Conclusions and orders
18While the tree is clearly a healthy specimen that makes a contribution to the ecosystem and to the general amenity of the area it has, unfortunately, caused damage to a large and important storm water pipe.
19Similarly, while I understand council's and the respondents' reluctance to remove the tree [likewise the Court considers tree removal as the last and least preferred option], rectification of the problem and the prevention of future damage will require the removal of large structural roots close to the base of the tree.
20I am satisfied that the range of practical options was thoroughly explored on site, particularly with Mr Dagg's assistance. It would be unhelpful of the Court to make orders that could destabilise a tree.
21After considering the evidence, I have determined that the tree is to be removed. Given the cost of removing such a large tree, the tree need not be taken to ground level but can be left as a 3m stump if the respondents so desire. However, the stump must be poisoned to prevent regrowth.
22The respondents contend that they should not be required to pay the full cost of removing the Blackbutt as it is a self-sown individual over which they have had no control. In the vast majority of tree disputes, orders for the payment of any costs - for pruning or removal of a tree, have been made against the tree owner unless there are particular circumstances that justify apportionment of costs between the parties. In this particular case I am not satisfied that the applicant should contribute to the cost of removal. As previously mentioned, in order to keep the respondents' costs as low as possible, the bulk of the stump can be retained.
23The parties have agreed to share the cost of replacing a 5 metre section of concrete pipe with PVC. Quotes for this work are to be limited to the removal and replacement of the 5 m section, the removal of any roots in the immediate vicinity of the pipe, and the consolidation of soil beneath the replaced section of pipe. Any additional work that the applicant wants carried out must be separately itemised and is to be paid for by the applicant.
24Therefore, the Orders of the Court are:
(1)The application to remove the tree is upheld.
(2)Within 30 days of the date of these orders, the respondents are to engage and pay for an AQF level 3 arborist, with appropriate insurance cover, to remove the tree to a height no greater than 3 m above ground. The remaining trunk is to be poisoned to prevent any regrowth of any part of the tree.
(3)The applicant is to provide all reasonable access on two days notice for these works to be undertaken in a safe and efficient manner.
(4)The work is to be carried out in accordance with the WorkCover NSW Code of Practice for the Amenity Tree Industry. The arborist must ensure that no wildlife is harmed during the removal of the tree.
(5)The applicants are to obtain two quotes for the replacement of 5 metres of storm water pipe, associated root removal and soil consolidation beneath the pipe [as described in paragraph 23 of this judgment]. Any additional works are to be separately itemised and paid for by the applicant. The respondents are to obtain at least one quote for the same work.
(6)The parties are to exchange quotes and agree on the best quote.
(7)The applicant is to engage and pay for the selected contractor.
(8)The selected contractor is to liaise with the arborist to co-ordinate the removal of the tree and any necessary root pruning. If root pruning is carried out before the removal of the tree, it must not compromise the stability of the tree or the safety of anyone working in it.
(9)The respondents are to reimburse the applicant 50% of the cost of the works in order 5 within 21 days of the receipt of a tax invoice for the completed works.
J Fakes
Commissioner of the Court
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated: 17 August 2012