© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2002] NSWLEC 184
Land and Environment Court (NSW)
2002-06-25
Pain J, Mr P
Original judgment source is linked above.
Introduction
Facts 5. The facts as set out here are drawn in large part from the statement of agreed facts supplied by the parties. The Defendant is the registered proprietor of 66 Bradleys Head Road, Mosman (the property). The Defendant became the owner of the property on 28 June 2000 and continues to be the owner. The property was the site of the Bradleys Head Private Hospital (the building), a three storey building and a heritage item under the Mosman Local Environmental Plan 1998 (the LEP) on the dates of the offence. At the relevant time the property was zoned residential 2(a1) under the LEP. The LEP required development consent for the demolition of the building.
Development Application No. 8.2000.137.1 was lodged by the Defendant with the Prosecutor on 7 April 2000 for the development of a 10 unit retirement village conversion from the building. The consent for the development was issued by the Prosecutor on 1 September 2000. The conditions of development included demolition of much of the building but required that part of the existing walls and footings of the building be retained as detailed in plans attached to the Notice of Determination of consent.
Darren Mitchelson, through his company Network Property Services Pty Ltd (NPS), was appointed by the Defendant's parent company, Equity & Law (E&L), as the project manager for the development of the retirement village at the property. On 20 December 2000, Paul Gearin, an accredited certifier, issued a construction certificate for partial demolition of the building to the Defendant. The plans attached to the construction certificate marked S2A included a note to the following effect: Note: Where existing footings & walls are to be used, engineer is to inspect and approve structural adequacy of footings & walls before proceeding with level 2.
On 22 January 2001 the consulting engineer for the project, Taylor Thomson Whitting, issued a Site Instruction to Mitchelson. That Site Instruction noted that "the existing footings will be structurally inadequate for the new development". Mitchelson contacted the certifier to discuss the consulting engineer's advice. Mitchelson apparently believed he then obtained the certifier's verbal consent for total demolition of the building. The certifier was not called to give evidence.
Mitchelson instructed Menai Excavations Pty Ltd (Menai) to demolish the whole of the building, including the walls the development consent required to be retained (the walls). On 24 and 25 January 2001, Menai demolished the walls. On 6 February 2001, the consulting engineer confirmed by letter the Site Instruction that both the footings and the walls were structurally inadequate.
Menai has pleaded guilty in this Court to a similar charge in separate proceedings. Mitchelson has also been separately charged with a similar offence and has pleaded guilty in this Court.
The offence charged is a strict liability offence. Proof of intention of causing the offence is therefore not required, but the defence of honest and reasonable mistake of fact may be available to the Defendant. There is no dispute that development, namely demolition of all walls of the building, was carried out without development consent.
Contractual arrangement between Mitchelson and the Defendant 12. However, one of the key issues in these proceedings is what is the nature of the contractual relationship between the Defendant and Mitchelson, and hence the liability, if any, of the Defendant.
Prosecutor's submissions on the liability of the Defendant for Mitchelson's actions
Defendant's submissions 23. The Defendant maintained that Mitchelson was at all times an independent contractor and that the Defendant was not vicariously liable for his actions. The Defendant argued that vicarious liability would arise in two circumstances: (a) Where the Court finds that Mitchelson was an employee of Waratah and that his acts and omissions that led to the offence were carried out within the scope of his employment; or (b) Where the Court finds that Mitchelson was an independent contractor of Waratah and there was direct authorisation of Mitchelson's acts or omissions by Waratah.
The Defendant submitted there was no evidence suggesting Mitchelson was an employee of the Defendant. Mitchelson performed project management services for E&L pursuant to the Agreement dated 7 April 2000. That agreement provided that Mitchelson through his company NPS would provide project management services to a number of projects, including the project at the property. It is clear from the agreement, namely cl 3.1 and 3.2, that Mitchelson and NPS were independent contractors, not employees. The Defendant relies on Stevens v Brodribb Sawmilling Company Proprietary Limited (1986) 160 CLR 16 in support of this proposition. Furthermore, Mitchelson was carrying out work in relation to the project pursuant to that agreement.
Further, the Defendant argued that even if Mitchelson was an employee, the Defendant is only vicariously responsible for actions carried out within the scope of his employment. Mitchelson was only authorised to act lawfully in putting the development consent into effect. Any unlawful action was outside the scope of his employment.
