The Tribunal's decision on the major disturbance issue
17 Ngan Aak-Kunch's first ground of review (at [9] above) challenged the Tribunal's assessment of the extent of the disturbance that was likely to occur to the area concerned under s 237 of the NTA. In this respect, it should be noted that this proceeding is confined to the major disturbance criterion expressed in s 237(c) (see at [5] above). Thus the criteria prescribed by ss 237(a) and (b) are not presently in issue. On this major disturbance issue, Ngan Aak-Kunch specifically identified two paragraphs of the Tribunal's decision ([114] and [118]), as follows:
[114] I accept that should the State proceed to grant [the proposed licence] to Glencore, the grant will be subject to the [protection conditions]. At [50], I noted the State's and Glencore's position that any application to have those conditions removed or to expand the authorised activities would trigger a 'native title assessment' resulting in the application of the right to negotiate process.
[118] Finally, I concluded that taking account of the Work Program, the Environmental Authority, the Code of Environmental Compliance, and the results of previous activities, it was not likely that Glencore will engage in activities which involve significant ground disturbance. That conclusion is supported by the contentions of the State and acceptance by Glencore that any form of sampling which might cause major disturbance would not be permitted without requiring another native title process to be followed.
18 Both of these paragraphs appear in the section at the end of the Tribunal's decision where it summarises the main conclusions it had reached earlier. Thus, [114] referred back to, and summarised, its earlier conclusions about the protection conditions (at [50] set out at [15] above). Similarly, [115]-[117] summarised the conclusions the Tribunal had reached about the criteria in ss 237(a) and (b). For example, [117] summarised the conclusion it reached about the criterion in s 237(b) as follows:
While there was information regarding sites within the [proposed licence] area, for example, in the Sites Register and anthropological reports, apart from general descriptions, I concluded at [93] to [98] that sites of particular significance had not been identified - noting that the cultural heritage protective regime and engagement framework of the [protection conditions], coupled with the proponent's obligations under the ACHA and the MRA, would make adverse or unacceptable impact on sites unlikely.
This reflects the Tribunal's conclusions on that criterion at [93]-[98] where, first, it concluded there was insufficient evidence identifying any sites of particular significance such that there was any "real risk of interference" to them (see at [95] and [98]). Secondly, it observed that, even if such sites existed, it was satisfied that there was a "site protection regime in place which would make adverse impact on sites unlikely" (see at [98]).
19 The Tribunal adopted a similar approach with [118]. That paragraph contains a summary of its earlier conclusion at [112] (in almost identical terms) with respect to the criterion in s 237(c), as follows:
Taking account of the Work Program, the Environmental Authority, the Code of Environmental Compliance, and the results of 'previous activities' (including retained drilling samples which can be used to evaluate resources), I am of the view that it is not likely that Glencore will engage in activities which involve significant ground disturbance. I also accept and would find it highly unlikely, based on contentions made by the State, that any form of sampling that might cause major disturbance would be permitted without requiring another native title process to be followed.
20 This conclusion reflects the Tribunal's consideration of that criterion at [99]-[111] of its decision. That section of the Tribunal's decision begins at [99] with a description of the case Ngan Aak-Kunch advanced before the Tribunal on this issue. Its case was that, in determining whether a major disturbance to the area concerned was likely to occur, the "full scope of rights permitted" under the proposed licence should be considered. Adopting that approach, it contended that it was likely that Glencore would carry out activities that exceeded the scope of its Work Program. In particular, it contended that there was a likelihood that Glencore would wish to conduct bulk sampling on the site in the later years that the proposed licence was in effect and, if it did, that activity would be unconstrained by the protection conditions (see [2016] NNTTA 22 at [99]). Finally, it again raised the discretion which the Minister had to vary the protection conditions (see its contentions at [13] above).
