Mikeon Projects Pty Ltd v Staffseal Pty Limited
[2022] NSWSC 170
At a glance
AI case summaryResult
defendant. Orders made: (1) Referee to provide supplementary report within 28 days addressing calculation issues; (2) Plaintiff to provide copy of judgment and submissions to Referee by 2 March 2022; (3)...
Key principles
- The Court's discretion to adopt, vary or reject a referee's report under UCPR r 20.24 must be exercised consistently with the purpose of Pt 20, which provides partial resolution...
- Where a referee relies on invoices admitted only as evidence of the amount claimed, the referee does not err by using them to establish that claims were made on a particular...
- A referee is entitled to rely on affidavit evidence describing a system for preparing invoices and timesheets, and cross-examination concessions that invoices were checked by the...
- The mere fact that a change in method of calculation (from fee per square metre to hourly rate) produces a substantially increased price does not render a referee's finding...
Issues before the court
- Whether the Court should reject paragraphs of the referee's report concerning the Additional External Works on the basis that the referee relied on...
Plain English Summary
The Supreme Court dismissed a builder's challenge to most of a referee's report in a construction dispute, but ordered the referee to provide a supplementary report to explain apparent discrepancies in the financial calculations. The Court confirmed that judges should generally accept referees' findings unless they contain errors of principle or are manifestly unreasonable, and should not simply re-agitate factual findings. The builder had challenged the referee's findings about payment rates for extra work on two apartment towers, but the Court found the referee had properly interpreted the contracts and assessed the evidence. However, because the builder identified an unexplained $198,000 discrepancy in the calculations, the Court sent that issue back to the referee to fix, with the builder to pay the referee's costs for the extra work.
AI-generated legal information, not legal advice. Zoe can make mistakes — check the cited source, and for advice about your situation consult a qualified Australian lawyer.
Judgment (8 paragraphs)
Introduction
- By a notice of motion filed on 20 August 2021, the plaintiff, Mikeon Projects Pty Ltd (Mikeon), seeks orders pursuant to Uniform Civil Procedure Rules 2005 (NSW) (UCPR) r 20.24 that (1) the Court reject certain paragraphs of a referee's report prepared by Mr Frank Hicks SC (the Referee) which was originally issued on 18 June 2021 and which was revised to correct a number of minor errors on 30 June 2021 (the Report); (2) the Court refer the matter back for further consideration by the Referee of the issues raised by the rejection of those paragraphs of the Report.