4994/09 N A Investments Pty Limited v Perpetual Nominees Limited
JUDGMENT
1 His Honour: This is the hearing of an application to set aside a statutory demand under s 459 G, s 459H and s 459J of the Corporations Act 2001. The demand, which was served by the defendant on the plaintiff, was dated 28 September 2009 and it was in respect of an amount of $7,655,603.93. The description of the debt in the demand was as follows:
"Being the total of the debts owing as at 23 September 2009 in respect of a commercial advance facility provided to Future Fuels Australia Pty Limited (in liquidation) ACN 116 448 143 on the terms and conditions set out in a Facility Agreement dated 3 July 2006, as varied on 11 January 2007 and on 28 June 2007 and amended and restated on 15 October 2008, calculated as follows: …"
2 There were then set out calculations of interest in tabular form giving the amount of claim of being both principal and interest.
Background facts
3 These are helpfully set out in the parties' submissions which I will incorporate with some amendment. It may be necessary to refer in more detail to events referred to in this part of the judgment.
4 In 2005 N A Investments Holdings Pty Ltd ("N A Investments") was the holding company and 100% shareholder of three entities, namely, Future Fuels Australia Pty Ltd ("FFA"), FFA Properties ("FFA Properties") Pty Ltd and FFA Equipment Pty Ltd ("FFA Equipment") (collectively known as "the FFA Group").
5 In August 2005 the FFA Group purchased property and equipment in Moama being a refinery plant which at that time was not a going concern.
6 In June 2006 Perpetual Nominees Limited ("Perpetual"), through its agent MFS Investment Management Limited, agreed to provide a facility of $23M to FFA to fund the continuing development of the bio-diesel plant in Moama. A Facility Agreement was subsequently executed on 3 July 2006. N A Investments, Messrs Nabil and Adil Magar guaranteed the obligations of FFA under the Facility Agreement.
7 After the full $23 M was drawn on the facility two further amendments were made to the Facility Agreement on 11 January 2007 and 28 June 2008.
8 By early 2007 the bio-diesel plant was up and running but FFA was experiencing cash flow difficulties because of the increase in the price of raw materials and the expense of dealing with glycerol, a highly volatile by product of the bio-diesel refinement process.
9 In about March 2007 Adil Magar had a conversation with Tim Martin, Perpetual's representative, in which FFA sought $2 M to $3 M in additional funding from Perpetual. Mr Martin's reply was:
"When we can see that you are producing finished product and resolving the Glycerol issue we can give you the money."
10 There is debate as to what steps were then taken to comply with Perpetual's requirements. In May 2007 a further request was made for additional funding. Mr Martin's reply was:
"OK but we will need more security to raise the funds."
11 FFA offered additional security and there were a number of emails detailing requirements for security.
12 In August 2007 Perpetual declined to lend any further money.
13 FFA and N A Investments then investigated a sale of the business. On 1 November 2007 N A Investments entered into a contract for sale of the business with Jonvana Enterprises Pty Limited, which contemplated the sale of N A Investments' shares in the FFA Group. The purchase price was $41.55 M but also involved Jonvana taking over FFA's debt to Perpetual. This put the price at about $63 M.
14 The sale was delayed a number of times by the purchaser (and in fact has never been fully executed). Notwithstanding this on 18 October 2008 N A Investments, FFA, Perpetual and Jonvana entered into an arrangement the effect of which was to reduce FFA's debt to Perpetual by $20 M with the new purchaser effectively taking over that obligation. As part of that arrangement a new Restated Facility Agreement was executed between FFA and Perpetual. N A Investments was again a party as one of the guarantors. It is in its capacity as a guarantor that the demand has been issued against N A Investments.
Plaintiff's claims
15 The plaintiff seeks to set aside the statutory demand on four different basis which are:
The subject of the statutory demand is a debt which is not recoverable by action,
The statutory demand is a "proceeding" prohibited by the agreement between the parties,
The statutory demand is an abuse of process, and
An offsetting claim rising out of the failure to extend further finance and the consequent sale of the business.
16 The first three of these claims arise out of clause 11.18 of the Restated Facility Agreement which is in these terms:
"11.18 Limitation of liability
(a) The Trustee's liability to pay any amount in accordance with the Finance Documents, may be discharged from, and the recourse of the Trustee is limited to, the FFA Trust Property. The Lender may not seek to recover any shortfall in the amounts owing to it under or in connection with this agreement by bringing proceedings against the Trustee or applying to have the Trustee wound up. This clause applies despite anything in this agreement but subject to clause 11.18 (b) and clause 11.18 (c).
(b) The Mortgagee may:
(1) do anything necessary to enforce its rights in connection with the FFA Trust Property; and
(2) take proceedings to obtain:
(A) an injunction or other order to restrain any breach of this agreement by the Trustee; or
(B) declaratory relief or other similar judgment or order as to the obligations of the Trustee under this agreement.
(c) Clause 11.18 (a) does not apply in respect of the Trustee to the extent of fraud, negligence or wilful breach by the Trustee."
17 In the deed "Trustee" is defined to mean N A Investments. This is because, as is apparent from the deed, that the company, although being the holding company of the three other companies, holds those shares as the trustee of the N A Investments Trust of which it is the trustee.
18 According to N A Investments the commercial rationale to be gleaned from the clause is to limit the liability of the trustee to the assets of the trust, and prevent Perpetual from seeking recourse to the company's other assets. It effectively quarantines the liability. Although Clause 11.18(c) provides an exception enabling Perpetual to sue for negligence, wilful breach or fraud any such cause of action is for damages and is not a debt recoverable by statutory demand.