In relation to vicarious liability of a principal for an independent contractor, the Defendant submitted on the basis of the decision of Lloyd J in Environmental Protection Authority v Multiplex Constructions Pty Ltd (2000) 112 LGERA 1 that there must be sufficient control and direction over the independent contractor's activities by the principal in order to support a finding of vicarious liability.
Dorney's affidavit (par 29) states that Mitchelson was in control of the project and the evidence of both Dorney and Mitchelson was that Mitchelson had control of how the project was to be carried out. The only area where Mitchelson said he did not have authority was in relation to spending money, as he only had authority to spend up to a certain amount.
Dorney disputed in his oral evidence that he stated to Prosecutor officers at the meeting held at the Prosecutor's Chambers on 31 January 2001 that Mitchelson was representing the Defendant in addition to stating he was the project manager for the property.
There is no evidence, the Defendant submitted, to support a conclusion that Mitchelson was anything other than an independent contractor over whom the Defendant did not exercise sufficient direction or control to justify a finding of vicarious liability. There was no evidence of any direction by the Defendant to Mitchelson in relation to the unlawful demolition. This submission was made on the basis that there was no evidence inconsistent with the arrangements between the parties being controlled by the agreement under which Mitchelson's company is described and employed as an independent contractor. Further, the Defendant submitted, I need to be satisfied beyond reasonable doubt that the Defendant directed Mitchelson other than in accordance with the development consent issued by the Prosecutor. Finding Was Mitchelson the heart, mind and will of the company? 30. As the Prosecutor identified, Tesco was applied in Australia in Hamilton. In Tesco it was recognised that where an employee or agent can be said to be acting as the company, such that the agent's "mind which directs his acts is the mind of the company", the company will be liable - the agent's guilt is the guilt of the company. Furthermore, it is a question of law, having regard to the facts of the case, as to whether a person can be regarded as the mind of the company. In Tesco Lord Reid held at 170 - 1: It must be a question of law whether, once the facts have been ascertained, a person in doing particular things is to be regarded as the company or merely as the company's servant or agent… Normally the board of directors, the managing director and perhaps other superior officers of a company carry out the functions of management and speak and act as the company. Their subordinates do not. They carry out orders from above and it can make no difference that they are given some measure of discretion. But the board of directors may delegate some part of their functions of management giving to their delegate full discretion to act independently of instructions from them. I see no difficulty in holding that they have thereby put such a delegate in their place so that within the scope of the delegation he can act as the company. 31. On the evidence relied on by the Prosecutor, I do not think Mitchelson could be described in this way. I note the evidence relied on by the Prosecutor, set out at par 19, as the basis for the Prosecutor's submission that Mitchelson was the heart and mind of the company. It is clearly important to determine the extent to which Mitchelson was able to exercise his discretion independently of instructions from the Defendant in carrying out his work. It was also the evidence in the proceedings that: (i) Mitchelson had an office next to Dorney and kept him regularly informed of matters. Mitchelson estimated that he spent approximately fifty percent of his time in his office. He agreed with the Prosecutor in cross-examination that it was important that he keep the owners fully informed and that it was the owners of the site who controlled access and possession of the site for the purposes of carrying out work. (ii) Mitchelson and Dorney had numerous informal meetings to discuss progress on the project so that Dorney was kept informed of progress regularly by Mitchelson. Mitchelson's affidavit and cross-examination confirmed that Dorney gave directions for some actions to be taken during the course of the project. Examples were instructions to Mitchelson to get builders' quotes and to obtain a construction certificate. (iii) Dorney was told by Mitchelson of the potential problems with the footings and walls on 9 or 10 January 2001 and Dorney asked him what he was going to do about it. (iv) Dorney was also informed on 23 January 2001 before the demolition took place, that Mitchelson had instructed Menai Excavations to demolish all the walls and footings, and Dorney said "OK". (v) While the evidence discloses that Mitchelson did have discretion in how he went about much of his day to day duties and filled out forms such as the application for modification, Dorney signed such documents on behalf of the Defendant. (vi) Mitchelson only had limited authority in relation to spending money, that is, up to a certain defined amount. (vii) Mitchelson agreed in cross-examination that he asked Dorney whether to proceed with getting construction drawings and to engage the services of and get quotes for a builder as referred to in par 13 of Mitchelson's affidavit sworn 28 May 2002. He was asked to forward fee proposals to Dorney and was instructed by Dorney to find a builder for the project . 32. In all the circumstances I do not think the Defendant is directly liable for Mitchelson's actions on the basis that Mitchelson was the heart, mind and will of the company, as he was not invested, in my view, with such complete discretion in how he did attend to matters on behalf of the Defendant to justify such a finding. While it is clear that Mitchelson had authority to make arrangements for Menai to undertake demolition, it is also clear that Dorney had ultimate control over what occurred at the site. There was frequent communication between Dorney and Mitchelson about the work being conducted on the property and, on more than one occasion, Dorney instructed Mitchelson on what action to take. Mitchelson advised Dorney of the difficulties with the footings and walls in early January and advised him on 23 January 2001 (before the demolition took place) that he had organised for the demolition to be undertaken. This evidence suggests that Mitchelson was not the heart, mind and will of the company, as he was not invested with full discretion to act independently of instructions from Dorney.