21 In considering these contentions, the Tribunal first looked at whether the activities to be undertaken on the site under the proposed licence would involve bulk sampling. After noting that Glencore's Work Program did not refer to such sampling, it recorded a submission from Ngan Aak-Kunch, consistent with its contentions above, to the effect that (at [101]):
… 'given the considerable work already undertaken with respect to the resource located within [the proposed licence], and the potential 10 year life of the tenement, it is reasonable to predict that some form of bulk sampling will occur within the area of [the proposed licence] in conjunction with considerable infrastructure work as [Glencore] moves to establish the development potential of the Aurukun project and validate its business case' …
22 The Tribunal then recorded Glencore's response that it "did not propose to undertake any bulk sampling"; and it "has always understood the [proposed licence] activities it sought were exploratory and no bulk sampling would be approved" (see at [101]). It also recorded the State's position that it the proposed licence "would be conditional upon compliance with the approved Work Program, which does not provide for any bulk sampling or 'considerable infrastructure work', and that carrying out either of those, in the absence of an application for variation, would be a breach of the licence". On this latter aspect, the State again addressed the question whether the proposed licence could be varied to remove the protection conditions without it following the right to negotiate process in Subdivision P. On that matter, the Tribunal recorded the State's contention that (at [102]):
… '[it] should conduct its predictive assessment on the basis that the conditions of the [proposed licence] will not allow [Glencore] to engage in activities which involve significant ground disturbance (including bulk sampling or considerable infrastructure work) without an application from [Glencore] to vary those conditions and that such an application would trigger a new native title process …'
23 These contentions were considered by the Tribunal later in its reasons on two alternative bases: if the protection conditions applied; and if they did not apply. With respect to the former basis, it recorded the State's contention that any major physical disturbance to the land was unlikely if those conditions and the Land Access Code applied (see at [107]). On the latter basis, it recorded the State's contention that, even if the protection conditions did not apply, the limited nature of Glencore's Work Program, including the rehabilitation and mitigation measures to be undertaken under it, and the non-inclusion of any bulk sampling or considerable infrastructure work, meant that there would be no major disturbance under s 237(c) (see at [108]).
24 In determining whether any major disturbance was likely to occur on the area concerned, the Tribunal also referred to Glencore's contentions about the effect of the State's regulatory regime, including the Environmental Authority and the Code of Environmental Compliance, and then examined the nature and effect of the constraints imposed under both of those regimes (at [103]-[105]). In this respect it is important to note that, earlier in its decision, when considering whether Glencore's activities under the proposed licence would be likely to interfere with any sites of significance in the area concerned under s 237(b), the Tribunal conducted a detailed examination of the "intended activities and the nature of the licence" (see [2016] NNTTA 22 at [76]-[92]). In the course of that examination, the Tribunal considered, among other things, the apposite provisions of the MR (Qld) Act (at [77]-[81]); Glencore's Work Program, including the sampling and drilling work that was likely to be required (at [82]-[84] and [88]-[90]); the construction activities that were likely to be conducted upon the site (at [85]-[87]); and the operation of the State's Land Access Code (at [92]).
25 Returning to its consideration of the major disturbance criterion in s 237(c), the Tribunal also recorded the contentions made by both Glencore and the State that the activities under the proposed licence would be limited because of the extent of the previous activities undertaken on the area in question. In this respect, the Tribunal noted the State's contention that "significant work, including drilling and sample collection, has been undertaken for the bauxite deposit by previous tenement holders … [and that there were] extensive drilling samples from previous works, which can be used to evaluate resources for present purposes without the need to collect any more samples" (see at [106]).
26 Finally, before coming to its conclusion at [112] (set out at [19] above), the Tribunal identified the assessment task it was required to undertake (see at [109]-[111]) citing the Full Court's judgment in Little v Oriole Resources Pty Ltd (2005) 146 FCR 576; [2005] FCAFC 243 (Little) at [51]-[54]. In particular, it noted that it was required to assess whether the "future act is likely to involve, or create rights whose exercise are likely to involve, major disturbance to the land and waters must be evaluated by reference to what is likely to be done, rather than what could be done" (see at [109]); and that it was entitled to have regard to "the history of mining and exploration in the area, the characteristics of the land and waters concerned and any relevant regulatory regime" (see at [111]).