The question of Power
32 In Windy Dropdown I decided that an application for modification of a development consent could be considered notwithstanding that the development had been carried out. The second respondent submits that a consent authority does not have the power to modify a development consent where the development has been substantially constructed. Moreover, the alleged illegality of the works undertaken by the applicant and the alleged failure of the applicant to comply with the requirements of the relevant legislation are said to be matters relevant to establishing lack of power to grant an approval to an application for modification under s 96 of the EPA Act either generally or particularly where dispensation was required under SEPP 1 and not obtained in the first instance. To the extent that the decision in Windy Dropdown is to the contrary, Mr Perram has asserted that it should not be followed and Mr Garnsey reiterates that contention.
33 Mr Perram submitted that as a matter of text it is apparent from s 96(5) that at least in that provision the word modification must refer to a process which occurs prior to the development occurring. I find it difficult to derive any assistance in relation to the present issue from the text of s 96 (5) as in its own terms it refers specifically to an application for modification of the kind that relates to a critical habitat, a threatened species population, or ecological community. The reasons for there being a special provision in respect of development consents of that kind are self evidently related to the special circumstances which relate to threatened species and habitat. Clearly an assessment in accordance with the consultation and concurrence process stipulated in s 79B (3) to (7) would be severely jeopardised if the development had already been carried out. Conversely, the special provision in (5) suggests a construction in respect of any other development consent that is consistent with the finding in Windy Dropdown.
34 In my opinion the power given to the Director-General and a Council pursuant to s 96A(1), called in aid by Mr Perram, takes the second respondent's argument no further. That provision relates to a power to revoke or modify a consent where it appears to either of the authorities that a development application should not be carried out or "completed". Section 96A has no bearing on the operation of s 96, except that it empowers the authorities to modify a consent. It is otherwise a stand alone provision.
35 I agree with subsequent distinguishing observations made by Bignold J in Willoughby City Council v Dasco Design and Construction Pty Ltd (2000) 111 LGERA 422 and Lloyd J in Kendall Street Developments v Byron Shire Council (No. 2) (2004) 138 LGERA 360 that the effect of s 96(4) is not retrospective. As Bignold J said at 442, it does not require a fictional relation back of the modification to the date when the development consent that it modifies was granted. Lloyd J came to the same conclusion at page 369 and 370. The question did not strictly arise in Windy Dropdown itself. The reference to a modification of consent pursuant to s 96 operating retrospectively by dint of s 96(4) in the Windy Dropdown judgment is certainly an unfortunate use of language that arose almost as a side wind in the narrow context of determining whether an application that relates to development which has already been carried out can be made pursuant to s 96. I found in Windy Dropdown that such an application can be made. Bignold J and Lloyd J as well as Cowdroy J in Austcorp No. 459 Pty Ltd v Baulkham Hills Shire Council (2002) 122 LGERA 205 have since concurred. The decisions of Bignold and Lloyd JJ, followed specific argument on the issue.
36 The effect of the decisions in Dasco Design and Kendell Street is merely that the Court has the power to entertain an application made under s 96 irrespective of whether the development has been carried out. However, that does not have any impact upon the possible consequence that any works carried out otherwise than in accordance with the original development consent between the date of the original development consent and the date of the approval under s 96, may have been carried out illegally.
37 Mr Perram persisted with an argument that the rejection by Bignold J and Lloyd J of the finding in Windy Dropdown that works which were illegal ceased to be so upon the approval of the modification, is inconsistent with the pivotal reasoning relied upon in Windy Dropdown. However, rather than being part of the pivotal reasoning, the reference to retrospective operation was only a consequence of the reasoning which supported the conclusion that an application for modification of development consent could be considered notwithstanding that the development had been carried out.
38 Furthermore, the submissions on behalf of the second respondent do not appreciate the fact that s 76 operates in respect of development whereas s 96 operates in respect of a development consent. The former is intended to overcome an impediment to the carrying out of development at all without consent whereas the latter deals with an amendment to an existing approval, usually to take into account subsequent facts and circumstances. The modification relates to the documentation of the approval.
39 If an application pursuant to s 96 cannot be made where development had already been carried out, it would defeat one of the purposes of the provision namely to enable changes to be made where carrying out the development strictly in accordance with a development consent has proved to be impracticable or even impossible. Often circumstances change and necessitate adjustments to the operation of or the means of carrying out development.
40 Finally Mr Perram submits that the power in s 96(2) can only be dispensed to a person who is "the applicant or any other person entitled to act on a consent". This argument is developed by reference to the provisions of s 76A(1) which insists that development is to be carried out in accordance with a development consent and the environmental planning instrument which provides that the specified development may not be carried out except with development consent. Because it is alleged the landscape plans approved by the original consent did not comply with the provisions of clause 25I of the KPSO and as there was no dispensation with that requirement under SEPP 1, Mirvac was not, therefore, a person entitled to act on the consent and hence had no entitlement to apply under s 96(2). It follows according to the argument that if s 96 is utilised in the present case it would be a means to circumvent the SEPP 1 procedure entirely by the simple expedience of applying for consent without disclosing the departure from the development standard or making a SEPP 1 objection, carrying out the work to which it would have related illegally, and then seeking modification. Even if this argument is correct it has not been proved to my satisfaction on the balance of probabilities that a SEPP 1 objection was required in the first instance. The SEE asserted to the contrary. The development was supported by a Deep Soil Zone plan that demonstrated provision of 50.16 percent of the site being deep soil zone. The Council accepted, considered and dealt with the application on the basis that the development standard in clause 25I of the LEP would be satisfied. The non compliance with the standard arises now only as a consequence of the evidence of Mr Pittendrigh, a landscape architect and of the way in which the development has been built. The applicant was entitled to act on the consent and continues to be entitled to do so whilever the consent continues to operate and remains in force.