The evidence suggests that although the Defendant and Mitchelson might have considered that Mitchelson was engaged on the basis that he was an independent contractor, he was clearly also held out as the Defendant's agent, in my view.
E&L owns fifty per cent of the shares in the Defendant and the two companies share common directors, of whom Dorney is most relevant in this circumstance given his close involvement with the Defendant's day to day activities. It is quite possible for Mitchelson to be an agent of the Defendant at the same time as he is either an employee or independent contractor of E&L or the Defendant. The evidence set out above at par 19 and 21 relied on by the Prosecutor demonstrates that Mitchelson is the Defendant's agent, despite the Defendant's reliance on the agreement in which E&L employed NPS as an independent contractor. There was evidence in Mitchelson' cross-examination to the effect that when he dealt with Dorney, Dorney did not advise him whether he was communicating with him as a director of E&L or the Defendant. Further, although Mitchelson did not make clear to the Prosecutor's officers when he dealt with them which company he was working for, there was no reason for people dealing with Mitchelson to think he was not working for the Defendant rather than another entity, such as E&L, in relation to the property.
Further, in relation to the conversation during the meeting at the Prosecutor's chambers on 31 January 2001, I accept the evidence of the Prosecutor's officers, James Perica and John Carmichael, that Dorney said Mitchelson was the project manager and was representing the Defendant. I note that Dorney agreed with the Prosecutor in cross-examination that although he could not recall the terms of the conversation with the Prosecutor's officers on 31 January 2001 he was likely to have said Mitchelson was the project manager for the project but denied he said Mitchelson was representing the Defendant.
It seems to me that Mitchelson was acting as the agent for the Defendant and it is therefore vicariously liable for his actions. Mitchelson clearly committed the offence in the course of his work for the Defendant. The situation is similar to that in Power v Penthill House, where the first Defendant was held vicariously liable for the actions of the second and third Defendants as its agent.
The fact that the action was unlawful does not take it outside the scope of Mitchelson's work conducted for the Defendant for which the Defendant is liable. It cannot be suggested, on the evidence, that Mitchelson was acting outside the scope of his work when he caused the unlawful demolition to take place. Although the argument was put by the Defendant on the supposition, which the Defendant denied, that he was an employee, this finding also applies to Mitchelson as an agent.
The submission of the Defendant that I need to be satisfied beyond reasonable doubt that the Defendant directed Mitchelson other than in accordance with the consent, if he was an independent contractor, appears to go beyond the level of control and direction necessary to found vicarious liability, based on Multiplex amongst other authorities, and I do not accept that submission. In any event, it does not arise as I have not founded the Defendant's liability on the basis of vicarious liability for an independent contractor, but rather on the basis of Mitchelson being the Defendant's agent. Primary and secondary offender The parties' submissions 40. The Defendant argued that even if it was vicariously liable for the actions of Mitchelson it is not a principal offender; it could only be guilty as a secondary offender. This was because Mitchelson could only be guilty as a secondary offender - he pleaded guilty to the offence of causing to carry out. As the offence is framed as that of a secondary offender, being "causing to carry out development" the Prosecutor must prove that the Defendant had actual knowledge of the essential elements of the offence. In support of this proposition the Defendant relied on Giorgianni v The Queen (1985) 156 CLR 473 in which Gibbs CJ stated at 488 that the prosecution must show that the defendant: intentionally aided, abetted, counselled or procured the acts of the principal offender. Wilful blindness…is treated as equivalent to knowledge but neither negligence nor recklessness is sufficient.
