© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2022] NSWCA 95
Court of Appeal (NSW)
2022-03-18
Payne JA, White JA, Beech-Jones JA
Original judgment source is linked above.
Background
The Pleaded Case
The Primary Judge's Findings
The Appeal
Ground 2: The Counterfactual
Ground 1: Approach to the "No Transaction" Case
Conclusion
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 17 June 2022
Morris
Leaney
Solicitors: Gilberts Legal (Appellants) Holman Webb Lawyers (Respondent) File Number(s): 2021/195267 Decision under appeal Court or tribunal: District Court Jurisdiction: Civil Citation: [2021] NSWDC 224 Date of Decision: 10 June 2021 Before: Smith SC, DCJ File Number(s): 2018/187937
HEADNOTE [This headnote is not to be read as part of the judgment] The respondent was engaged as architect to design the appellant's home renovations. The appellants objectives for the renovations included an extension of their house as well as a pool, tennis court and sauna. They indicated that their initial budget of $300,000. The Respondent advised them that they could not achieve what they wanted within that budget. In April 2015 the Respondent provided the appellants with "opinion on probable cost" for a preliminary design that estimated the cost of the renovations as $590,000 excluding GST and other items. Later that month the appellants revised their budget to $600,000 although the primary judge rejected the appellants' evidence that they specified that figure as their maximum budget. The appellants and the respondent then refined their design and they sought quotes from a builder. In October 2015 a builder provided a quote for the renovations of between $550,000 and $600,000 excluding pool, sauna, tennis court, a driveway, and other works. Work commenced on the renovations with another builder on a cost-plus basis from December 2015. In February 2016 the parties had a falling out and the appellants continued with the builder. In June 2016 the builder advised that the cost of achieving their objectives would exceed $1,000,000. The appellants did not pursue all their objectives with the renovations. It was agreed that the renovations ultimately cost $780,000 but only increased the value of the house by $330,000. The appellants sued the respondent for a breach of s18 of the Australian Consumer Law alleging, inter alia, that in April 2015 he expressly represented that they could achieve their renovation objectives for $600,000 by making some costs saving. The trial judge rejected their evidence and dismissed that claim. However, the trial judge found that, if the representation had been made, then the appellants relied on it. The appellants also sued the respondent in contract and tort alleging, inter alia, that he breached a concurrent contractual and tortious duty to advise them about the "likelihood of achieving the clients stated budget and time requirements for the architectural service concerned". The primary judge found that the respondent breached that duty but did not specify what advice should have been given or make a finding about whether the appellants would have not pursued the renovations had the duty been complied with. However, the primary judge found that "if the [respondent] felt himself unable or unqualified to give an accurate estimate of costs, he should have warned of that in writing and advised the plaintiffs to obtain an estimate from a properly qualified professional". The appellants framed their claim for damages on a "no transaction" basis that is, had the alleged representation not been made or the relevant duty been discharged, then they would not have pursued the renovations. The primary judge found that they did not suffer any loss and only awarded the appellants nominal damages for breach of contract. The issues on the appeal were: (i) Whether the primary judge found, or this Court should find, that the respondent was obliged to advise the appellants they "that they could not achieve their objectives for their budget of $600,000" and if he had whether they would not have undertaken the renovations? (ii) If issue (i) was resolved in favour of the appellants, did the primary judge err in concluding that they did not suffer any loss? The Court held, dismissing the appeal: As to issue (i) per Beech-Jones JA (Payne JA and White JA agreeing):
[2008] WASCA 262
[1986] HCA 3
[2020] VSCA 192
(1986) 160 CLR 1
(2020) 61 VR 384
(1963) 110 CLR 74
(2019) 272 FCR 373
(1991) 174 CLR 64
(1989) 16 NSWLR 130