(a) produce up to 350,000 tonnes of saleable coal a year from the project.
7 For the purposes of these proceedings, the annual production of coal permitted by condition 6(a) of schedule 2 of the approval is measured during the period between 7 September 2006 and 6 September 2007 (approval year).
8 The amount of saleable coal produced by the defendant in the approval year was 635,277 tonnes. This was reported to the Department of Planning in accordance with condition 4 in schedule 5 of the approval in the defendant's Annual Environmental Management Report.
9 The total daily deliveries from the project for the approval year were 597,129.9 tonnes as reported in the verified statement of total daily amounts dated 5 June 2008 by the defendant. A further 39,773.6 tonnes was purchased by the defendant for delivery during the approval year, whereby total deliveries on behalf of the defendant during the approval year were 636,903.5 tonnes.
10 On or around 4 April 2007, an application for modification dated 21 March 2007 was lodged with the prosecutor by the defendant (modification 1). Modification 1 was to allow the processing (washing) of coal recovered from the project at the on-site coal preparation plant. On 4 June 2007, the application for modification was approved by the prosecutor.
11 On or around 11 April 2007, an application for modification dated 4 April 2007 was lodged with the prosecutor by the defendant (modification 2). Modification 2 was to allow the introduction of auger mining techniques to improve coal recoveries and an increase in approved coal production from 350,000 to 500,000 tonnes a year from the project. On 6 December 2007, this application for modification was approved by the prosecutor. Additional conditions relating to community enhancement contributions, noise mitigation measures, a pollution reduction program, transport route restrictions, and land acquisition requirements were inserted into the approval.
12 On or around 6 September 2007, a major project application for the Invincible open cut coal mine - extension (the proposed project) dated 17 August 2007 was lodged with the prosecutor by the defendant. The proposed project was to allow an increase in annual coal production from 500,000 to 900,000 tonnes a year over a maximum period of eight years, expanding open cut and auger mining activities, crushing and processing coal on site, and trucking coal to Mount Piper. The proposed project has not been determined by the prosecutor.
13 It is not alleged that the defendant is in breach of any conditions in schedules 2 to 5 of the approval other than condition 6(a) in schedule 2.
14 The adverse environmental impact generated by the circumstances identified in the prosecutor's summons and charge was the lost opportunity for prior environmental assessment before the activity was carried out. The environmental assessment carried out for the project approval application, particularly in relation to impacts associated with traffic, dust and noise, was based upon the proposed rate of extraction.
15 The defendant has co-operated to the fullest extent with the enquiries made by the prosecutor in relation to the offence.
16 There is no record of any prior environmental offence by the defendant.
17 The defendant's profit and loss statement for the approval year is in evidence and I consider it below.
Mr Follington's evidence
18 The following evidence was given by Mr Ian Follington, who has been the managing director of the defendant since November 2006 when a new major shareholder of the defendant came upon the scene. I accept his evidence.
19 In November 2006, the defendant prepared a document called "Overview of Existing Planned Developments for 2006 to 2012" which it lodged with the Department of Planning to initiate discussion regarding increased production. A presentation was made to officers of the Department prior to lodgement. The document contemplated production at the rate of one million tonnes per annum. There was dialogue between the defendant and the Department thereafter. One of the issues canvassed was the option of seeking to increase production by modifying the existing Part 3A project approval.