Correspondence between 23 October 2000 and 12 December 2000 (Exhibit A, Vol 10, pp 3872-3875) establish that Tract Consultants Pty Ltd was engaged to carry out the work required under condition 19.
108 The whole of the evidence establishes, in my opinion, that this was work which, in breach of the 96 agreements, Macquarie failed to do. I therefore hold Macquarie liable to pay Area Health the total sum of $2,930 for these components, plus interest.
109 The invoice from Ove Arup & Partners of 9 April 2001 for $720 states that it is "… For undertaking site survey and documentation of Mallet Street pedestrian refuge". The invoice from Ozpave of 26 June 2002 for $5,995 states that it is for "… the preparation and pouring of Concrete Pedestrian Refuge Island …".
110 Condition 11 required provision of a pedestrian refuge complete with pram ramps in Mallet Street prior to operation of the car park. Following repossession, Atkinson Capital Insight Pty Ltd acknowledged the need for compliance in its letter to council of 19 June 2000. Thereafter there was correspondence with South Sydney City Council and Marrickville Council concerning this work, until approval was obtained and the work was carried out as described in the invoices (Exhibit A, Vol 10).
111 The description of the work in each invoice supports the finding, which I make, that each was for work necessitated by Macquarie's default. The correspondence puts the matter beyond doubt. It follows that Macquarie is liable to Area Health for the amounts paid under them in the total sum of $6,715, plus interest.
112 In conclusion, I hold that the total amount for which Macquarie is liable to Area Health under claim A(v) is $9,645 plus interest.
B Damages for expenditure in negotiating with South Sydney Council and applying to Land and Environment Court in relation to the car park
113 Area Health claims the sum of $22,795.60 as detailed in the summary of Exhibit 25. It is accepted that the costs were incurred and are reasonable.
114 The relevant background is recorded in the judgment of 23 July 2008 as follows:
"658. On 24 August 1999 council informed Macquarie that it could not grant an interim certificate of occupancy for the car park and prohibited its operation pending fulfilment of outstanding conditions. The default notices were given on 13 September and 15 September 1999. The car park was opened unlawfully by Macquarie on 24 September 1999. The events of default were denied in Mr Klinger's letter of 29 September 1999, and Macquarie took no action for remediation or rectification under cl 16.6 car park lease and cl 17.6 hospital lease."
"439. On 10 February [2000] council informed its solicitors that before occupancy would be permitted, Macquarie was required to comply with all conditions referred to in its letter of 1 November 1999.
440. On 17 March [2000] the notices of termination were served on Macquarie, and Area Health took possession of the car park. This happened upon the expiry of the six month period within which Macquarie was allowed to sell and assign its interests in the leases (cl 16.6(d) car park lease and cl 17.6(d) hospital lease).
441. On 16 June [2000] the Land and Environment Court, in proceedings initiated by Pace and taken over by Area Health ordered, by consent, variations to the development consent conditions for the car park which deferred the requirement for building traffic lights, and the need for Area Health to grant an easement for Link Road. The Court also ordered deletion of condition 2 which required substantial commencement of the adjoining private hospital prior to issuing a certificate of classification by council to allow the operation of the car park.
442. On 23 June [2000] council issued an interim certificate of occupancy for the car park for 600 spaces.
…
659. On 1 November 1999 Macquarie was ordered to cease use of the car park. On 21 December 1999 Macquarie sought council's permission to operate the car park with 600 spaces, and relief from compliance with some of the approval conditions, including condition 2, in circumstances that there was no "… reasonable assurance a private hospital will be constructed on the site". It appears that it was with regard to this changed circumstance that the Land and Environment Court ordered the conditions to be varied or deleted, thereby enabling council on 23 June 2000 to permit Area Health to use the car park for 600 spaces. In other words, the situation at this time was brought about by Macquarie's defaults which resulted in re-entry under the leases."
115 It should be tolerably plain from the above that Macquarie's defaults which led to termination directly resulted in the need for Area Health to negotiate with council, and to proceed in the Land and Environment Court, to enable it to lawfully operate the car park. This it did with the advice and assistance of its solicitors, Bolzan & Dimitri, and consultants Ove Arup & Partners. The orders made by consent by the Land and Environment Court on 16 June 2000 paved the way for the provision of the occupation certificate on 23 June 2000. The orders, inter alia, postponed compliance with conditions 8, 13 and 15 for periods of 12 months, 9 months and 12 months respectively.
116 The invoice from Bolzan & Dimitri of 19 June 2000 for $17,110.60 was for professional services between 11 May and 19 June 2000 for dealing with council, and involvement in the proceedings in the Land and Environment Court.
