Background
4 The plaintiff is the owner of a parcel of land at 12 Arter Avenue Figtree. The land is within the boundaries of Wollongong City Council (the Council). It is the statutory authority responsible for the administration within its area of the Local Government Act 1993. The plaintiff, who is an engineer by profession, made application to the Council for approval to erect a three-story dwelling house on his land. The application was supported by a geotechnical report of Coffey Partners dated 30 October 1995.
5 On 8 December 1995 the Council issued an approval for the erection of the dwelling house subject to conditions that included:
"6. All proposed building works must comply with the geotechnical engineer's report No SCL 5000/1-65 dated 30 October 1995.
7. Before construction is commenced, plans and specifications prepared and endorsed by a suitably qualified and approved structural engineer shall be submitted to, and approved by Council for all reinforced concrete floor slabs, the footings of the proposed structure, the proposed retaining walls, the proposed works required to stabilise the rock and excavation and all structural steel work."
Plans denoted as structural plans were lodged with the Council on 22 October 1996 and approved by an authorised Council officer on 23 October 1996.
6 Work on the site commenced during December 1996. The first work undertaken appears to have been an excavation down to a depth of between seven and eight metres. Amended foundation plans were lodged with the Council in February 1997. These were approved by Council officers. However, in the week following their approval the Council wrote to the plaintiff requesting him to provide an engineer's certificate in relation to the footings and retaining walls. After receipt of such letter, but before providing the certificate that had been requested, the plaintiff completed 21 pad footings and a number of foundation beams and he commenced erection of supporting columns for the building in April 1997. On 17 April 1997, the Council informed him that an inspection had revealed that the works that had been carried out were not in accordance with the building consent issued by the Council and that there were serious concerns about the extent of the excavation that had been carried out. Following a meeting on 18 April 1997 the plaintiff was advised that Coffey Partners had assessed the risk of slope instability at the site as high, and the land as subject to land-slip. This, he was informed, may give rise to major property damage and even loss of life.
7 The plaintiff appears not to have accepted the situation as stated by the Council and proposed to continue with the work. As a consequence the Council sought relief in the Land and Environment Court. This consisted of a declaration that the plaintiff was in breach of condition 6 of the Council's consent and an order that the plaintiff carry out certain nominated remedial works.
8 The proceedings in the Land and Environment Court were heard between 1 and 5 June 1998 by Talbot J. On 19 June 1998 Talbot J delivered his judgment in which he, inter alia, was critical of an expert, Mr Thomas, who had been retained by the Council and called as an expert on its behalf in the proceedings. Notwithstanding such criticism Talbot J held that the Council had proved its case and, subject to the exercise of the Court's discretion, was entitled to the declaration and other relief claimed. Thus breach of condition 6 was determined against the plaintiff. However Talbot J expressed the view that the structure could be completed in a way that ensured that the loads were supported and the site made safe from land-slip. Accordingly he determined that:
"The application will be dismissed if, before 30 September, the (plaintiff) furnishes to the council a design certification by Peter John Yttrup, or such alternative structural engineer who is acceptable to the council, other than Dennis Thomas, in the following form:
That the structure and associated retaining system and details have been designed to support the adjacent land to the level of risk of landslip equivalent to the current condition of 'medium risk' in terms of the AGS Guidelines.
The building shall have a performance expectation similar to normal residential building construction.
The structural system shall comply with relevant design codes."
9 The matter came before Talbot J again on 3 and 5 November 1998 on which last mentioned date His Honour observed that "the parties still find it difficult to have an amicable and mutually satisfactory relationship in regard to the prospect of the structure being completed in a way which is satisfactory, both from a practical point of view and from a legal aspect." The upshot of the further evidence and argument before Talbot J was that on 5 November 1998 he made orders as follows:
"1. That the building partly constructed on the property known as number 12 Arter Avenue, Figtree be demolished and the land restored to its pre-development condition.
