© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2017] NSWSC 1121
Supreme Court of NSW
2017-08-17
Hammerschlag J
Original judgment source is linked above.
Solicitors: Colin Biggers & Paisley - Plaintiff Moray & Agnew - Defendant File Number(s): 2017/86514
What this case is about
The Act
Facts
The First Ground of Challenge - Supporting Statement
The Second Ground of Challenge - Void as Being Out of Time
The Adjudicator's Fees
Conclusion
SCHEDULE SCHEDULE 1 - Form of supporting statement (Clause 19 (1)) Supporting statement by head contractor regarding payment to subcontractors This statement must accompany any payment claim served on a principal to a construction contract by a head contractor. For the purposes of this statement, the terms "principal", "head contractor", "subcontractor", and "construction contract" have the meanings given in section 4 of the Building and Construction Industry Security of Payment Act 1999. Head contractor: [business name of head contractor] ABN: [ABN]
Schedule of subcontractors for which an amount is in dispute and has not been paid Subcontractor ABN Contract number/identifier Date of works (period) Date of payment claim (head contractor claim)
Endnote
Mt Lewis Estate Pty Ltd
Metricon Homes Pty Ltd
(1998) 194 CLR 342
(2011) 81 NSWLR 716
(2010) 78 NSWLR 393
(1998) 194 CLR 355