50142/03 Oil Drilling & Exploration (Borneo) Pty Limited & Anor v Nerdlihc Company Inc & Anor
JUDGMENT
The state of these proceedings
Assessment of damages
1 These proceedings are presently before the Court for the assessment of damages.
2 The short position is that:
· this proceeding was commenced in this Court by summons, filed in the Commercial List, on 15 October 2003. The defendants filed an appearance on 20 November 2003. An amended summons was filed on 23 December 2003;
· there followed a series of defaults by the defendants in relation to complying with orders of this Court as to conduct of the matter. In particular, no defence was filed;
· eventually the plaintiffs moved for judgment to be entered against the defendants on two bases: that the defendants had breached three court orders, and for want of prosecution by way of defence;
· this motion was heard by Justice Bergin on 28 May 2004. The defendants were represented at the hearing of the motion, but filed no evidence. Bergin J noted that the defendants' representative had indicated "firstly, that he has been in a position to obtain instructions and, secondly, that he has none". In the result on 28 May 2004, her Honour entered judgment for the plaintiffs as against the defendants, with damages to be assessed, and with the defendants ordered to pay the costs of the proceedings (including of the motion);
· some three months later, on 20 August 2004, the defendants filed a motion seeking that the "default judgment" be overturned and that the amended summons be struck out. That motion was heard by McDougall J on 24 September 2004. The only material evidence relied upon by the defendants was hearsay evidence that Mr Knowlton had desired to settle the litigation (see judgment of McDougall J at para 16). His Honour dismissed the motion.
The evidence before the Court
3 The plaintiffs rely on affidavits of Mr Kenneth John Picard, the current chief executive officer of the second plaintiff and a director of the first plaintiff [7 July 2004 and 1 April 2005 paragraphs 5, 6, 7], and of Mr Kenneth John Skirka, the former managing director of the second plaintiff and a director of the first plaintiff [7 July 2004]. The defendants, who continue to appear in this matter through their legal representative, have filed no evidence, and have indicated that Messrs Picard and Skirka are not required for cross-examination. A complaint advanced in terms of late service of affidavits on and after 1 April 2005 was withdrawn when the plaintiffs limited the new material to paragraphs 5, 6 and 7 of Mr Picard's affidavit of 1 April 2005.
Background
4 The plaintiffs have addressed detailed submissions to the Court in relation to each parameter of the material background and in relation to the orders which are sought. These submissions are accepted in their entirety, subject to certain matters to be referred to below, in particular concerning damages for loss of chance, and are generally, subject to that matter, adopted in what follows.
5 The proceedings concern a dispute about non-payment for extended hire and use of a large oil drilling rig in Western Australia. The first plaintiff owns and operates the rig, known as "Rig 16". The first plaintiff is a wholly owned subsidiary of the second plaintiff.
6 On 22 September 2000 the first plaintiff entered into a contract (at KJP1) with the first defendant ("Nerdlihc") whereby it agreed to provide the use of Rig 16, and associated personnel to operate it, to Nerdlihc to carry out certain "operations". Those operations were the drilling of at least one exploratory oil well at a site in Western Australia called "Patience #2", with options for also drilling wells at two other sites (see KJP1 at "Exhibit A", which is attached to the contract).
7 The first plaintiff moved the rig to the Patience #2 site and commenced operations in September 2000 (Picard para 8). The drilling operations continued until late February 2001, at which point Nerdlihc claimed that the force majeure clause in the contract should come into operation because it had been unable to obtain certain equipment. The first plaintiff accepted that the clause could apply, and went into standby operations, as provided for in the contract (summarized in Picard paras 9-12). The force majeure clause gave either party the right to terminate if it applied (KJP1, cl.17.5). Neither party sought to do so. The contract provided that certain lower rates applied for use of the rig during such operations (KJP1, Exhibit A, cl.13(c)). Those rates reflected the fact that personnel were still required to man the rig to keep it in proper condition, even though it was not actually being used (see cl.13, ibid).