2. Order 1 is suspended and to have no effect until further order provided the (plaintiff) complies with the following directions and orders:
1. That a certificate in the form of the certificate dated 4 November 1998, comprising part of exhibit 17, with the calculations and design documents referred to therein attached, be submitted to the Council of the City Wollongong by 4.00pm on 12 November 1998.
2. Working drawings for the proposed residence to be lodged with the Council of the City of Wollongong on or before 4 December 1998 and to be accompanied by a certificate by a suitably qualified and independent structural engineer. That the working drawings are in accordance with the certified calculations and design documents for the proposed residence.
3. All structural works necessary for the support of the adjacent land to be completed on or before 5 April 1999, subject to any reasonable extension of time to take account of only wet weather.
4. That the (plaintiff) provide a clearing certificate to the Council of the City of Wollongong. The certificate is to be by a suitably qualified and independent structural engineer and to the effect that the structural works have been erected in accordance with the certified working drawings."
10 The matter came back before Talbot J yet again in February 1999 and on 17 February, 1999 Order 2 that had been made on 5 November 1998 was varied so as to provide that the order for demolition and restoration of the land should take effect in default of compliance with the following directions and orders:
"(i) working drawings for the floor slabs of levels 1 and 2 confined within the retaining walls of the structure to be lodged with Wollongong City Council on or before 3 March 1999 and to be accompanied by a certificate by a suitably qualified and independent structural engineer that:
(a) the working drawings are in accordance with the certified calculations and design documents for the proposed residence; and
(b) the works when carried out in accordance with the working drawings for the floor slabs of levels 1 and 2 confined within the retaining walls of the structure and the working drawings of the proposed retaining walls and drainage shown in Drawing No. 979-1, 979-2 and 979-3 dated 25 January 1999 together with the existing structure will retain the surrounding lands.
(ii) Working drawings for the remainder of the proposed residence to be lodged with Wollongong City Council on or before 31 March 1999 and to be accompanied by a certificate by a suitably qualified and independent structural engineer that such working drawings are in accordance with the certified calculations and design documents for the proposed residence.
(iii) The (plaintiff) shall commence retaining works on site within one month of lodgment of the working drawings and certificate referred to in Order 2(i) subject only to any reasonable extension of time to take into account of wet weather.
(iv) All structural works necessary for the support of the surrounding lands to be completed within six months of the date of lodgment of the working drawings and certificate referred to in Order 2(i) subject only to any reasonable extension of time to take account of wet weather.
(v) A clearing certificate by a suitably qualified and independent structural engineer that the structural works referred to in Order 2(iv) have been erected in accordance with the certified working drawings be provided to Wollongong City Council by the respondent within one month of the completion of those works."
11 At the hearing of the present application the plaintiff gave evidence that he has complied with orders 2(i)(a) and (b) and 2(ii). This was confirmed in correspondence passing between him and the Council and was not challenged. However the plaintiff also gave evidence of his non-compliance with orders 2(iii), (iv) and (v), the basis for such non-compliance being his claimed impecuniosity.
12 The plaintiff took the proceedings that had been commenced against him by the Council in the Land and Environment Court to the Court of Appeal by which, on 4 April 2001, he was refused leave to appeal and his appeal was dismissed as incompetent. Notwithstanding an admonition by the Court of Appeal to the effect that the plaintiff "should have accepted the decision (of Talbot J) and got on with the job of complying with the spirit, if not the letter, of the Judge's requirement", the plaintiff continued along the path of argumentation and applied for Special Leave to Appeal to the High Court. It was refused on 17 September 2002. The plaintiff then filed a Statement of Claim in this Court on 29 October 2002 in which he joined the Council, Talbot J and the Australia and New Zealand Banking Group Limited (the Bank) as defendants. Subsequently, on 5 March 2003, the action was discontinued as against the Bank. Talbot J has filed a submitting appearance, other than in respect of costs.
13 On 26 June 2003 the plaintiff filed a requisition for a trial with a jury.