McPherson v Mace
[2016] NSWCATAP 198
At a glance
Source factsCourt
NCAT Appeal Panel
Decision date
2016-09-02
Source
Original judgment source is linked above.
Judgment (8 paragraphs)
Background
- These proceedings involved a building claim, made under the Home Building Act 1989 (HB Act). Mr Mace sought compensation from Mr McPherson in respect of 12 items in dispute. On appeal, the award in respect of two items was in dispute, item 2 (the retaining wall), and item 4 (the soffit lining). The Tribunal had allowed $14,299.27 for the rectification of the retaining wall and $5,366.44 for the cost of painting the soffit.
- As we noted in par [26] of the Principal Decision, the appellant raised, in essence, two issues. The first issue was that there was a "constructive failure to exercise jurisdiction", in that the Tribunal gave no consideration to the issue of liability under the contract. The second issue was that the written reasons were inadequate. The essential question for the Appeal Panel was whether or not the Tribunal's reasons for making the awards for each of the two items was adequate. The Appeal Panel considered that it was necessary to consider what "liability and quantum" issues were to be determined and whether those issues were adequately addressed by the Tribunal in its reasons for decision.
- In relation to item 4, the Appeal Panel was not satisfied that the reasons given by the Tribunal were inadequate, and this ground of appeal failed.
- In relation to item 2, as the Appeal Panel was not provided with all of the evidence below, it was unable to resolve the appeal by determining whether or not the award made in relation to item 2 should stand. However, having regard to various matters including deficiencies identified by the Appeal Panel and the fact that there appeared to be a mathematical calculation error in the award originally made, the Appeal Panel varied the original money order to reduce it by an amount of $14,249.47 (being the value of item 2), and directed that the matter be remitted to the Tribunal as originally constituted to provide further reasons in respect of its decision in item 2 and to consider whether the total award should be varied by reason of any mathematical error which we identified above.