117 On 22 June 2000 Area Health paid council the sum of $75 as a fee for the occupation certificate for the car park.
118 The invoice of Ove Arup & Partners of 23 June 2000 for $950 was for the preparation of evidence on traffic for the Land and Environment Court, and subsequent advice on approval conditions. Their invoice of 1 January 2001 for $4,660 was for undertaking traffic surveys and documentation of results.
119 Macquarie denied liability on the ground that (submission 25.05.07 ch 4 par 67):
"67. Macquarie does, however, submit that necessarily encompassed by the claim is a recognition that the costs of obtaining the interim occupation certificate can only be pursed in lieu of a claim for work to comply with all Council conditions, irrespective of whether or not they were required in order to secure the interim occupation certificate. In other works, it cannot be right to say that Macquarie was obliged to comply with all of the Conditions of Consent of Council, irrespective of whether or not they had any relevance to the opening of the car park, as well as a claim for altering the conditions of consent to permit the early occupation of the car park."
120 To the extent that I understand the submission, in my opinion it should be rejected. It overlooks the self-evident intended scope and purpose of the indemnity provisions. I am satisfied that Area Health's expenditure under the invoices which evidence this claim is within the description of a loss arising or any reasonable cost incurred in connection with Macquarie's default under, for example, cl 7.8(a) of the construction deed. Once the connection is established, as it has been in this case, so too is Macquarie's liability.
121 I therefore hold that Macquarie is liable to Area Health in the sum of $22,795.60 as claimed, plus interest.
C Damages for expenditure for quality testing, rectifying defects in respect of construction, and completion of the car park and New Hospital Road
122 Area Health claims the sum of $37,928.56 as detailed in the summary of Exhibit 25.
123 In support of each amount claimed under this head, Area Health submitted that it was for expenditure incurred as a result of Macquarie's breach of cl 2.1 and cl 3.1 of the construction deed to complete construction of the car park and ancillary works.
124 Macquarie denied liability on the ground that there is no evidence that the invoices were for work done in connection with its defaults under the 96 agreements, or for the purpose of remedying defective work. In addition, it submitted that the invoices were for work which Macquarie was prevented from doing by reason of the termination and/or was work which was an ordinary incident of possession of the car park and/or arose from the operation of the car park post termination.
125 Some background matters have particular relevance to the claim overall. Macquarie was in breach in failing to complete construction of the car park by 30 June 1999. At the time of re-entry on 17 March 2000 construction of the car park was incomplete, and its operation by Macquarie was unlawful. As a result, it became necessary for Area Health to undertake work for completion of the car park to the stage where its operation was lawful. Such work resulted in the issuing of the occupation certificate on 23 June 2000, which permitted lawful operation of the car park. Further work was required, and undertaken, to comply with outstanding consent conditions, and to rectify defective work left by Macquarie.
126 I turn to each component of this claim separately.
127 The invoice from K & W Signs of 14 June 2000 for $18,670 was for the installation of traffic signs at the car park. Consent conditions 33 and 34 required this work be done. I infer that it was necessary for the lawful operation of the car park. I find that it was work which Macquarie failed to do and, accordingly, hold Macquarie liable to pay Area Health the sum of $18,670 for these items, plus interest.
128 The invoice from Warren Smith & Partners of 15 June 2000 for $700 was for the provision of design and construction certification for the installed storm water drainage system. In my opinion it is highly probable that this work was necessary to ensure compliance with consent condition 29 which required completion and certification of a storm water drainage system. I find that Macquarie's default obliged Area Health to undertake and pay for this work. It follows that Macquarie is liable to pay Area Health the sum of $700 for this item, plus interest.
129 The invoice from Scott Wilson Irwin Johnston Pty Ltd of 30 June 2000 for $1,260 is for the certification of mechanical and electrical services at the car park. It is self-evident that the construction and operation of the car park required the installation of many and various services of such kinds. I infer that certification of such services was required in order to ensure compliance with relevant consent conditions e.g. conditions 43, 44, and 45 which related to the ventilation system. I am satisfied that the work the subject of this invoice was work which Macquarie, in breach, failed to do. Accordingly, Macquarie is liable to pay Area Health the cost of this item in the sum of $1,260, plus interest.
130 The invoice from K & W Signs of 26 June 2000 for $2,565 was for the installation of traffic signs relating to the use of the car park. For reasons given in upholding Area Health's claim in respect of the invoice from K & W Signs of 14 June 2000, I hold Macquarie liable to pay Area Health the sum of $2,565 for this item, plus interest.
131 The invoice from Network Security Pty Ltd of 6 September 2000 for $867.90 was for the installation of a boom gate and a controller board, and for the reconditioning of a boom gate. Consent condition 31 envisaged the installation of boom gates; condition 1(a) of the occupation certificate required installation of boom gates within fourteen days. In my opinion the work described in the invoice was work Area Health was obliged to pay for as a result of Macquarie's default. I hold Macquarie liable to pay Area Health the sum of $867.90 for this item, plus interest.
