Items 2 & 3: Demolish Existing Brickwork and Erect New Brick Work
- It is clear from the conclave report and the handwritten notes initialled by the experts at conclave that where relevant responsibility was agreed, rectification was agreed and cost were agreed. In relation to item 3 and the remedial work, it is even noted what that the remedial work includes:
-install remedial ties through masonry
- render existing facades
- coat with heavy build acrylic to manufacturer's specifications
- install and trim door flashings
- It was agreed at the conclave that the brickwork was a defect and the amounts for rectification relating to item 2 was included as part of item 3 and the agreed amount was $15,170.00 Mr Campbell now states it will cost $48,777.10 for removal and replacement of the new brickwork and render. He states that certain items were not allowed at the conclave.
- Mr Connor, after indicating that an amount was agreed at the conclave states the following:
If Found
I have reviewed the Bill of Quantities (BOQ) prepared by Wollongong Homes Pty Ltd (dated 8 October 2014) for the replacement of brickwork reusing the steel lintels and agree with the Scope of Works and costing methodology utlisied (copy attached at Appendix "f" to IBAS report dated 17 November 2014)
Accordingly, I opine that a replacement cost of $28,123.80 + builders margin is an appropriate quanta for this matter
- Mr Connor claims an amount of $28,123.80 based on the builder's bill of quantities, which is dated 8 October 2014. The Tribunal is not persuaded that this relates directly to the defects, scope of works and amount agreed at the conclave. While the Tribunal is not entirely clear why the amount is in the amalgamated Scott Schedule, it is clear from Mr Connors report dated 17 November 2014 that he does not agree with the findings made in Mr Campbell's affidavit after the conclave, including in relation to matters contained within item 3. He indicates at page 19 of his report that
8.2.7 All matters relating to brickwork repairs/restoration were considered at the Experts Conclave
- The applicant makes submissions that the Tribunal should reject evidence by Mr Connor because Mr Campbell has provided detailed reasoning for his conclusions and prepared an experts report that is independently costed as it is based on quotes that he has sourced. They make submissions that Mr Connor says nothing in response to Mr Campbell's revised costing's. However, Mr Connor has responded to Mr Campbell's affidavit in his report of 17 November 2014 and the Tribunal does not agree with the submissions of the applicant on this point. For the reasons stated above the Tribunal is not persuaded by the reliability of Mr Campbell's evidence. He has mind changed significantly over the course of the litigation. Given the findings made in relation to the reliability of Mr Campbell's evidence, the Tribunal prefers the evidence of the Mr Connor and finds that what was agreed at the conclave is a proper reflection of the liability, scope and quantum and allows the amount of $15,170.00 for the defect relating to brickwork.