Finding on Primary v Secondary Offenders 44. The issue as I see it is in slightly different terms to that put by the parties. It seems to me that, as the Defendant company is vicariously liable for Mitchelson's actions as its agent, whether it is liable as principal or secondary offender is irrelevant. The Defendant's guilt arises because of its relationship with Mitchelson. There is no need to consider separately from Mitchelson's actions whether the company itself had the requisite "knowledge" of the relevant circumstances to render it guilty in its own right as a secondary offender, as the Defendant argued.
Defences raised 46. The Defendant raised two defences. (i) Honest and reasonable mistake of fact 47. The Defendant relied on the defence of honest and reasonable mistake of fact, namely, did the Defendant have an honest and reasonable belief in a set of facts which if true would exculpate him? The Defendant argued it honestly and reasonably believed that the walls to be retained would not be demolished until approval had been obtained, and this belief was reasonable (see Rao at par 54). The Defendant argued that on the basis of the evidence of Dorney and Mitchelson the Court would find:
(i) The Defendant was aware of the development consent. (ii) The Defendant was aware that development consent required some of the walls to be retained. (iii) The Defendant believed the walls to be retained could be demolished if approval was given. (iv) The Defendant believed the walls to be retained would not be demolished until necessary approval had been obtained. (v) These matters were honestly believed by the Defendant and that belief was reasonable. There is nothing unreasonable in the belief on the Defendant's part that Mitchelson, an independent contractor, would only act lawfully. (vi) Neither Dorney nor the Defendant gave any instructions in relation to the demolition of the walls that were required to be retained under the development consent. Further there was no other form of approval or wilful blindness by the Defendant. 48. The defence of honest and reasonable mistake is only available in relation to questions of fact, not law. The Defendant submits this is a mistake of fact. Once the defence has been raised by the Defendant to show that sufficient evidence indicates the defence might apply, the Prosecution then bears the onus of disproving the defence beyond reasonable doubt: State Rail Authority of NSW v Hunter Water Board (1992) 28 NSWLR 721.
(i) Both Mr Mitchelson and Mr Dorney knew that the company did not have development consent for complete demolition of the building; (ii) Both men also knew that development consent for demolition was required; (iii) Mr Mitchelson knew of the proposed demolition before it occurred; (iv) The principal certifier, Mr Gearin was not called to give evidence as to the advice he gave Mr Mitchelson; (v) In any event, according to Mr Perica, the principal certifier indicated to him that he had not advised the whole structure could be demolished, only the internal walls [see par 25 of Mr Perica's affidavit]; (vi) The principal certifier was not a Prosecutor agent or servant. His function was always quite separate and distinct from that of the consent authority; (vii) Mr Mitchelson and Mr Dorney both chose not to confirm with the Prosecutor that the principal certifier's advice was correct; (viii) Mr Dorney was made aware of the proposed demolition before it occurred or was complete; (ix) Mr Dorney admitted that a phone call to the Prosecutor was all that was required to clarify the situation and that he did not act prudently to make that check before demolition occurred; (x) The development was a significant project involving additions and alterations to a heritage item.
Finding on defence of honest and reasonable mistake 51. The Prosecutor bears the onus of proof beyond reasonable doubt that the Defendant did not hold the relevant honest and reasonable belief. I do not agree with the Prosecutor's submission as to the level of proof which falls on the Defendant. It is for the Prosecutor to prove beyond reasonable doubt that the Defendant did not hold the relevant honest and reasonable belief once the defence is raised.
(ii) Section 80(12) of the EP&A Act 54. The Defendant lastly argued that there was a defence based on s 80(12) of the EP&A Act. This section provides that: Effect of Issuing Construction Certificate If a consent authority or an accredited certifier issues a construction certificate, the construction certificate and any approved plans and specifications issued with respect to that construction certificate are taken to form part of the relevant development consent (other than for the purposes of section 96). 55. The Defendant argued the section is necessary because of cl 145 of the Environmental Planning and Assessment Regulation 2000 (the EP&A Regulation) which anticipates that there may be a difference between a development consent and a construction certificate. Clause 145(1) provides: A certifying authority must not issue a construction certificate for building work unless it is satisfied of the following matters: (a) that the design and construction of the building (as depicted in the plans and specifications and as described in any other information furnished to the certifying authority under clause 140) are not inconsistent with the development consent,… 56. The Defendant argued that the use of the words "not inconsistent" in cl 145(1)(a) is deliberate and envisages differences that are still "consistent". A person is entitled to act pursuant to a construction certificate and assume that the construction certificate is valid unless or until it is declared otherwise. Swadling v Sutherland Shire Council (1994) 82 LGERA 431 at 436 was relied on in support of that submission, that judgment concerned the validity of a development consent which, the Defendant argues, is an appropriate analogy for a construction certificate. As the construction certificate has not been challenged or set aside it is therefore valid. The construction certificate permitted the walls to be demolished. There was therefore no breach of the development consent.
