSWSC 49 at [16]). This was the approach adopted by Young J in Jampco at pp56,585-6 where there was an absence of evidence showing that a higher or lower rate of interest was appropriate. The purchaser had not challenged the use of Schedule 5 interest rates.
36 The award in the District Court had proceeded on the following basis (adopting the submissions and calculations of the vendor: see Black 77-82). Interest was calculated according to Supreme Court rates for the period from 23 May 2000 (when the contract was terminated for breach) to 20 March 2001 (when the resale contract was completed) on the sum of $2,771,600. That sum was derived as follows:
Sale price $3,150,000
Less deposit $ 315,000
Less agent's fee $ 63,000
Less extra legal fees $ 400
$2,771,600
37 This approach to interest damages did not involve calculations based upon actual losses incurred by the vendor in consequence of his inability to discharge the mortgages he had placed over Hunters Hill, either at the time of contracting or by way of refinancing when the purchaser defaulted. Calculations based on such outlays had been provided, and they had been the basis of the interest damages claim as pleaded (see Red 5-6). But in final submissions at trial, the vendor referred to the mortgage outlays only to demonstrate the justice of awarding interest damages at Supreme Court rates according to the reasoning in Jampco (see Black 78). The vendor adhered to this approach when defending the award in this Court.
38 It will be seen that after allowing for the forfeited deposit and the additional costs of resale, the trial judge awarded interest on the unpaid balance of the purchase moneys spanning the period from 23 May 2000 to 20 March 2001. This tracked the approach adopted by Young J in Jampco (see at p56,581). In Senavale Pty Ltd v Nolan (2000) NSW Con R 55-948, [2000] NSWSC 619, Macready M had approached interest on common law damages in a similar fashion, holding that he considered himself bound to do so in light of Jampco (see Senavale at [46]-[48]).
39 Young J explained the principles as follows in Jampco (at p56,585):
In equity, where damages or compensation was claimed, it was customary to allow interest on the purchase money from the date fixed for completion, but to allow a set-off if appropriate, for the vendor's occupation or the benefits which it derived from remaining in possession of the property, see Leggott v Metropolitan Railway Co (1870) LR 5 Ch App 716, at p719. The set-off was not permitted where the circumstances were that the vendor was against his wishes forced to remain in possession of the property on a precarious basis, never knowing exactly when his occupation would come to an end. Interest under sec 94 of the Supreme Court Act [the predecessor to s100 of the Civil Procedure Act 2005 ] is awarded to compensate a successful plaintiff from being kept out of his moneys whilst proceedings are taken to enforce his claim. Had the defendant paid what is subsequently held to be a just debt at the appropriate time, then the plaintiff could have put out the money at interest. In the instant case, moreover, the evidence quite clearly shows that the plaintiff could have made very good use of that money, and in fact had to pay interest at penalty rates in respect of some part of the mortgages over the property, and was not able to complete the contract at Paddington.
Normally, the interest would be calculated on the balance of the net proceeds of sale up until the resale, and on the balance of the damages to which the plaintiff is entitled from the date of resale at the Court rate. However, where there is evidence before the Court that the plaintiff has had to pay out interest at a greater rate than the Court rate, then, in accordance with the Court of Appeal's decision in Leighton Contractors Pty Ltd v Queensland Insurance Co Ltd (4 October 1978, unreported) the Court should allow that higher rate. Similarly, if the successful party is borrowing money at a lower rate, only the lower rate will be allowed.
40 The parties joined issue in this Court as to particular aspects of what I shall term the Jampco approach. In subsequent written submissions they addressed a memorandum from the Court inviting their views as to the correctness of Jampco.
41 The purchaser submitted that the date of resale should be taken as the date of contracting the resale transaction, as distinct from the completion date of that transaction. This submission should be rejected because a vendor's loss referable to delayed receipt of the purchase price does not come to an end until receipt of the proceeds of the resale (assuming that the resale is at the same price). The remarks in Jampco (at p56,587) upon which the purchaser relies in this regard do not indicate a different result, because in that portion of his judgment Young J was dealing with the date on which interest started to run in a situation, unlike the present, where a vendor claimed liquidated damages based on an express contractual right to recover a deficiency upon a resale pursuant to a contractual right such as cl 9.3.1 of the standard Contract for the Sale of Land. Here the vendor relied upon the alternative common law right to damages for breach of contract recognised by cl 9.3.2.
42 When a vendor duly elects to terminate a contract because of breach, the purchaser is discharged from the duty to complete.
43 The general principle governing the award of damages for breach of contract is that stated by Parke B in Robinson v Harman (1848) 1 Ex 850 at 855, 154 ER 363 at 365 which was cited with approval in Commonwealth v Amann Aviation Pty Limited (1991) 174 CLR 64 at 80, 98, 117, 134, 148, 161:
… where a party sustains a loss by reason of a breach of contract, he is, so far as money can do it, to be placed in the same situation, with respect to damages, as if the contract had been performed.