This was an internal costing that was not shown to the respondents until much later.
40 There was a meeting attended by the Vos and Mr Nikolic in which the proposed amendments were negotiated in detail (see Blue 26-29) and recorded by Ms Habibeh making notes to a copy of the 25 May floor plan (Blue 92, 393).
41 As the parties moved towards contractual commitment on those lines there were elements of trust each way. The primary judge held that the appellants were experienced in both design and construction, thereby likely to adopt a robust approach to contracting and costing (Red 63). Her Honour also found (Red 69) that Mr and Mrs Vo accepted on trust Mr Damien Nikolic's costings and (as regards the matters excluded from the original 34 items) a contract price set on a formula with a variable (the price of the deductions) known only to the appellants. The judge observed:
The defendants make no complaint about that. In these proceedings, they stand behind that decision and accept the plaintiffs' costings on their face.
42 These findings based upon her Honour's observation of the parties in the witness box are relevant to the probabilities that the parties would have contracted as they were found to have done, both as regards their several subjective intents and as regards the impression that their conduct during the negotiation stage is likely to have engendered in the other party.
43 Ms Habibeh was instructed to make a long list of adjustments to meet the budget estimate of $690,000 (Blue 385-7). The details are summarised at Red 65-6. During this period Mr Mangila also made a free hand sketch (Blue 396, Red 55Q).
44 The fact that certain items of work nominated in the Quotation were removed by agreement prior to the payment of the deposit is attested to by: Mr Vo's evidence (accepted by the judge); the annotations on the Quotation; Ms Habibeh's annotations on the 25 May floor plan; the evidence of Ms Habibeh and Mr Mangila about the instructions they received from Mr Nikolic on about 3 June 1999 for particular deletions to the previously discussed works; and the substantial correspondence between the agreed deletions and the credits later allowed by the appellants (see Red 67N-T).
45 On about 4 June, Mr and Mrs Vo went to the Marconi Club where, at the request of Mr Nikolic, they inspected the quality of the finish of a comparable job. Mr Nikolic had told them:
Trust me. I am putting my reputation to this project and it will be an example of the quality for my business, something to be proud about. You should go to the Marconi Club where I finished renovations for the club.
46 This evidence was used to support a submission that there was a term in the contract regarding the quality of finishes. The effect of such a term was that they would be comparable to those at the Marconi Club.
47 The appellants now submit that the "Marconi Term" was so vague as to be meaningless (Orange 27-8). I do not agree, especially because the term (if such it was) related to no more than the general quality of finishes. This submission also has a self-defeating aspect in that an agreement void for uncertainty would expose the appellants to the perils of a restitutionary claim that are discussed below. I say "if such it was" in recognition of the appellants' submission that neither party is said to have put their case before the trial judge on the basis that the "Marconi Term" was a term of any agreement. If it was a term, I see no problem from an incompleteness or uncertainty point of view. If it was not, the terms that remained were sufficient to constitute an enforceable contract for reasons that I explain below.
48 On 6 June 1999 employees of the appellants created a document that costed, item by item, the 34 items of work shown on page 1 of the Quotation. These assigned a value to each item (eg "5. New screen walls $14,000.00"). There was a 35th item ("Design fees $30,000") which, when added to the 34, brought the total cost to $690,000. This was an internal working document of the appellants which was first shown to the respondents in typewritten form as an attachment to the second version of the appellants' invoice/statement dated 17 November 1999 delivered after the job was finished (see below).
49 This 6 June 1999 document formed no part of the pre-contractual communications between the parties. It is, however, significant because it shows that as early as 6 June 1999 the appellants understood enough about the work which was the subject matter of the Quotation to be able to cost it, item by item. In addition, it supports the probabilities that the appellants may have conveyed to Mr and Mrs Vo in some manner now forgotten their sense of confidence that the deleted items from the Quotation had a reasonable cost capable of ready ascertainment by a trusted contracting party. In my view, this undercuts the appellants' argument that their own understanding of the contract works was so incomplete by 7 June 1999 as to make it improbable that they would have entered into a fixed price contract by that stage. I also observe that the Quotation included items for "new … walls", one of the matters that the appellants now say were only clarified later in June.
50 Judge Gibb found that the parties collectively attended to the fleshing out of the content of the contractual works around this time (Red 63T). She also found that the content of the works was settled by the parties by reference to the amended list in the Quotation with the Marconi Club work being accepted as the standard for form and quality (Red 70-1). In my view, these conclusions were correct having regard to the 6 June document and the evidence that the parties considered themselves in a position to conclude the deal by 7 June (possibly 9 June, in the alternative) in the following circumstances.
