(viii) It was in these circumstances of ongoing protests against the Department's decision not to proceed any further with the flood study that the Department's Executive Director wrote the memorandum to the Director-General that I have earlier referred to (see par 94). I infer that it was not until this point of time that the Director-General had personally become involved in the Department's decision not to proceed further with the flood study (meaning by that, that the earlier decisions taken in respect of Condition 67 had been taken by the Director-General's subordinates). Thus, the memorandum expressly sought the Director-General's endorsement of the approach that had been followed by the Department in respect of Condition 67. Rather than summarise the contents of the memorandum, I should quote its content in full (noting that I have earlier quoted (par 96) the "Background" component of the memorandum which immediately preceded the following content):
DISCUSSION
In response, to the Condition, the Department took certain steps in the period February 1999 to July 2000. These, and the manner in which they are considered to satisfy the requirements of the Condition are as follows:
1. Condition No. 67 requires the Applicant to participate in and contribute funds to the preparation of a flood study. Powercoal contributed $30,000 to a flood study and collaborated with the Department during the design of the study.
2. The Condition No. 67 requires the study to be set up to determine the 1:100 year flood, and other such matters considered necessary in consultation with Council and DLWC. The study was designed to determine the 1:100 year flood and to provide information about subsidence effects. Lake Macquarie City Council (the Council in the Condition) and the Department of Land and Water Conservation (DLWC) were consulted in the design and implementation of the study on multiple occasions. Mr Preston emphasised that neither was required to sign off on the stud but merely to be consulted.
3. Condition No. 67 requires the Director-General to select a consultant to conduct the flood study. The Director-General commissioned an independent expert consultancy, Water Research Laboratory (WRL) of the University of New South Wales. The objects of the study were is (sic) accordance with the Condition
4. The study was to be completed within 6 months of the date of consent. This time frame proved to be unrealistic and was not met. Mr Preston has indicated that these time provisions can be considered directory and not mandatory, because action had been clearly initiated through the study.
5. The amount of reasonable funding required from the Applicant was determined as indicated under 1
6. Definition of the flood hazard included an extensive public consultation and submission process that was managed by the consultant, WRL.
7. The study is to include a public consultation and submission process. Public consultation has been extensive and has continued throughout the period since Approval was given.
8. The Condition requires that the results of the study be incorporated into a revision of the Water Management Plan. The Department received a Water Management Sub Plan in September 1999 and this was subsequently approved by the Department. In doing so, the Department determined that the Plan was consistent with the findings of the flood study.
9. The study was undertaken to the satisfaction of the Director-General and its report made available to the DLWC, Council and the Community Consultative Committee in June 2000. In addition, briefing sessions were held by the Department with the Consultative Committee and the Council.
10. It is argued that the requirements of the Condition have been completely satisfied by the steps described above. Advice from Mr Preston confirms that the Director-General has the discretion to decide upon the nature of the studies that are to be carried out, so long as the other tests stipulated by the Conditions are met.
11. During the study by WRL, the consultant indicated that it was unlikely that the modelling conducted for the EIS would be varied by this work unless there had been a major error in the original data processing. Also, in August 2001, modified Consent Conditions were approved and these recognised that the location and configuration of longwalls would not be known with any accuracy until closer to the time mining would commence. Consequently, the Director-General concluded that continuation of this study would be a misuse of public funds and the study was terminated.
12. Following this, a concern was raised by the Mandalong Valley community that all three stages of the proposed study had not been completed. In addressing this concern a separate independent peer review was commenced by Lawson and Treloar on behalf of the Department, but is currently waiting on the transfer of date from Powercoal. However, it is considered unlikely that this study will provide any information which would change the existing understanding of the 1:100 year flood profile. Consequently, the Department now considers that continuation with any flood study is inappropriate at this time but that once the configuration of longwalls is known more accurately, it may be appropriate to recommence the study at that time.
RECOMMENDATION
That the Director-General form the opinion that the response by the Department the requirements specified in the Conditions of Consent relating to the characterisation of the flood risk for the Mandalong Mine, is appropriate for compliance with the Condition to be considered to have been achieved.