41 The overriding position is that on a plain reading of s 96(2), Mirvac is entitled to make the application in its capacity as the original applicant.
42 The evidence of Mr P Pittendrigh is that he has calculated the area of the deep soil landscaping provided in the approved plans as less than 50 percent of the site area. Even if those calculations are correct the conditions of consent required that the area of deep soil landscaping comply with the standard. The SEE and the supporting plan asserted that would be so. It follows that the development was approved on the basis that the amount of deep soil landscaping would be as prescribed by cl 25I of the LEP.
43 Inadvertent mistake or inaccuracy is not necessarily a ground for treating a determination to grant development consent as invalid. Although Mr Pittendrigh was not cross examined it is certainly arguable that parts of the site he excluded from the calculations could be included to account for the alleged deficiency at the date of the determination. I agree with the applicant's submission that the power in s 96 is not a power which is to be used to punish errors but to relieve from their consequences in appropriate cases (Jonah Pty Ltd v Pittwater Council (2006) 144 LGERA 408). If there was an error initially then the time has long past for that to be an issue. The s 96 application has become necessary in order to overcome the deficiency in the provision of deep soil landscaping area as a consequence of the way in which the development has been built. Not as a consequence of the initial error or mistake, if indeed there was one.
Non compliance with the Development Standard
44 The second respondent seeks to distinguish the circumstances that prevailed in Michael Standley or indeed Windy Dropdown from this case on the basis of the following evidence:-
· The development in the initial development application did not comply with the standard.
· Accordingly, the development was prohibited unless a SEPP 1 objection was lodged.
· It was asserted in the development application that compliance was achieved.
· No SEPP 1 objection was lodged.
· The council proceeded to assess the application on the false assumption that compliance was achieved.
45 I have already said that I am not able to find that a SEPP 1 objection was required in support of the original development application, notwithstanding the evidence of Mr Pittendrigh. However a careful reading of the judgments of Mason P in Michael Standley and applying his conclusion at 480-481 to the application of cl 25I to the facts of this case leads to a further problem. The President of the Court of Appeal dealt with three examples at the top of page 480. None of the examples apply in the circumstances of this case. At page 481 His Honour makes a statement as follows:-
A modification application may be approved notwithstanding the development would be in breach of an applicable development standard were it the subject of an original development application. And s 102(3A) controls the way in which the consent authority takes into account the development standards found in any environmental planning instrument.
46 However what the President did not address is a circumstance, such as the present, where effectively there was compliance by the description or design of the proposal at the time the development application was considered but the modified development (as built) does not comply with the standard. This is not a case where a development standard has been introduced after the original development application was determined. Furthermore even if the standards in cl 25I(2) are development standards they are ambulatory and apply irrespective of the terms of any consent or approval unless development consent is granted on the basis that compliance with the relevant standard is unreasonable or unnecessary in the circumstances of the case.
47 A reading of the plain words of cl 25I(2) demonstrates that its effect enures beyond the date of consent. It applies to the development unless dispensed with. The clause relevantly states:
25I Site requirements and development standards for multi-unit housing
(1) …
(2) Minimum standards for deep soil landscaping
The following standards relating to deep soil landscaping apply to multi-unit house:
(a) …
(b) …
(c) a site with an area of 1,800 square metres or more is to have deep soil landscaping for at least 50% of the site area.
48 The dispensing power contained in SEPP 1 only applies to a development application. Section 76A(1) provides:-
76A Development that needs consent
(1) General
If an environmental planning instrument provides that specified development may not be carried out except with development consent, a person must not carry the development out on land to which the provision applies unless:
(a) such a consent has been obtained and is in force, and
(b) the development is carried out in accordance with the consent and the instrument.
49 As the development may not be carried out except with development consent it must not only be carried out in accordance with the consent but also the KPSO. Clause 25I(2) has not been dispensed with and cannot be varied except by means of a SEPP 1 objection. An application for development consent is not capable of adaption to a modification application for the purposes of applying SEPP 1 (see Michael Standley at p 480 overruling the decision of Bignold J in Haywood & Bakken Pty Ltd v North Sydney Municipal Council).
50 The decision in Michael Standley does not facilitate ignoring an ongoing provision such as clause 25I(2) that controls a specification for the state of the site at any given time. It has not been dispensed with and accordingly has continuing effect. The only means to engage SEPP 1 is by the lodgement of a development application. There is no such application on foot.
51 The problem for the Court therefore is that it is being asked to approve a modified development in a form that cannot be maintained whilever clause 25I(2) operates against it. As a matter of policy the Court should not embrace such a position by granting an approval to a form of development that can only be carried on in breach of the Act (see s 76A(1) and s 125).