Demolition, excavation, clearing, construction, subdivision, or associated activities must no commence until a Construction Certificate has been issued for the proposed development pursuant to the Environmental Planning and Assessment Act 1979.
16 On 13 and 14 November 2007, officers of the Department conducted inspections of the lodge site. They observed that the concrete footings had been poured for a new addition that was proposed to be constructed at the rear of the existing building and that a new concrete extension to the slab on the second level had also been poured. Further, several concrete block walls had been erected. No construction certificate had been issued.
17 During the inspection on 13 November 2009, Mr James Corrigan spoke to several of the directors of Fancott and Mr John Taylor, a person who had been employed by Fancott to supervise the building works. Mr Corrigan stated that because no construction certificate had been issued, all building work should immediately cease. It did. Mr Corrigan also stated that it was possible that a building certificate might be issued by the Department for the building works that had been carried out.
18 On 19 November 2007, Mr Shane Brown, a director of Fancott, attended the Department's offices to file an application for a building certificate for the works that had been observed. In the process he informed Mr Corrigan that construction had been ongoing for a period of approximately two weeks prior to the inspection on 13 November 2007.
19 As a result of its investigations, the Department confirmed that the construction works had been ongoing since 30 October 2007. It also confirmed that prior to pouring the foundations, the pier holes were inspected by an appropriately qualified engineer.
20 On 7 December 2009, an application for a construction certificate was sent to Mr Nathan Halstead, the principal certifier for the development. It was received by him on 13 December 2009.
21 On 21 December 2007, KT's architects send final construction drawings for the development to Mr Halstead in support of the application for the construction certificate. These were, as it transpired, the wrong drawings and the correct drawings were subsequently sent on 7 January 2008.
22 On 24 December 2007, the Department issued a building certificate to Mr Brown and an entity called Jakesam Developments Pty Ltd for the building works that it had observed.
23 On the morning of 2 January 2008, Mr Reid drove past the lodge and observed workmen present on site. He proceeded to question Mr John Taylor, another director of Fancott, whether a construction certificate had been issued for the work. Mr Taylor stated that a certificate had been obtained. This was incorrect. No certificate had in fact been issued. Mr Reid spoke to Mr Brown who repeated the erroneous information to him.
24 On the afternoon of the same day, Mr Reid conducted an inspection of the lodge site. During this inspection he observed that two rows of block work had been constructed on the footings that had been built at the rear of the site in October or November 2007. He noticed that the cement was still wet.
25 Later that day, while Department employees were present, workers engaged by Fancott demolished the two rows of block work and then ceased work.
26 On 3 January 2008, KT submitted a further application for a construction certificate for the lodge to Mr Halstead. The application was for a subset of the whole of the proposed construction project at the lodge. It sought approval for the construction of the slabs and lower walls of the development.
27 On 7 January 2008, a construction certificate was issued in respect of the application made by KT on 3 January 2008 ("the first construction certificate").
28 On 17 January 2008, a second construction certificate was issued in respect of all remaining works but excluding works approved under the first construction certificate ("the second construction certificate").
29 Building work then resumed and was completed.
Evidence of Fancott
30 Fancott relied on an affidavit of Mr Alastair Bailey sworn 28 September 2009. Mr Bailey is one of the directors and the secretary of Fancott.
31 In his affidavit, Mr Bailey deposed that:
(a) Fancott will not carry out any further development;