(a) In the case of the NAB cheques, the claim for interest dates from the time of their respective conversions. In round terms that was about three years before the proceeding was commenced. The defendant made no submission that by reason of delay this period should be excluded. I do not consider that it should.
(b) In the case of the TT cheque, the claim for interest dates from the demand in May 1991 - about 18 months before commencement of the proceeding. The same observation applies as in the case of the NAB cheques.
(c) The end date of calculation in each case should be the date of judgment, not the date on which the trial commenced. The plaintiff made calculations to 17 September 1999. That is a convenient end date.
(d) It is very likely that some of the delay which the defendant's counsel identified in his submissions was occasioned by the frequency with which the plaintiff changed its solicitors. According to counsel for the plaintiff, those changes were not attributable to the plaintiff's default; and the defendant should not have the benefit of delay resulting therefrom. Even if the delays so occasioned, or any of them, were not attributable to any intent by the plaintiff to delay its claims, that is what happened; and I think the plaintiff must abide the consequences.
(e) On 16 March 1999, on an application by the plaintiff to amend its statement of claim, Hedigan, J. reviewed the history of the proceeding. He described the delay on the plaintiff's part as lamentable. The delay was, he said, "virtually wholly due to the plaintiff". No allegation had been made for the plaintiff that the defendant had caused any delay. His Honour went into book, line and verse of the delay which he said was attributable to the plaintiff. In the end, His Honour allowed the amendment. It might be said that his characterisation of the plaintiff's conduct was unnecessary to his decision. Assuming that were so, my own analysis of the material leads me to an ultimate conclusion similar to that reached by His Honour.
(f) Counsel for the defendant submitted that there were seven discrete periods of delay by the plaintiff. I will refer to each of them in a moment. Counsel for the plaintiff submitted that the chronology upon which these periods were identified was incomplete. Insofar as there was substance to that submission, I have taken it into account when considering whether the defendant has made out each of the periods of delay which its counsel identified.
(g) Counsel for the plaintiff submitted also that the defendant took no steps to bring the matter on, but itself delayed taking necessary interlocutory steps. He contended that whilst it is not for a defendant to make the running in a proceeding, it was relevant to consider the defendant's conduct in that connection in a dispute about interest. I do not exclude the possibility that this matter could tell against a defendant in some circumstances. But in the present case, any default by the defendant pales into insignificance when contrasted with the default of the plaintiff. In expressing that conclusion I have not forgotten the fact that the bank was itself the plaintiff in the possession claim.
(h) I am satisfied that the plaintiff was responsible for most of the first period of alleged delay - that is, between 26 March and 6 December 1993. I consider, however, that it was reasonable for the plaintiff to consider and decide to join the ANZ as a defendant; and I should allow some time for it to have done so - albeit that joinder was not in fact effected until 1995. I reduce the delay attributable to the plaintiff to 200 days.
(i) I am satisfied that the plaintiff was responsible for most of the second period of alleged delay - that is, between 9 August 1994 and 18 May 1995. In this period, however, the plaintiff needed to give consideration to the possession claim then recently commenced by the defendant. I reduce the delay attributable to the plaintiff to 250 days.
(j) I am satisfied that the plaintiff was responsible for delay between 14 April 1996 and 9 September 1996. Between the latter date and 6 November 1996 the plaintiff did take some action to have the three proceedings then on foot heard together. The application was, it seems, adjourned sine die. But in substance it was not without merit. In due course the three proceedings were heard together. I am not satisfied that there was any delay between 6 November and 24 December 1996, the latter date being the date on which, according to the defendant, the third period of delay ended. I consider, then, that the plaintiff was responsible for delay, in the third period identified by the defendant, amounting to about 150 days.
(k) I am not satisfied that the defendant has made out the fourth period of delay which it alleges - a period commencing 15 January 1997 and ending 11 March 1997. 15 January 1997 is the day, the defendant says, that the plaintiff should have answered interrogatories which it, the defendant, chose to serve on Christmas Eve. In the overall scheme of things any delay in answering the interrogatories was so small as to be insignificant.
(l) The defendant has not made good its claim in respect of the fifth period of alleged delay - between 15 May and 15 July 1997. That period commences a month after NAB filed its amended defence, and concludes a fortnight before a mediation was held. The selection of dates appears to be arbitrary. There is nothing to suggest that the plaintiff delayed in getting the matter on for mediation in 1997.
(m) The defendant has not made good its claim in respect of the sixth period of alleged delay - between 8 August and 2 September 1997. On the latter date, it seems, the proceeding was fixed for trial. That was only about five weeks after the mediation ended. It is difficult to imagine what the plaintiff could have done to speed up that sequence of events.
(n) The defendant has satisfied me that the seventh period of delay - between 18 February 1998 and 2 August 1999, a total of 530 days - was attributable to the default of the plaintiff. It was on the plaintiff's application that on 18 February 1998 the trial date for March 1998 was vacated. The matter was in due course refixed for trial in mid-March 1999. It had to be adjourned at that time when the plaintiff belatedly applied to amend its statement of claim. There could be no fresh hearing until August of this year. The plaintiff's counsel submitted that the defendant's side had not been idle in preparing its case in the period between February 1998 and August 1999. That could be expected to be the case. It provides no reason to excuse the plaintiff for the delay.
(o) In all, the defendant has satisfied me, then, that the plaintiff was responsible for delays amounting to 1,130 days. I consider, in the present case, that it accords with the pertinent provisions of the Act to take that entire period of days into account so as to reduce the interest which I would otherwise give the plaintiff.