Inground latent conditions
6The first item in dispute related to "inground latent conditions". That was the subject of a provisional sum allowance in the contract. Clarendon said that it was required to remove certain asbestos, that its removal was necessary, that it was a latent condition, and thus that it was entitled to a payment out against the provisional sum allowance.
7The issue before the adjudicator appears to have been whether or not this was a latent condition covered by the provisional sum allowance. The adjudicator dealt with this argument relatively briefly. He said at [133] that he was "in no doubt that this work is covered by the relevant provisional sum item..." in the contract.
8He expanded on that in the following paragraph, [134]. He said that the superintendent's representative had agreed, in an assessment made by him, that Clarendon was entitled to be paid for asbestos removal on the "latent condition" basis. That followed, the adjudicator said, because the superintendent had assessed the claim in a particular way, to which he referred. He noted that the Corporation had paid the claim so assessed.
9Mr Christie of Senior Counsel, who appeared with Ms Culkoff of Counsel for the Corporation, submitted that there was a want of reasoning shown. He relied on a number of decisions on this point, including my own decision in Bauen Constructions v Westwood Interiors [2010] NSWSC 1359 at [22] to [24] and again at [40] to [42]. Since it appeared to be accepted that I had stated the relevant approach correctly in those paragraphs, and the debate before me proceeded on that basis, I shall relieve myself of the necessity of restating what I there said by setting out those paragraphs in these reasons:
[22] Adjudicators are required, by s 22(3)(b) of the Act, to give the reasons for their determination unless the parties have dispensed them from doing so. That engages the problem of sufficiency of reasons. In the context of the courts, that question was considered by Hayne J (with whom McHugh and Gummow JJ agreed) in Waterways Authority v Fitzgibbons (2005) 79 ALJR 1816. His Honour said at [129] that reference to the sufficiency of reasons may give rise to "some doubt about what principles are engaged". At [130], his Honour explained one of those principles as follows:
... because the primary judge was bound to state the reasons for arriving at the decision reached, the reasons actually stated are to be understood as recording the steps that were in fact taken in arriving at that result.
[23] Although adjudicators work under significantly greater time pressures than judges, and their reasons should not be scrutinised with the attention to detail to which the reasons of trial judges and intermediate appellate courts are subjected in ultimate courts of appeal, nonetheless the reasons must indicate why it was that the adjudicator arrived at the determination given in accordance with s 22(1). Just as there is with judges, so too with adjudicators there is a presumption that the stated reasons are all of the reasons for coming to the conclusion expressed.
[24] Of concern in Waterways Authority v Fitzgibbons was the primary judge's acceptance of the evidence of one medical practitioner over that of others. It appears from what Hayne J said at [131] that the trial judge concluded that the evidence of a particular practitioner should be accepted and preferred "but disclosed no reasoning supporting that conclusion". As his Honour said at the end of the same paragraph, "[t]he absence of explanation for, and reasoning and support of, the conclusion expressed ... reveals that the process of fact finding miscarried".
...
[40] In this case, para 11 of the determination gives no intellectual justification for the decision that was made. It does not involve any process of consideration or reasoning; it is, in my view, an abdication of the obligation to reason. As Mr Christie of Senior Counsel (who appeared with Mr Shipway of counsel for Bauen) submitted, if para 11 were a sufficient statement of reasons, adjudicators could deal with applications very quickly and their determinations would be very short. Whilst ordinarily one should be wary of "floodgates" arguments, I think that there is substance in that submission. I repeat that it is not appropriate to expect the detail of reasoning from adjudicators that litigants rightly expect from judges of this Court, from judges of equivalent courts, and from judges of intermediate and ultimate appellate courts. But the parties to an adjudication application are still entitled to see some intellectual process that leads to the conclusion, particularly where, in many cases, very substantial sums of money are involved.
[41] In those circumstances, it seems to me, this is again a case of jurisdictional error, because on the face of the reasons, and by application of what was said in Halkat, the adjudicator did not perform his statutory function; and of denial of natural justice.
[42] I should note that Halkat was a decision given when the grounds of review were understood to be as stated in Brodyn Pty Limited v Davenport (2004) 61 NSWLR 421. The position is now somewhat different, having regard to the decision of the Court of Appeal in Chase Oyster Bar v Hamo Industries [2010] NSWCA 190. The changes that flow from the decision in Chase are focused more on the juristic basis on which, and the way in which, the Court grants relief than on the substance of the bases upon which relief is granted.
10As I noted, there must be some statement of an intellectual justification for the decision that was made: some process of reasoning leading to the conclusion stated by the adjudicator.
11In my view, the adjudicator did display a process of reasoning, involving an intellectual exercise, in the paragraphs of the determination to which I have referred. He took it that the superintendent had already looked at the question of whether or not the claim was for a relevant latent condition, and concluded that he had. The adjudicator took it further: that the Corporation had accepted that conclusion, because it had paid for the work in question. Thus, he reasoned, the matter was not properly in dispute before him and he need do no more than rest on what the superintendent had to say and, in the adjudicator's view, the Corporation had accepted.
12I express no view as to whether this process of reasoning was correct or not. I am not concerned with assessing the merits of reasons given, in the sense that I am not required, as if on some form of appeal, to consider whether the adjudicator was right or wrong in the conclusion to which he came. The question is whether he gave a process of reasoning that justified his conclusion that Clarendon had demonstrated an entitlement to be paid on the basis that it claimed. He concluded that it had. He gave reasons for this. In my view, those reasons are sufficient to discharge the obligation to which I referred in Bauen Constructions.
13It follows that this ground of complaint is not made out.