P & N NSW Pty Ltd T/As Euro Solar v James
[2017] NSWCATAP 138
At a glance
Source factsCourt
NCAT Appeal Panel
Decision date
2017-05-31
Source
Original judgment source is linked above.
Judgment (12 paragraphs)
Background
- This is an appeal from a decision made in the Consumer and Commercial Division of the Tribunal published on 12 January 2017. We will refer to the decision as "the Decision". In the proceedings, the applicants sought compensation for damage to the roof of their home alleged to have been caused by the respondents' subcontractor who installed solar panels on the roof.
- The result of the Decision was that the applicants were awarded compensation in the sum of $9,231.53. The respondent in the proceedings (the party contracting to install the solar panels) has appealed the Decision. We will refer to the installer as the appellant and the applicants at first instance as the respondents.
- The appellant received the Decision on 16 January 2017 and lodged the Notice of Appeal on 12 March 2017. Accordingly, the appeal was lodged out of time. It should have been filed within 28 days of 16 January 2017 (see cl 25(4)(c) of the Civil and Administrative Tribunal Rules 2014 (the Rules)). The appellant makes an application for the Appeal Panel to extend the time for lodgement of the appeal and therefore invokes the power of the Tribunal provided under s 41 of the Civil and Administrative Tribunal Act 2013 (NCAT Act).
The Decision
- The Decision may be summarised as follows: 1. The respondents purchased the home in August 2015 and had obtained a pre-purchase inspection report. The solar panels were installed by the appellant or by its subcontractor, Mr Ingersol in December 2015; 2. The respondents' evidence was that there were no dents on the roof prior to the installation but there were 36 dents in the roof in the vicinity of the solar panels afterwards. The respondents relied upon a quotation from JMB Plumbing dated 17 March 2016 which quoted a sum of $13,187.90 (inclusive of GST) to repair "roofing sheets around solar system". The quote stated that roofing sheets need replacing: That have been dinted durning (sic) installation of solar system. As all dings are in direct area of solar, appears that no care was taken to stop sheets from being dinted The quote also stated that the solar system will need to be removed to "replace sheets at additional charge". 1. Mr Ingersol gave evidence that he had installed the solar system and claimed that the roof was already damaged; 2. Mr Ingersol's evidence was that the respondents had signed an acknowledgement that the roof was damaged before installation. He acknowledged a couple of dents before he commenced work and he acknowledged that he had put some dents in the roof during installation. He gave evidence that he had been told by another business, East Coast Roofing, that the roof could be repaired by placing profile caps over the dents; 3. The Decision found that the respondents' evidence was "by and large supported by the photographs, the pre-purchase report and the quote from JMB Plumbing"; 4. The Decision found that the quote from JMB Plumbing did not comply with the directions issued by the President of the Tribunal concerning tendering expert evidence but that fact did not make the report inadmissible. Rather, it was a question of how much weight should be given to it; 5. The Decision found that the evidence from JMB Plumbing came from a licenced plumber and was the best evidence submitted by either party. The Tribunal accepted that evidence; 6. The Decision found that Mr Ingersol was an electrician and not qualified to express some of the opinions he did; 7. The Decision found that the use of profile caps would not be an appropriate method of repair given that the Tribunal was satisfied that there were 36 dents on the roof; 8. The Decision found that the appellant's services had not been provided with due care and skill and were in breach of the consumer guarantee contained in the Australian Consumer Law (ACL); 9. The Decision found that the acknowledgment signed by one of the respondents that the roof was already damaged did not preclude their claim; 10. The respondents were entitled to compensation for the reasonable costs for the repair of the roof which the Tribunal found to be the replacement of that part of the roof that was damaged in accordance with the quote from JMB Plumbing; and 11. The Decision calculated the damage by reference to the JMB Plumbing quote less 30% being an amount conceded by the respondents having regard to the age of the roof. Accordingly, the order made by the Tribunal was that the respondents were entitled to compensation in the sum of $9,231.53.