Proud Nominees' and Mr Proud's grounds for making the representations as to future matters
6 I had summarised the basis on which Proud Nominees and Mr Proud contended that they had reasonable grounds for making the representations as to further matters in an interlocutory ruling in respect of s 51A that I made during the trial: North East Equity Pty Ltd v Proud Nominees Pty Ltd [2007] FCA 1587 at [22]-[24]. In essence their contentions for them having such reasonable grounds were:
"(1) Mr Proud's statement of his education and training.
(2) Previous dealings between Proud Machinery and Mr Proud on the one hand, and North East Equity and Mr Tana on the other.
(3) Mr Proud's knowledge of previous grading facilities at North East Equity's Sumich operation.
(4) Mr Proud's knowledge and experience of a Bruynooghe system installed at the Kalfresh plant in Queensland.
(5) Mr Proud's dealings with the Bruynooghe factory in Belgium.
(6) Mr Proud's knowledge of the equipment at Sumich to be incorporated in the new production line.
(7) Mr Proud's activities as agent for Bruynooghe and another manufacturer of packaging equipment used in the new production line, Gillenkirch, and his knowledge of the capacities of the equipment supplied by each of those manufacturers.
(8) Matter disclosed in the two letters said to contain the representations sued on, namely, his and Proud Machinery's letters of 29 July 2002 and 30 September 2002.
(9) The respondents also rely on the contents of one paragraph in Mr Tana's evidence in which he said:
'I agree that these machines may have this capacity in isolation, however when incorporated into a complex system they are not necessarily able to run at these capacities all of the time. The key to the actual operating capacity of each machine in the new line is the feed to it. The maximum design capacity is irrelevant unless the line can provide sufficient feed to the machine.'
(10) Lastly, the respondents relied on the responsive statement of an expert called by the North East Equity, Mr David Harris, in the sense that he was asked to review Mr Proud's statement, and to 'provide any comment that he may have as to the matters raised'."
7 After hearing all the evidence and submissions, I was satisfied that Mr Proud had a sufficient and sound knowledge of the configuration, workings and general operation of North East Equity's grading facilities (the old line) existing at the time at which the representations were made, and of the operation of the Bruynooghe system installed at the Kalfresh plant. I was also satisfied that Mr Proud had extensive practical experience, built up over many years, from the time he was working towards qualifying for his diploma of mechanical engineering that he was awarded in 1970. He had experience in the early to mid 1970s as first, a fitter and turner and, later as a line manager before becoming involved in selling cars from 1976 to 1995. Since 1996 he had been the managing director of Proud Machinery.
8 I found Mr Proud was experienced in how production plants in the food processing industry operated (my principal reasons [2008] FCA 1189 [79]). He had done many courses including with Newtec, Gillenkirch and Bruynooghe to familiarise himself with his suppliers' equipment, and the operation of fruit and vegetable washing, grading and packing equipment and plants, including sophisticated ones of the kind he was discussing with Mr Tana. He had supplied a considerable number of machines, equipment and plants in the six years before the representations were made. This included supplying, over a period, 10 items of equipment to North East Equity that were used in the old line. He was, as I found, familiar with how Mr Tana and Mr Webster proposed to operate the new line with a split shift and why that was to be done: my principal reasons [2008] FCA 1189 [31]-[38].
9 I found that a number of the representations that were made did not correspond to the pleaded case of North East Equity. That was because I found that each of those was qualified by an implication that the new line would be reasonably fit for the purpose that North East Equity had specified, in an unqualified way, in its pleaded representations. Thus, those pleaded representations were not proved and needed no consideration under s 51A. I did consider the factual questions relating to whether the new line was deficient in those respects, lest my findings were incorrect. But, no issue under s 51A arose, on the pleadings, because I had found that those pleaded representations were not made.
10 The Full Court upheld my findings as to the actual representations that I found were made. I considered then, and now, that no issue under s 51A could arise on the pleaded case in respect of those representations because the unqualified representations pleaded by North East Equity were not made by the respondents. I also considered that the claim under s 51A was hopeless on my findings because the new line performed (or was not shown not to have performed) to the standard of the representations I had found.
