Mitchell v Pacific Dawn P/L [2003] QCA 526
[2003] QCA 526
At a glance
Source factsCourt
Court of Appeal (Qld)
Decision date
2003-11-28
Before
McPherson, JA and Mackenzie and Wilson JJ, Separate reasons for judgment of each member, of the Court, each concurring as to the orders made
Catchwords
- APPEAL
- AND NEW TRIAL - GENERAL PRINCIPLES - INTERFERENCE WITH JUDGE'S FINDINGS OF FACT
- - WHERE FINDINGS CLEARLY WRONG - GENERALLY
- - trial judge's finding of fact
Source
Original judgment source is linked above.
Catchwords
Judgment (32 paragraphs)
[1] McPHERSON JA: The respondent plaintiff Bruce Mitchell is a builder who on 2 September 1999 entered into a contract with the appellant defendant Pacific Dawn Pty Ltd for the construction of a commercial building on land it owned at Toowong. The contract incorporated standard printed provisions used for lump sum building contracts but provided for what was described as "a guaranteed upper limit cost of $2,650,000". It was agreed that if at completion the construction cost did not exceed that limit, the plaintiff would receive an additional fee of 7.5% = $198,750 plus 107.5% of the cost of variations and extras for which the defendant was liable under the contract. The object was evidently to provide the plaintiff with an incentive to complete the work within the limits of the estimated cost. If completed for less, the parties were to share the reduction in costs below that sum. The construction agreement therefore had, as the learned judge remarked, characteristics of a lump sum and a cost plus contract.