© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2022] NSWSC 170
defendant. Orders made: (1) Referee to provide supplementary report within 28 days addressing calculation issues; (2) Plaintiff to provide copy of judgment and submissions to Referee by 2 March 2022; (3)...
The Supreme Court dismissed a builder's challenge to most of a referee's report in a construction dispute, but ordered the referee to provide a supplementary report to explain apparent discrepancies in the financial calculations. The Court confirmed that judges should generally accept referees' findings unless they contain errors of principle or are manifestly unreasonable, and should not simply re-agitate factual findings. The builder had challenged the referee's findings about payment rates for extra work on two apartment towers, but the Court found the referee had properly interpreted the contracts and assessed the evidence. However, because the builder identified an unexplained $198,000 discrepancy in the calculations, the Court sent that issue back to the referee to fix, with the builder to pay the referee's costs for the extra work.
AI-generated legal information, not legal advice. Zoe can make mistakes. Check the cited source, and for advice about your situation consult a qualified Australian lawyer.
Introduction
1 cited instrument linked from this judgment.
Background
Relevant legal principles
Additional External Works
The Additional Internal Works and Tower A Internal Works
The Referee's calculations
Orders
Amendments 01 March 2022 - Typographical error in 12(a) - reference to Mikeon changed to Staffseal DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 01 March 2022
Mikeon Projects Pty Ltd
Staffseal Pty Limited
Orders made: (1) Referee to provide supplementary report within 28 days addressing calculation issues; (2) Plaintiff to provide copy of judgment and submissions to Referee by 2 March 2022; (3) Plaintiff to pay Referee's costs of supplementary report; (4) Matter stood over to 1 April 2022 for directions. Challenges to substantive findings on Additional External Works and Additional Internal Works dismissed.