11 I considered each relevant representation in my principal reasons: [2008] FCA 1189 at [345]. For ease of comprehension of these reasons I will repeat that paragraph below and analyse the representations as to future matters by reference to the five categories identified in that paragraph. I will then explain why Proud Nominees and Mr Proud had adduced evidence to the contrary for the purposes of s 51A(2) so that they were not deemed not to have reasonable grounds for making the representations as to future matters. The onus of proof then shifted to North East Equity to establish that Proud Nominees and Mr Proud did not have reasonable grounds for each such representation, as the Full Court confirmed: [2010] FCAFC 60 at [35]. In my principal reasons ([2008] FCA 1189 at [345]) I said:
"[345] I summarise below the contractual terms and representations which I have found Proud Machinery made to North East Equity and my findings on them. In analysing whether the new line, as installed, conformed with the purposes and terms referred to in 66-(e) above, I have had regard to the implication that the new line would be reasonably fit for those purposes (Helicopter Sales 132 CLR at 4, 6, 8, 15: see [64]-[66] above).
(1) Pack out rate per hour
I have not found that terms or representations were made exactly corresponding to those pleaded and set out at 66 and 67 above. Rather I have found (at [87] above) that, at the time of entry into the contract, the processing capacity was contained in a term and representation that:
the new line would have the capacity to process and pack at a rate of production per operating hour of 18.75 tonnes final pack out on the pallet (later reduced to 17.55 tonnes).
For the reasons given above, I am not satisfied that this was incorrect or misleading or deceptive. The new line had that capacity. And, by operating a split shift, the new line had the capacity to achieve a pack out in excess of 150 or, later (after the handline was deleted), 140.4 tonnes in eight working hours.
(2) Temperature
I have found that terms and representations were made which corresponded to those pleaded and set out at 66, (c) and 67 and 102 and (v), namely that the new line would, first, be designed so as to be reasonably fit to achieve:
(b) the ability to process farm fresh carrots at field temperatures;
(c) the core temperature of packed carrots to be not more than 5°C;
and secondly,
(h) achieve a guaranteed maximum of 5°C core temperature for North East Equity's carrots;
(iii) have hydro-cooling tanks capable of producing constant product output; and
(v) be capable of controlling the temperature of the carrots.
I have found that I am not satisfied that the new line did not have these capacities if operated correctly.
(3) Grading
I have found terms and representations were made that corresponded to those pleaded and set out at 66 and [102] (ii) and (iv), namely that the new line would, first, be designed so as to be reasonably fit to achieve:
(d) the ability to sort and grade carrots into eight distinct streams of size and length grades;
and secondly,
(ii) have nine hydro-cooling tanks which would allow one of those tanks for each length or size grade and provide the opportunity to have a spare tank; and
(iv) provide quality length sizing for three separate lengths.
I have found that I am not satisfied that the length graders (there being no complaint about the width or girth graders) were not reasonably fit for the purpose of providing quality length sizing in accordance with what both parties understood were their inherent limitations. I am not satisfied that the new line was not reasonably fit for the purpose of having the ability to sort and grade carrots into eight different streams of length and size. I am satisfied that the hydro cooling tanks conformed with representation (ii).
(4) Efficiency
I have found that terms and representations were made that corresponded to those pleaded and set out at 66 and 102, namely that the new line would first, be designed so as to be reasonably fit to:
(e) achieve an increase in efficiency of labour usage compared to the existing Sumich line;
and secondly,
(vii) increase production while reducing the man hours required to achieve that production compared to the existing at the Wattleup plant line.
I am satisfied that these were correct. As Mr Tana admitted in the meeting of 18 November 2003, labour costs per carton had reduced by 25% or more.
(5) Reduction in damage to carrots
I have found that a representation was made that corresponded to that pleaded and set out in 102 namely that the new line would greatly reduce damage to carrots and wastage.
I am not satisfied that this was incorrect, misleading or deceptive. In any event there were no records of waste or damage to carrots so as to enable any finding to be made as to the position before or after the new line was installed. And, the quality of carrots delivered for processing after the new line was installed was very different from, and worse than, their earlier quality. North East Equity has not established that this representation was not met."