19 N A Investments emphasises that the clause expressly prohibits Perpetual specifically in relation to N A Investments' obligations under the Restated Facility Agreement, from "bringing proceedings against" N A Investments or applying to have it "wound up".
20 In its submissions N A Investments submitted that the clause is quite clear in its terms, but even in the event of some ambiguity a "doubt as to the status of a provision in a guarantee should ... be resolved in favour of the surety." It referred to Ankar Pty Limited v National Westminster Finance (Aust) Ltd (1987) 70 ALR 641 on this point.
21 N A Investments' construction ignores the initial qualification in the second sentence of the clause. The bringing of proceedings or applying to have the trustee wound up is conditioned by the first part of the sentence to a situation where the lender is seeking "to recover any shortfall in the amounts owing to it under or in connection with this agreement…". Plainly the shortfall is the extent to which the trust property is insufficient to allow recovery of the full amount due.
22 The effect of this condition may be illustrated by a situation where a plaintiff simply refuses to pay any amount that is due under the facility. If the lender then sued it would be open to the borrower to plead as a matter of defence that the whole or some part of the amount sought to be recovered is beyond the amount of the trust property and therefore not recoverable. It could hardly be imagined that a proper construction of the clause would allow the borrower to defend the proceedings simply on the basis that they are "proceedings" for recovery and thus prohibited by the clause.
23 On an ordinary grammatical construction the condition in the first part of the sentence would have to apply to both the alternatives in the second part of the sentence.
24 In the case there is no evidence before me in these proceedings that the amount sought in the demand represents in whole or in part a "shortfall in the amounts owing".
25 The first basis on which the plaintiff seeks to set aside the demand is that the debt which is the subject of the statutory demand is a debt which is not recoverable by action. It is plain that this is a condition that must be met before a demand can be issued. See Takchi Bros Constructions Pty Ltd v Woods [2010] NSWSC 115 at [5] and Remuneration Data Base Pty Ltd v Pauline Goodyer Real Estate Pty Ltd [2007] NSWSC 59 at paras [40] - [43]. This is a matter which I must decide to see whether the demand should be set aside under s 459J(1)(b). I am not dealing with whether there is a genuine dispute as to the existence or amount of the debt.
26 I do not think that the primary submission of N A Investments as to the construction of the clause is correct. Absent any evidence to enliven the qualification in the second sentence of the clause there is no basis to conclude that there is some other reason to set aside the demand.
27 The second basis is that the statutory demand is a "proceeding" prohibited by the agreement between the parties. N A Investments' submissions were as follows:
"A statutory demand is itself capable of being a "proceeding" within the terms of the Restated Facility Agreement.
The service of the statutory demand constitutes "bringing proceedings against the Trustee" to "seek to recover any shortfall in the amounts owing to [Permanent] under or in connection with this agreement" and falls foul of clause 11.18.
The service of the demand is analogous to the situation in Arcade Badge Embroidery Co Pty Ltd v DCT (2005) 157 ACTR 22. In that case it was held that where there was an oral agreement between the creditor (in this case the tax office), and the Company, in which the ATO sought to renege on a promise or representation to withdraw the statutory demand. In those circumstances, the ACT Court of Appeal set aside the demand saying that:
"What is contemplated by s 459J(1)(b) is a discretion of broad compass which extends to conduct that may be described as unconscionable, an abuse of process, or which gives rise to substantial injustice ..."
The demand should be set aside under s 459J(1)(b)."
28 As it is again a claim that the demand be set aside under s 459J(1)(b) I have to decide the question of construction and thus in the absence of the relevant evidence I would not set it aside on this basis.
29 The third claim is that the statutory demand is an abuse of process. The submissions were:
"Paragraph 4 of the Statutory Demand contains the usual statement that:
"The Creditor may rely on a failure to comply with this demand within the period for compliance ... as grounds for an application to a court having jurisdiction under the Corporations Act 2001 for the winding up of the Company."
That paragraph is incorrect and misleading in the present case as the Creditor is not able to rely on the statutory demand to wind up N A Investments because of clause 11.18 of the Restated Facility Agreement. It is, at the very least, a defect in the demand which would cause substantial injustice if the demand were not set aside.
Moreover, whilst it is accepted that there is no prima facie abuse of process where a statutory demand is used for the collateral purpose of obtaining payment of a debt, there is an abuse in circumstances where the creditor is unable to obtain the ultimate relief, that stated in paragraph 4 of the demand, namely an order that the company be wound up. This is an abuse in the sense of Williams v Spautz (1992) 174 CLR 509. In that case Brennan J, cited the proposition from an earlier Court that:
"the term 'abuse of process' connotes that the process is employed for some purpose other than the attainment of the claim in the action."
In the present case, the ultimate remedy of winding up the Company is unavailable to Permanent, and it must follow that the payment of the debt would not be a collateral benefit or purpose, but the only benefit or purpose available to it. For that reason, it is submitted that the service of the demand is an abuse in the relevant sense."
30 For the same reasons, namely, the construction that I adopt and the absence of evidence, this ground is not made out. I do not see that the condition in the first part of the second sentence only applies to the first alternative in the second part of that sentence.
31 I turn to whether there is an offsetting claim rising out of the failure to extend further finance and the consequent sale of the business. N A Investments helpfully included in their submissions a pleading of the claim that they say arises on the facts of this case. The claim provides: