© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2020] NSWCATAP 53
NCAT Appeal Panel
2020-01-29
Original judgment source is linked above.
ty Ltd [2019] HCA 32 Parkdale Custom Built Furniture v Buku (1982) 149 CLR 191 Prendergast v Western Murray Irrigation Ltd [2014] NSWCATAP 69 Progressive Mailing House Pty Ltd v Tabali Pty Ltd (1985) 157 CLR 17 McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457 Shevill v Builders Licensing Board (1982) 149 CLR 620 Simmonds v Rust; Rust v Simmonds [2018] NSWCATCD 75 Yorke v Lucas (1985) 158 CLR 661 Texts Cited: None Category: Principal judgment Parties: Gregory Ross Boughton (Appellant - Builder) Dale Longbottom and Natalie Longbottom (Respondents - Home Owners) Representation: Counsel: A. Justice for the Builder J. Weightman for the Home Owners
Solicitors: Peter Rogers, Moroney Rutter & Mantach Lawyers, for the Builder Nicholas Pidcoc, Fletcher Pidcoc Lawyers, for the Home Owners File Number(s): AP19/46638; AP19/50591 Publication restriction: Nil Decision under appeal Court or tribunal: NSW Civil and Administrative Tribunal Jurisdiction: Consumer and Commercial Division Citation: Boughton v Longbottom [2019] NSWCATCD Date of Decision: 18 September 2019 Before: K. Ross, Senior Member
Introduction
Background
The findings of the Tribunal
(1) On 4 September 2016 the Builder attended the site to measure up and order materials. Physical work commenced on site on 5 October 2016. (2) When the builder went onto the roof at the commencement of the work he determined that, in his view, the Burston plans were incorrect in respect of the ridge at the apex. He determined that he could not build the roof shown on the Burston plans without removing the entire roof structure (including the pressed metal ceilings) and reconstructing it. (3) At some time after commencement of the work, (the Builder says shortly after and the Home Owner says after the frames were erected) the Builder had a conversation with the Home Owner Natalie Longbottom to the effect: GB "I can't build the roof the way your draftsman has drawn it without replacing the whole roof. That would mean taking out the pressed metal ceilings. NL "We don't want that" GB "I'll see if I can get an alternate design and come back to you". (4) On 18 October 2016 the Builder sent an email to the Home Owners in respect of 3 issues claimed as variations. On 19 October 2016 the Home Owners emailed acceptance of those variations. On 4 December 2016 the Builder raised Variation 1 in respect of them in an amount of $4330.00. (5) On 14 November 2016 the Builder sent an email to the Home Owners attaching a copy of amended roof plans and a 3D design for the trusses. (6) On 15 November 2016: (a) the Builder sent a further email to the Home Owners requesting approval for the changes to the roof. The email stated that the pitch on the rear roof would be reduced and it would "look different to the plans", and (b) the Home Owners emailed acceptance of the changes to the roof. (7) The Builder constructed the roof in accordance with the amended plans. (8) On 9 and 10 December 2016 the parties exchanged text messages in respect of a builder's blanket and cable. On 9 December 2016 the Builder raised variation 2 in respect of these items, as well as removal of double ceilings and cable for A/C, in an amount of $3820.00. (9) On 19 December 2016 the Builder sent an email to the Home Owners proposing a variation in respect of four issues: (a) double thickness walls in and around fire place and alterations to wall $1210.00 incl GST (b) complete minor repairs to saddle trusses in existing roof $870.00 incl GST (c) levelling kitchen floor by replacing bearers and joists $2956.00 incl GST (d) excess on provisional allowance for tiles $513.00 incl GST (10) On 20 December 2016 a meeting was held on site. Present were the Home Owners, the Builder, Graham Burston and Natalie Longbottom's father. (11) On 21 December 2016 the Home Owners requested that work on site be suspended to enable them to seek advice. The Builder responded by stating that he agreed subject to a number of conditions: (a) That the Home Owners engage clause 22 of the contract in question of dispute resolution, (b) That the plasterers be allowed to complete their work, and (c) That access be permitted to enable the site to be cleaned, items removed and the garage cleared. (12) On 22 December 2016 the Builder's plasterers were denied access to the Site by the Home Owners. (13) On 23 December 2016 the Builder sent an email to the Home Owners seeking payment of the invoices for variations 1 and 2 and submitting an invoice for progress claim 3. (14) On 24 December 2016 the Home Owners sent an email disputing the claims for payment and advising that a complaint had been lodged with Department of Fair Trading. (15) On 6 January 2017 the Builder's then solicitors wrote to the Home Owners stating that if payment of $51,336.25 was not made by 20 January 2017, the Builder would terminate the contract. (16) On 20 January 2017 the Home Owner's solicitor wrote to the Builder's solicitor disputing that the monies claimed by the builder were due and owing and disputing that the Builder was entitled to terminate the contract. (17) On 24 January 2017 the Home Owners' solicitor gave the Builder's solicitor a notice of dispute under clause 22 of the contract. (18) By notice dated 25 January 2017 (apparently attaching an invoice for PC items in an amount of $6877.66 dated 30 January 2017) the Builder's solicitor responded to the Home Owner's notice and terminated the contract."
Scope and nature of internal appeals
Builder's Submissions
The Home Owners' Submissions
Builder's Submissions in Reply
Consideration
Ground 4: Termination pursuant to clause 21 of the contract
Builder's Submissions
Home Owners' Submissions
Consideration
Ground 5: Interest
Home Owners' Cross-Appeal
The Tribunal's Reasoning
The Home Owners' Submissions
The Builder's Submissions
Consideration
Submissions of the Builder
Submissions of the Home Owners
Consideration
ORDERS In respect of appeal AP19/50591, the orders will be: 1. Leave to appeal is refused. 2. Appeal is dismissed. In respect of appeal AP19/46638: 1. The appeal is allowed in part. 2. Set aside order 1 of the orders of K. Ross, Senior Member, made 18 September 2019. 3. In lieu thereof, Gregory Ross Boughton is to pay to Dale Longbottom and Natalie Longbottom the sum of $51,719.01. In respect of both AP19/46638 and AP19/50591, the following directions are made: 1. Each party is to give to the Appeal Panel and the other party any application for costs, including in respect of costs of the hearing at first instance, and submissions in support within 14 days of these orders. 2. Each party is to give to the Appeal Panel and the other party any submissions in reply within 14 days thereafter. 3. Any such submissions shall include submissions as to whether the Appeal Panel should make an order dispensing with a hearing in respect of the issue of costs pursuant to s.50(3) of the Civil and Administrative Tribunal Act 2013 (NSW).
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales. Registrar DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 23 March 2020
Longbottom
Boughton
[2019] NSWCA 3007
(2000) 201 CLR 520
(1986) 162 CLR 1
(1984) 2 FCR 82
(1978) 140 CLR 216
(1982) 149 CLR 191
(1985) 157 CLR 17
(1933) 48 CLR 457
(1982) 149 CLR 620
(1985) 158 CLR 661
(1992) 37 FCR 445