Owners Corporation SP 4670 v Con Korakis t/as Mihcon Building
[2015] NSWCATCD 44
At a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2015-03-23
Source
Original judgment source is linked above.
Judgment (11 paragraphs)
INTRODUCTION
- This application was filed in the Tribunal on 16 January 2014 seeking orders for compensation in the sum of $493,518.00 in respect of allegedly defective residential building work. Initially the application named a number of individual lot owners as additional applicants but those parties later withdrew without any issue of costs being raised.
- The matter proceeded to a number of directions hearings and a conclave of experts was conducted with the assistance of a Tribunal Member on 13 May 2014.
- As a result of that conclave there was agreement by the parties in relation to the nature and extent of the defects in the waterproofing and the agreed scope of necessary remedial work. It was also agreed that the total cost of remediation was $297,334.00 plus GST, being $327,067.40 in all.
- However, it was not agreed that the respondent was liable for all of the cost of remediation.
- Hence, when the matter came on for hearing on 23 March 2015 the issue for determination was whether the respondent was liable for all the cost of remedial work or for a lesser sum based on the defence raised.
- It was agreed that if the Tribunal was of the view that the respondent was liable for all of the rectification costs, orders should be made in the applicant's favour in the abovementioned sum.
- However, if the Tribunal was persuaded that there was merit in the respondent's defence it would be necessary to determine the proportion of the whole sum for which the respondent was liable.
- At the hearing there was some difficulty with the expert evidence in that the respondent's expert had not previously seen the second report prepared by the applicant's expert (going to the issue of dividing the remedial work) and the respondent's expert was unavailable for the second day of the hearing. Further, the experts were unable to progress their discussions directed at arriving at some common ground. These difficulties raised concerns that the matter would take much longer than the time allocated and in any event would not be able to be completed in the two days allocated for hearing.