Maloney v Blue Haven Pools South Pty Ltd
[2019] NSWCATCD 17
At a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2018-10-31
Source
Original judgment source is linked above.
Judgment (16 paragraphs)
Application
- This dispute arises from a contract dated 7 January 2016 between the applicant home owner ("Ms Maloney") and respondent builder ("Blue Haven") for the construction of an in- ground swimming pool. When excavation began on 6 July 2016 water inundated the site and construction ceased. The parties have been in dispute since then as to who is contractually liable to pay the additional costs necessary to enable construction of the pool. Ms Maloney alleges that Blue Haven is liable to pay those costs, whilst Blue Haven argues that the costs are payable by Ms Maloney.
- In the application filed on 23 February 2018 Ms Maloney sought an order that Blue Haven construct the pool in accordance with the contract. However by letter dated 19 September 2018 Ms Maloney alleged that Blue Haven had repudiated the contract. She purported to accept the repudiation and terminated the contract. She now seeks an order that Blue Haven pay her damages of $182,332.23.
- Blue Haven opposes the order sought. It states that it has at all times been willing and able to construct the pool upon acceptance by Ms Maloney of her obligation to pay the additional costs. It argues that Ms Maloney was not entitled to terminate the contract and that in doing so she repudiated the contract. Blue Haven says that it accepted Ms Maloney's repudiation and itself terminated the contract. On that basis Blue Haven argues that it is released from the contract. It seeks that the application be dismissed.