NSWNSWCATCD
Long & Fitzpatrick v Wollongong Homes Pty Ltd
[2015] NSWCATCD 141
NCAT Consumer and Commercial|2014-12-02|Before: Mr J
View original sourceAt a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2014-12-02
Before
Mr J
Source
Original judgment source is linked above.
Judgment (10 paragraphs)
[1]
Reasons for the DecisioN
- The applicants in these reasons will be referred to as the homeowners and the respondent as the builder.
- The application was lodged with the Registry on 14 February 2013. The matter was heard over two days on 2 December 2014 and 18 March 2015.
- The homeowner's initial application was for the builder to undertake rectification works for defects in the premises. On 28 November 2013, the homeowners amended their application seeking a monetary amount of $200,000.00 for breach of statutory warranty pursuant to section 18E of the Home Building Act (NSW) 1989 (The Act). They were also seeking damages for defects in negligence that by their own admissions was not materially different to the scope of the breach of statutory warranties contained in the Act. The $200,000.00 amount is for the following: 1. Rectification and relocation costs; 2. Interest 3. Costs
- The amount now claimed by the applicant for rectification costs has now been revised to $101,116.88.
[2]
Jurisdiction
- It is agreed that the parties entered into a contract dated 15 October 2010 for the builder to construct a single level home for the homeowners for an amount of $248,780.69. That contract was provided to the Tribunal. It is also not in dispute that construction commenced in January 2011 and the Tribunal finds it was completed on about 16 July 2011 when the property was handed over by the applicant. It should be noted that that the applicant had complained in relation to the defective brickwork before handover, but in any case handover occurred.