"[3] By an agreement in writing dated 10 June 1998, the owner, Palm Bridge, entered into a contract with the builder, whereby the builder agreed to construct a residence on the land for the sum of $542,300. The building contract was in a standard form and made provision for the works to be executed in a proper and workmanlike manner in accordance with times prescribed by the contract. By its points of claim, the owner, Palm Bridge, contended that the works were not carried out in a workmanlike manner and as a consequence of the builder's failure or refusal to remedy a substantial breach, the contract was terminated on 3 December 1999. Palm Bridge claimed, in addition to the cost of rectifying certain work, loss of rental and other damages.
[4] By its points of defence and counterclaim, the builder said that it commenced the works on or about 1 July 1998 and brought the same to practical completion on or about 28 September 1999. The builder said further that it was entitled to extensions of time beyond the date of practical completion and denied that there was any substantial breach of the contract. The builder said that Palm Bridge had paid the builder $455,075.86 under the building contract and, by its conduct in giving a notice of termination and retaking possession of the works, it had repudiated the building contract.
[5] In par 28 of the points of defence and counterclaim, the builder contended that the amount due from Palm Bridge included a progress claim of $65,000 and variations to the value of $63,417.57. A claim was also made for further loss said to have arisen as a result of the alleged repudiation.
[6] Palm Bridge presented a reply and defence to counterclaim in which it denied that the works were brought to practical completion on or about 28 September 1999. It denied that the builder was entitled to any extension of time. Palm Bridge specifically denied par 26 to par 30 inclusive of the counterclaim and thereby denied that there was an amount due to the builder in respect of the progress claim and claim for variations mentioned earlier. Elsewhere in its pleading, however, it did make some comparatively minor concessions in regard to variations.
[7] It appears, then, on the face of the pleadings, that the Arbitrator was obliged to address various matters in issue between the parties and that the resolution of these issues could have a bearing upon the financial claims on either side. In other words, it would not be until the arbitration had been completed that a final determination could be made as to whether a further amount, if any, was due to the builder.
[8] By his final award dated 25 September 2000, the Arbitrator made some comparatively small corrections to figures appearing in his interim award. He went on to say that the effect of the corrections was that there was payable by Palm Bridge to the builder the amount of $97,733.63.
[14] The Arbitrator dealt with other matters in his final award, including costs. He referred to s 34 of the Commercial Arbitration Act which provides that unless a contrary intention is expressed in the arbitration agreement, the costs of the arbitration (including the fees and expenses of the Arbitrator) shall be in the discretion of the Arbitrator who may direct to and by whom and in what manner the whole or any part of those costs shall be paid.
[16] Against that background, the Arbitrator then said this: