Mo v ABC Homes NSW Pty Ltd
[2019] NSWCATAP 16
At a glance
Source factsCourt
NCAT Appeal Panel
Decision date
2018-12-11
Source
Original judgment source is linked above.
Judgment (27 paragraphs)
Background
- This is an appeal from a decision made in the Consumer and Commercial Division of the Tribunal published on 15 August 2018 (which we will refer to as the Decision). The Decision concerned two applications: one brought by the appellant (the homeowner) and the other, an application brought by the respondent to the appeal (the builder). Both applications were dismissed. The homeowner appeals the Decision in respect of her application.
Summary of the Decision
- In understanding this appeal it is helpful to have a summary of the Decision which is set out as follows: 1. The homeowner and the builder entered into a written contract in July 2015 for the builder to construct a new two storey dwelling. The builder issued Progress Claim 5 (PC5) on 13 September 2016 for $145,750.00 of which the homeowner paid $60,000.00; 2. A dispute developed and the builder last worked on site in mid-October 2016; 3. The homeowner commenced proceedings in the Tribunal in April 2017 seeking damages for incomplete work, alleging that the builder was not entitled to stop work, seeking damages for defective work and delay costs; 4. The homeowner alleged that the builder overcharged her in PC5 and that the builder engaged in "double dipping" by charging for the same work in PC5 and in variation claims issued in September 2016; 5. The builder lodged a cross application in August 2017 seeking $47,537.00; 6. The Decision describes the homeowner's evidence and points to deficiencies in the evidence. For example, at paragraph 27 the Decision records that the homeowner put forward "partial documents" to support her case (e.g. a final page of a letter from Parramatta Council) and states that without "any frame of reference and in the absence of being in complete form, such documents are of no weight"; 7. The evidence put forward by the builder is similarly described as having little weight (for example see paragraph 33 of the Decision); 8. The Decision records the homeowner's claims with respect to items of defective work. All of those claims were dismissed and, to the extent necessary, we will subsequently in these reasons return to the basis for those dismissals; 9. In the Decision, there was an analysis of whether PC5 was issued consistent with the terms of the contract or in breach of the contract. The Member found that the builder was entitled to issue PC5 with the consequence that, as a result of non-payment by the homeowner, the builder was entitled to suspend the work. That was the consequence of the Tribunal finding that non-payment of PC5 put the homeowner in breach of the contract; 10. In the Decision, the Member outlined the chronology of events and concluded that the homeowner was not entitled to purport to terminate the contract and that the builder did not repudiate the contract. The Decision recorded that it followed that the homeowner was not entitled to damages for incomplete work or delay costs; and 11. In respect of the builders cross application, the Decision recorded that the builder could not adequately explain how he arrived at the sums claimed because no material was provided to substantiate the figures sought. Essentially, through the lack of supporting evidence, the Tribunal came to the conclusion that the builder was unable to provide evidence in support of his application.