8 Rig 16 was thereafter kept at the Patience #2 site, at Nerdlihc's request, for an extended period. However, Nerdlihc ceased making payments on the regular invoices issued by the first plaintiff after 29 January 2001 (Picard paras 8, 42-194). One payment of US$100,000.00 was made by Nerdlihc on 6 June 2003 (Picard para 31). Otherwise, the regular ongoing invoices of the first plaintiff were not paid.
9 The failure of Nerdlihc to pay for the continuing use of Rig 16 led to ongoing discussions between the parties. The first plaintiff was concerned to obtain the monies owed to it for use of the rig. It also wanted to know whether there was any real chance of payment being made - because if there was not, the rig could have been used elsewhere, or at least put into storage, which is cheaper than maintaining a rig in standby readiness on-site (see Picard paras 205-9).
10 In the period 8 February 2001 through to 21 November 2003 Nerdlihc, through its sole director and shareholder Mr Knowlton (the second defendant - see Am summons para 4), made a series of representations by telephone, facsimile and in person to the first plaintiff. The gravamen of these representations was that the first plaintiff would be paid by Nerdlihc for the accumulating amounts that were owing, that Nerdlihc did wish to continue to engage the services of the first plaintiff in providing Rig 16 and the associated personnel, and that Nerdlihc either had or imminently would have monies available to pay the amounts owing.
11 Such representations were made on approximately 29 occasions over the period (these representations are set out in the amended summons at paras 34-62; and see Picard paras 13-37, and affidavit of Skirka, and documents referred to in those affidavits). The claims were never made good. It may be inferred they were not capable of being made good.
12 Apart from these representations, further agreements were entered into in order to seek to resolve the situation,. First, on 10 February 2003 the first plaintiff and Nerdlihc entered what has been labelled the "February 2003 Letter Agreement" (see amended summons paras 13-16; Picard paras 23-26, and KJP12), which sought to resolve the outstanding payments on the basis that Nerdlihc would pay the first plaintiff the amount of US$3.5m. This amount was never paid, as the defendants accept (subs para 9). It may be noted that although this was signed on behalf of the second plaintiff, it appears from all the circumstances that the second plaintiff was entering the contract as agent for the first plaintiff, as the defendants here also indicate (subs para 10).
13 At the same time a new drilling contract (the "February 2003 Drilling Contract") was to be entered by the first plaintiff and Nerdlihc (KJP13). This was in substantially the same terms as the original drilling contract, except that it provided that the first plaintiff would charge higher rates (see Picard para 25, and KJP 13 "Schedule of Rates). In fact it appears that whilst this was signed on behalf of Nerdlihc, it was not executed on behalf of the first plaintiff (see KJP 13, execution page at p.21). As discussed below nothing turns on this. In practice, the first plaintiff continued issuing invoices at the lower rates set out in the original drilling contract (Picard para 25).
14 A further attempt to settle the outstanding payments was made in June 2003. This was contained in what has been labelled the "June 2003 Letter Agreement" (Am Summons paras 22-28; Picard paras 27-37; KJP 15 and 16). This provided that Nerdlihc would pay US$3.2m for the outstanding invoices, in instalments up to 1 September 2003, with the first amount of US$1.0m to be paid by 10 June 2003. US$100,000.00 of this was paid on 6 June 2003, but the remainder was not (Picard paras 31-37). This was despite Mr Knowlton sending a facsimile to the first plaintiff indicating that US$2.0m had actually been paid into the first plaintiff's account (Picard para 36, KJP 22). In fact, that money was never transferred. The defendants here do not dispute that the total amount due under the June 2003 Letter Agreement was not paid (subs p.3, para 9).
15 Again, a new drilling contract was discussed between the parties at this time (the "June 2003 Drilling Contract" - Am Summons paras 29-33; see KJP 17). Again, this appears to have been signed on behalf of Nerdlihc, though not on behalf of the first plaintiff, although note clause 4 of the June 2003 Letter Agreement. In any event, once again it was in much the same terms as the original drilling contract, except that again it provided for higher rates (Picard para 30). Once more, the first plaintiff continued to issue invoices at the lower rates applicable under the original drilling contract (ibid).
16 The drilling contract was terminated by the first plaintiff by letter of 5 November 2003, and steps to transfer Rig 16 were implemented on 21 November 2003 (Picard paras 38-9; KJP 23).