Finding on s 80(12) 61. While cl 145 of the EP&A Regulation does not allow the issue of a construction certificate which is inconsistent with development consent, the EP&A Act appears to be silent on the legal issue raised here, namely the extent to which a construction certificate can be incorporated into a development consent under s 80(12) if inconsistent with the development consent and the construction certificate has not been declared invalid by a Court. Section 80(12) on its face simply states that any construction certificate issued forms part of the development consent. It seems to me this is a live legal issue given the way the EP&A Act and EP&A Regulation have been drafted. As it is not necessary that I decide the issue finally here because of my view of the facts, I will simply note that the Defendant's interpretation of the reason for the reference to s 96 in s 80(12) is the preferred interpretation on my reading of s 80(12) in the context of the EP&A Act. However, I express no opinion as to whether a defence is available under s 80(12) of the EP&A Act.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Mosman Municipal Council
Waratah Village Partners Pty Ltd
CITATION : Mosman Municipal Council v Waratah Village Partners Pty Ltd [2002] NSWLEC 184 PROSECUTOR Mosman Municipal Council PARTIES : DEFENDANT Waratah Village Partners Pty Ltd (ACN 090 814 672) FILE NUMBER(S) : 50067 of 2001 CORAM: Pain J KEY ISSUES: Prosecution :- not guilty plea - unlawful demolition of building - whether Defendant liable for agent's actions - whether agent was mind and will of Defendant - whether vicarious liability - relevance of primary versus secondary offender in relation to vicarious liability - whether honest and reasonable mistake of fact - whether s 80(12) of the Environmental Planning and Assessment Act 1979 is available as a defence Environmental Planning and Assessment Act 1979 s 76A, s 80(12), s 96, s 125(1) LEGISLATION CITED: Environmental Planning and Assessment Regulation 2000 cl 145 Mosman Local Environmental Plan 1998 Burrell v Jacenko (1998) 99 LGERA 173; Canterbury City Council v Saad (2000) 112 LGERA 107; Environmental Protection Authority v Multiplex Constructions Pty Ltd (2000) 112 LGERA 1; Environmental Protection Authority v Snowy Mountains Engineering Corporation Ltd (1994) 83 LGERA 51; Environmental Protection Authority v Taylor Woodrow (Australia) Pty Ltd (1997) 101 LGERA 226; Giorgianni v The Queen (1985) 156 CLR 473; Hamilton v Whitehead (1988) 166 CLR 121; Mosman Municipal Council v Menai Excavations Pty Ltd [2002] NSWLEC 132; CASES CITED: Mosman Municipal Council v Mitchelson [2002] NSWLEC 111; North Sydney City Council v Michael Standley & Associates Pty Ltd (1998) 97 LGERA 433; Owen v Wiltara (1998) 103 LGERA 137; Power v Penthill House Pty Ltd (1993) 80 LGERA 247; R v Australian Films Limited (1921) 29 CLR 195; Rao v Canterbury City Council (2000) 112 LGERA 360; State Rail Authority of NSW v Hunter Water Board (1992) 28 NSWLR 721; Stevens v Brodribb Sawmilling Company Proprietary Limited (1986) 160 CLR 16; Swadling v Sutherland Shire Council (1994) 82 LGERA 431; Tesco Supermarkets Ltd v Nattrass [1972] AC 153 DATES OF HEARING: 24, 25/06/2002, 15/07/2002 (written submissions), 23/09/2002 (written submissions) DATE OF JUDGMENT: 10/21/2002
(1998) 99 LGERA 173
(2000) 112 LGERA 107
(2000) 112 LGERA 1
(1994) 83 LGERA 51
(1997) 101 LGERA 226
(1985) 156 CLR 473
(1988) 166 CLR 121
(1998) 97 LGERA 433
(1998) 103 LGERA 137
(1993) 80 LGERA 247
(1921) 29 CLR 195
(2000) 112 LGERA 360
(1992) 28 NSWLR 721
(1986) 160 CLR 16
(1994) 82 LGERA 431