AMOUNT NOW DUE AND
PAYABLE WITHIN 30 DAYS $85,810
less 33,330
_______________________________________________________
$52,480
113 The last two entries on this Progress Claim, "less 33,330" and "$52,480" are handwritten and were obviously made the Council officers. It is clear that by this time controversy had arisen in relation to the plaintiff's involvement in what had been referred to as "Stage 3" relating to the "construction" phase of the Project. The correspondence extracted earlier indicates some friction between Mr Davies and Mr Brownlee in relation to this aspect of the matter. The reduction of $33,330 was a reduction relating to "construction services". Mr Brownlee discussed this progress claim with Mr James and Mr Brownlee wrote the words "Payment OK", signed and dated the authorisation. Mr Brownlee claimed in his evidence that in writing those words he was approving payment of the amount of $52,480 and that he intended to exclude the amount of $33,330 for construction services. The total of the figures in the plaintiff's PSP dated 2 March 1999 for Schematic Design, Design Development and Contract Documentation is $777,800 (exclusive of the $222,200 figure for Construction Services). The plaintiff claims that the Council has only paid it $744,650 for those first three items instead of $777,800, and claims that it owes the plaintiff $33,150.
114 The plaintiff submitted that by its conduct in authorising the payments in respect of the progress claims dated 31 March 1999 and 30 April 1999 the Council accepted that the fee for those three items was $777,800 rather than $744,650. In support of this claim reliance was placed on Empirnall Holdings Pty Limited v Machon Paull Partners Pty Limited (1988) 14 NSWLR 523 in which McHugh JA identified the ultimate issue as whether a reasonable bystander would regard the conduct of the offeree as signalling to the offeror that the offer had been accepted (at 535). The Council submitted that far from signalling acceptance of the plaintiff's 1999 PSP, it made very clear that all that it agreed to was a fee of $744,650 and that the plaintiff is not entitled to construct an agreement out of the correspondence between the parties, when that correspondence categorically deals with the alleged confusion with the Council maintaining that its agreement excluded the amount of $33,150.
115 The Council's letter of 31 March 1999 to the plaintiff in response to its 1999 PSP advised that the Council had given authority to proceed with full documentation of the work "for the agreed fee which has been adjusted for the estimated cost budget being increased" from $13.7 million up to $16.9 million and the deletion of the quantity surveyor's fee for the option (b) proposal. The Council resisted any suggestion that it had been confused about the plaintiff's letter and in its letter of 8 July 1999 purported to explain how it reached the figure of $744,650. It claimed that the plaintiff's fee on a project that would cost $13.7 million was 4.4% at $600,100 and that, on a pro-rata basis for a project that would cost $16.9 million, the plaintiff's fee at 4.4% would be $744,650. That was then broken down into Stage 1 fees of $189,800 and Stage 2 fees of $554,850, totalling $744,650.
116 The letter Mr Davies wrote to Ms Rosser on 9 August 1999 referred to the Council's denial of liability for the payment of $33,330 and did not mention the claim for $33,150. It is obviously unsatisfactory that these parties appear to have fallen out in relation to the plaintiff's fees, however I cannot be satisfied that there was a meeting of minds and an agreement to accept the plaintiff's fee proposal in its 1999 PSP, notwithstanding approval of the progress claims dated 31 March 1999 and 30 April 1999. The Council's letters of 31 March 1999 and 8 July 1999 seem to me to evidence an agreement only to pay the plaintiff the lesser amount of $744,650.
117 The plaintiff's claim for an order that the Council pay it $33,150 fails.
118 Variation claim: As I have said earlier, the only issue remaining for determination in relation to the large number of variation claims is whether the plaintiff is entitled to make a claim for variation CVC04-1. The question of the quantum ($33,000) is not in issue. Clause 13 of the plaintiff's Retainer was in the following terms:
13. If MDA's work is increased or protracted due to causes beyond its control and/or you request variations in the scope of services or to the approved design, a variation fee is payable. MDA will notify you when a variation fee is payable and shall not proceed with the variation until authorised by you. Variation fees will be charged for on a time basis as set out in the Professional Services Proposal unless you request some other basis of assessment, in which case the basis shall be agreed and authorised by you prior to MDA putting the work in hand.
119 One aspect of the plaintiff's entitlement to the fee for a variation is notification to the Council. The Council resists the plaintiff's claim on the basis that the plaintiff failed to give the Council notice of the work it did in relation to the removal of the sprinklers. The Council relied upon Rogers CJ Comm D's decision in Wormald Engineering Pty Limited v Resources Conservations Co International (1988) 8 BCL 158 at 162-163 in support of its submission that the requirement to give the Council notice was a precondition to recovery of the variation fee as opposed to providing an entitlement to the Council to damages for breach of retainer. The clause in that case (clause 40.2) involved the contractor forming an opinion about whether compliance with a superintendent's order was likely to prevent the contractor from, or prejudicing it in, fulfilling any of its obligations under the contract; and having formed such an opinion requiring it to "forthwith notify" the superintendent in writing of that opinion. Thereafter the superintendent was obliged "as speedily as is practicable" to determine whether or not the contractor had to comply with its order.
120 The plaintiff sought to distinguish Wormald on the basis that the clause in question in that case provided for: (a) a sufficiently timely variation order to enable re-programming and the formation of opinion as to value; (b) notice by the contractor of the likely effect of the variation order; and (c) a written direction to proceed with the variation order based upon an informed view about disruption and cost. Rogers J emphasised these "carefully constructed machinery steps" (at 161) that enabled potentially complex issues of disruption and cost to be addressed in advance of the instruction to proceed. It was also submitted that Wormald is limited to the construction of the clause in that contract and is accordingly of limited utility in this case.
121 In the present case clause 13 provided that the plaintiff would notify the Council when a variation fee was payable and that it would not proceed with the variation until it was authorised by the Council. The plaintiff submitted that clause 13 is quite different to the clause under consideration in Wormald in that there was no obligation on the plaintiff to advise the Council of the likely cost and its only obligation was to advise the Council that there would be a cost. The plaintiff also submitted that the failure to give a notice required by clause 13 is not destructive of the plaintiff's right to the fee, rather, it may entitle the Council to claim damages. It was further submitted that there is no implication from the express words of clause 13 that a variation that has been carried out without notice cannot be the subject of a later claim.
122 The plaintiff claims that in any event the Court should be satisfied that notice was given to the Council in the plaintiff's letter to Mr James dated 30 March 1999 which included the following:
We cannot progress any of the documentation on the Council and Police building until fundamental decisions are made in relation to: