(2) Whether the Magistrate erred in not finding there was an implied term of the contract
71The Magistrate found made a finding that there was one contract which included the construction of the lift core. The second ground of appeal relates to the Magistrate's decision in not finding that it was an implied term of the contract that work performed by Jantune would match the existing work at the site; namely, that the blocks supplied by Jantune would match the existing blocks which were face blocks (the alleged implied term).
72Counsel for Maksim submitted that the alleged implied term was breached because existing blocks were grey face blocks but the lift and stair core blocks supplied by Jantune were grey retaining wall blocks.
73Senior counsel for Maksim drew this Court's attention to Dillon v Gosford City Council [2011] NSWCA 328 at [45] to [46] where Basten JA (with whom Macfarlan JA and Handley AJA agreed) stated:
"[45] In an attempt to identify an issue of law in respect of what was almost entirely a factual assessment, the appellants took the court to various paragraphs in the joint expert report of 25 September 2009. These paragraphs involved, primarily, assessment of apportionment based on various models of possible flooding and the redirection of the flow of water. The appellants sought to challenge the bases of this assessment. Because they had been relied upon by the experts and were accepted by the primary judge, it was submitted that they thereby became "material considerations", whereas the appellants contended that they were "irrelevant matter" in relation to the question of the reasonableness of the disturbance claim: written submissions at para 82.
[46] This argument does not identify any question of law, let alone one erroneously determined. It appears to invoke the principle that an administrative decision, at least, may be set aside if the decision-maker has taken into account "irrelevant considerations". However, that principle provides no warrant for the court to inquire into findings of fact. Rather, it is limited to the identification, by reference to the statute or other legal principles under which the decision-maker acted, of some factor as a prohibited consideration, in the sense that, as a matter of law, it must be excluded from the decision-making process: M Aronson, B Dyer and M Groves, Judicial Review of Administrative Action (4th ed, 2009), p 282. Whether the modelling was done well or badly and whether different outcomes might have been achieved, are beside the point. It is not possible to say that the statutory scheme precluded the court taking into account the results of such an exercise. The challenge is misconceived and must be rejected."
74Counsel for Maksim submitted that that the term that the work on the lift core would match existing work was a term similar to an implied term by law. The said implied term requires a contractor to use reasonable care in doing the work and to supply materials which are of "good quality" and "reasonably fit for the purpose" for which they are supplied (GH Myers & Co v Brent Cross Service Co [1934] 1 KB 46 at 55 (approved by Young & Marten Ltd v McManus Childs Ltd [1969] 1 AC 454; adopted by Reg Glass Pty Ltd v Rivers Locking Systems (1968) 120 CLR 516).
75To support this proposition, counsel for Maksim drew this Court's attention to a passage in an extract from a letter of Mr Glew where he stated:
"I will concede my error. I believe I have misunderstood when we discussed the possible painting of the blocks, when looking at the option of charcoal which we considered would not possibly give a uniform finish."
76According to counsel for Maksim, Mr Glew's letter was a concession that the wrong blocks were used. That statement forms part of the factual matrix but this "concession" was not in relation to the terms of the contract but rather an apology for a previous conversation. The Magistrate was correct finding that there was no oral variation of the contract after considering the alleged concession.
77Counsel for Jantune submitted that there was no error in the Magistrate's finding that there was no implied term in the contract with respect to the blocks and that the Magistrate's finding was a finding of fact. On this topic, the Magistrate identified the issue as whether the wrong blocks were laid and if so was this a breach of contract. Her Honour provided detailed reasoning on this topic including reference to conversations between Mr Glew, Mr Nott and Mr Di Francesco and documentation on this topic and her reasons for preferring Mr Glew's evidence. Her Honour's reasoning appears at pages 9 to 12 of her judgment. It is not necessary to reproduce it in detail.
78Mr Nott's evidence was that the Council approved plans for the lift core specified "concrete block walls, selected paint finish". Mr Glew ordered concrete retaining wall blocks, also called standard blocks that were coloured grey and that these blocks were consistent with the architectural plans. Jantune was not contracted to paint the blocks.
79The Magistrate (J T9-10) stated:
"In late October the first delivery of block arrived on site. In November 2010 Jantune commenced block laying, however it was Glew's evidence that in August of 2010 in a meeting with Mr Nott he was handed the hand drawn specification and Nott that said:
'This is how I want the block work to look on the outside. I want charcoal blocks on the exterior of the lift core.'
Glew says that he told Nott:
'Don't do that because after you clean charcoal blocks they end up faded and different colours. They are not uniform and they look bad. Charcoal blocks increase the costs of materials. You are better off with standard grey blocks from Amber and painting them and you will get a consistent colour. If you want you can paint the charcoal.'
He says that Nott replied, 'I'll think about that.' In oral evidence Mr Nott agreed that it was possible that this conversation took place but denied that he said that he would think about that. He says that he said:
'The blocks should be charcoal. I don't want a painted finish due to the ongoing maintenance required' he agrees that, 'Possibly no construction certificate was approved at the time of this conversation.'
Mr Glew says that after the blocks were delivered on the site that Mr Di Francesco said to him at a time prior to their being laid in November of 2010, that, 'Warwick told me the blocks were the wrong colour' he says that he replied:
'I told Warwick we should get grey blocks and paint them. Any block needs to be sealed, but I can return them and replace them with charcoal if you want' and Mr Di Francesco said, 'No, Warwick said we don't have time, just go ahead and lay those blocks. We don't want to delay the job.'"
80This version of the conversation was disputed by Mr Di Francesco. Mr Di Francesco evidence is that he said:
"The blocks are the wrong colour, they should be charcoal", he says that Glew replied, "The plan shows paint finish, I discussed this with Warwick" and that he told Glew, "Don't start work, call Warwick."
81The Magistrate noted that Mr Di Francesco did not complain with respect to the blocks in any calls or conversations with Mr Glew face to face (J T11.30).
82The Magistrate concluded (J T12-13):
"... I accept Mr Glew's evidence wherever it deviates from that of Mr Nott and Mr Di Francesco. In particular, I accept that in the meeting in August of 2010 when Mr Nott expressed his preference for charcoal blocks that Mr Glew advised him, amongst other things, that:
'You are better off with standard grey blocks from Amber and painting them. You will get a consistent colour. If you want you can paint them charcoal' and that Mr Nott replied, 'I will think about that.'
This is consistent with the annexure to Mr Glew's letter to Mr Nott of 11 March where Glew says, 'I will concede my error', and goes on to explain that that be believes he misunderstood Mr Nott to have rejected the idea of charcoal blocks because of the issues raised with respect to the comparative benefits of standard grey blocks from Amber. I accept the evidence of Mr Glew that after the blocks were delivered he had a conversation with Mr Di Francesco in which he said:
'I told Warwick we should get grey blocks and paint them. Any block needs to be sealed, but I can return them and replace them with charcoal if you want' and Mr Di Francesco said, 'No, Warwick said we don't have time, just go ahead and lay those blocks. We don't want to delay the job.'
I accept Mr Glew's evidence that it was not until the meeting of 21 February 2011 that Mr Nott raised objections to the block work. While Mr Nott's evidence is effectively that he allowed the laying of the wrong blocks but did so in the belief that the blocks would not need painting, I accept the evidence of Mr Glew that he had raised the issue of the blocks needing to be painted with both Mr Di Francesco and Mr Nott prior to their being laid and I accept Glew's evidence that in February 20911 when the roof was approaching completion that Glew said to Mr Di Francesco, "The lift core won't be water proofed if you don't paint it" and that just prior to the scaffolding coming down that Mr Glew said to Mr Di Francesco, "Do you want to paint the core before we pull the scaffolding down?"
The blocks delivered to the site were consistent with the written specifications. ...
I am satisfied that the conduct of the parties and the dealing between them objectively demonstrated that the representatives of Maksim, in full knowledge of the nature of the blocks being laid, allowed them to be laid. On the evidence as I have found I do not find that there was an oral variation as to the bocks to be supplied from that in the written specifications. There was no breach of contract in this regard."
83The Magistrate preferred the evidence of Mr Glew over that of Mr Di Francesco. She gave cogent reasons as to why she did so. The Magistrate stated that Mr Di Francesco's evidence was marked by an inability to recall events and alleged conversations and that his evidence that he did not have a supervisory role with regards to Jantune unbelievable. On Mr Di Francesco's own evidence he had regular discussions with Mr Nott and was dealing with Mr Glew regarding the works on site. By contrast, the Magistrate found that Mr Glew's evidence to be definite and consistent. Mr Glew's evidence that before the blocks were laid, he offered to return and replace them with charcoal blocks was corroborated by his letter of 11 March 2011 (J T11-12).
84It is open to the Magistrate upon the evidence to come to the decision that there was no breach of the "implied term". This ground of appeal fails.
85So far as any other grounds of appeal are concerned, they raise factual issues or issues of mixed fact and law for which I would not grant leave. This is because there is in reality only a modest amount in dispute. There has already been a large amount of legal expenses incurred by both parties to date and three days of Local Court time has already been given to this dispute. The issues raised do not concern any matter of public policy.
86Even if I am wrong on the first ground of appeal, it is my view that there is no utility in remitting this matter to the Local Court to be determined according to law. The hearing has already taken three days in the Local Court. It is common ground that the contract was a "do and charge" one. In the exercise of my discretion, with the relatively modest amount in dispute and the costs already incurred by the parties, I would decline to remit the matter to the Local Court.
87The result is that the appeal is dismissed. The order of her Honour Magistrate McGlynn dated 24 April 2013 is affirmed. The amended summons filed 12 July 2013 is dismissed.
88Costs are discretionary. Costs normally follow the event. The plaintiffs are to pay the first defendant's costs on an ordinary basis as agreed or assessed.