132 The invoice from Northrop Holmes of 27 October 2000 for $360 was for professional services in providing an inspection and report regarding a cracked wall in the car park. With regard to the proximity of the date of the invoice to the cessation of work by Macquarie before construction was completed, absent evidence otherwise, I find it highly probable that the wall became cracked because of Macquarie's defective workmanship. I therefore find Macquarie is liable to pay Area Health the sum of $360 for this item, plus interest.
133 The invoice from Northrop Holmes of 27 November 2000 for $300 was for professional services in providing an inspection and details regarding remedial work to concrete spalling. Adopting an approach similar to that taken in dealing with the last mentioned item, I am satisfied that the invoice demonstrates that the concrete spalling required remediation, which, absent evidence otherwise, probably resulted from Macquarie's defective workmanship. I therefore find Macquarie is liable to pay Area Health the sum of $300 for this item, plus interest.
134 The invoice from Unisearch of 5 March 2001 for $1,017.66 was for an inspection and report for the measurement of slip resistance at the car park. Absent evidence otherwise, I accept Area Health's submission that it is probable that this work was for rectification of the structure left by Macquarie. Alternatively, it is open to conclude that it was work undertaken within a reasonable time after the issue of the occupation certificate to ascertain whether or not the degree of slip resistance complied with applicable standards for the operation of this car park and, if so, I find it was reasonable in the circumstances for Area Health to have it done.
135 I find Macquarie liable to pay Area Health the sum of $1,017.66 for this item, plus interest.
136 The invoice from Network Security Pty Ltd of 8 August 2000 for $950 was for the variation to access control by moving the boom gate to the next entrance and related matters. With regard to the description of the work and to the date on which it was done as shown on the invoice, I am persuaded that it was necessary for the efficient operation of the car park, and also as envisaged by consent condition 31 which required location of boom gates to be well inside the site to prevent vehicles queuing on the street.
137 I therefore find Macquarie liable to pay Area Health the sum of $950 for this item, plus interest.
138 The account from Seton Australia paid 6 June 2001 for $1,590 was for yellow speed humps. I find, as a matter of common knowledge, that these devices are usually an inherent part of an operating car park which are included for the purposes of traffic management and public safety. I conclude that completion of construction of the car park in this case involved installation of the speed humps the subject of this account. Absent evidence otherwise, I find that Macquarie failed in its obligation to install them. It follows that Macquarie is liable to pay Area Health the sum of $1,590 for this item, plus interest.
139 The invoice from Network Security Pty Ltd of 11 April 2001 for $6,833 is for cabling for transmission of the video signal to the camera at the car park. The description in the invoice supports the inference that the camera had been left, presumably by Macquarie, either without the necessary cabling, or with cabling so defective as to require replacement. In any event, I am satisfied the work was necessary for the useful operation of the camera which would have been an inherent feature of the car park had Macquarie proceeded to complete its construction. I am satisfied that the need for this work to be done resulted from Macquarie's failure to complete. I therefore find Macquarie is liable to pay Area Health the sum of $6,833 for this item, plus interest.
140 The invoice from Northrop Holmes of 28 June 2002 for $585 was for professional services by way of a preliminary inspection, and a report and remedial details in relation to "Queen Mary Car Park". There is no other evidence about this item and the circumstances in which Area Health arranged for this work were left as matters for speculation. In my opinion it does not support a finding that Macquarie should be liable to Area Health for its costs. Area Health's claim for this item is rejected.
141 The invoices from Stemar Engineering of 10 January 2003 for the total sum of $2,230 were for the installation of "Hilti" hollow block wall fixings, and remedial work by the installation of steel work to concrete stairs and an adjacent concrete block wall. Area Health submitted that these descriptions from the invoices support the inference that structural defects in the concrete stairs were then appearing, and required support, and that reinforcement to the block walls was required by means of "Hilti" fixings which justified recovery from Macquarie. Similar to the conclusion as to the last mentioned item, in my opinion this evidence is insufficient to discharge Area Health's onus of proof that its expenditure on these items is attributable to Macquarie's default. I reject the claims for these items.
142 In conclusion, I hold that the total amount for which Macquarie is liable to Area Health under claim C is $35,113.56, plus interest.
Summary of the claim for damages under par 8 of the cross-claim
143 The amounts, plus interest, for which Macquarie is liable to pay Area Health under this claim are:
(1) A(i) $21,260
(2) A(ii) $360,130
(3) A(iii) $353,966.18
(4) A(v) $9,645
Total $745,001.18