51 On 7 June 1999 the respondents paid a deposit of $60,000, half by cheque and half in cash. The cash payment is acknowledged by a receipt signed by Mr Damien Nikolic. The judge found that this occurred after what she described as the defendants' counter offer raised in the course of discussion had been accepted by the plaintiffs (Red 71M). This finding involved acceptance of Mr Vo's evidence that there was the following conversation:
Damien Nikolic said: 'The cost includes the design work and management fee. I am saving you money. If you want me to do the job you must give me a deposit of $60,000. To do the job quickly I need cash payments'.
I said: "I want you to do the job at a cost of $690,000 less deductions for those items of work that are not included."
Damien Nikolic said: "I agree. I will start on the plans and drawings straightaway."
52 The primary judge held that "the contract was settled by 7 June" (Red 73). Specifically, she found (Red 71):
I do find that Mr Damien Nikolic's three-page document had some contractual force. I find that it was a contractual quotation which, amended by the deletion of certain items, took the form of a counteroffer by the defendants, which was accepted by the plaintiffs, in the context of some oral agreements as to price. The oral agreement as to price included an agreement upon the contract price by way of a formula, relevantly "$690,000 less a variable (the price of the deductions)," which was a variable known only to the plaintiffs. There was a further oral component by way of agreement that there would be agreement as to variations.
53 There were nevertheless "numerous details to be settled" (Red 73). And, as often occurs, the clients closely monitored the work as it progressed, sometimes requesting changes of such materiality that there were admitted variations to the original contract.
54 Ms Habibeh undertook site measurement and inspection, spending seven hours on the project on 7 June 1999. She produced a drawing of the existing structure on 8 June 1999 (Blue 747, Red 55). As the judge observed (Red 73), this was not something that occurred casually. Indeed, Ms Habibeh had agreed in cross-examination that she went back to the site to measure it in a detailed way "after they agreed".
55 The appellants sub-contracted the construction work (on a do and charge basis) to Mr Spiteri through his company. He was initially engaged on 8 June (Red 77).
56 A lengthy meeting took place on 9 June attended by Mr and Mrs Vo, Mr Vo's sister and the appellants' two designers. During this meeting the Vos selected the carpet, tiles and marble effect paint from samples shown by Ms Habibeh. The judge held that it was on this occasion that Ms Habibeh made extensive notes on the 25 May floor plan, concluding that they "relevantly fleshed out some details" and "relevantly confirm[ed] with some precision that which Mr Vo recalls discussing with Ms Habibeh" (Red 74). Her Honour rejected evidence from Ms Habibeh that she flagged on that occasion that the matters under discussion were going to take the cost up to a million dollars (Red 74-5).
57 Senior counsel for the appellants would prefer to view this event as evidence that the definition of the contract work was so uncertain and/or fluid on 7 June to indicate that the parties cannot be taken to have reached a contract on 7 June, indeed even on 9 June. He nevertheless frankly conceded the possibility of a finding that the contract was formed on the later date while maintaining his submission that the price component was a "do and charge" basis. A third possibility is that a contract was formed on the earlier date and varied two days later.
58 None of these scenarios assist the appellants if (as the judge held) nothing was said on or before 9 June to flag the anticipated cost overrun. Each scenario involves a contract being concluded (as pleaded, apart from the date) with the striking of the bargain being evidenced by payment of a substantial deposit, by the appellants' designers promptly completing design work, execution of the demolition contract on 10 June, performance of that demolition contract by 1 July and thereafter (between 1 July and 4 September 1999) the performance of the works by the builders associated with the appellants. As will appear, the accounts submitted by the appellants in November 1999 also embody significant admissions to similar effect.
59 Ms Habibeh had no authority to make a contract on behalf of the appellants (see also Blue 389H). I see nothing improbable in Mr Nikolic allowing her to discuss design in detail two days after the fixed price contract was reached. Having regard to the way in which the parties joined issue, it was the appellants who needed to advance evidence showing that this conduct was inconsistent with an existing commitment to do the generally outlined work for a fixed price (less the reasonable cost of items deleted from the Quotation).
60 The appellants' case at trial and in this Court seldom rose beyond asserting that the contract said to have been formed was nevertheless so vague regarding scope of works as to lead to an implied term that the company would pay the reasonable cost of work on a do and charge basis.
61 On 10 June the parties signed a separate quotation document providing for demolition work to be done for $16,000. This relevantly stated (emphasis added):
Demolition work as required by the design
Please Note: If this is accepted please sign and fax to me urgently so that we can commence works on the 9 June 1999 .