© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2004] NSWLEC 99
Land and Environment Court (NSW)
1997-04-07
Robert J, Pain J, Mr J, Mr P
Original judgment source is linked above.
(b) For the Second Respondents: (1) Mr Wright, one of the Second Respondents, swore affidavits dated 4 September 2002 and 10 February 2003; and (2) Mr Brindle, a town planner, swore affidavits dated 11 September 2002, 15 November 2002 and 21 July 2003.
The Council did not tender any additional evidence. Grounds of invalidity of construction certificate 5. The Applicant alleged that the construction certificate is invalid on four grounds. Paragraph 18 of the Second Further Amended Points of Claim filed by the Applicant expresses these grounds as follows: 18 In the Premises the said Construction Certificate was invalid being inconsistent with the Development Consent and in breach of Regulation 145(1)(a).
18.A Alternatively the decision by the Council to approve the said Construction Certificate is one which was not reasonably open to the Council and was manifestly unreasonable.
18.B Alternatively the Respondent Council gave no real consideration to the inconsistency between the Development approval and the Construction Certificate Application as required by clause 145A [sic - cl 145(1)(a)] of the Regulations and thereby breached the Environmental Planning and Assessment Act.
18.C The approval of the Construction Certificate exceeded the jurisdiction of the Council in that the Construction Certificate was inconsistent with the Development Application. Argument 1 - Court has power to consider a breach of the EP&A Regulation (par 18 of the Second Further Amended Points of Claim) 6. The Applicant submitted that: (a) as s 122, s 123 and s 124 of the EP&A Act gives the Court power to consider whether there has been a breach of the Environmental Planning and Assessment Regulation 2000 (the EP&A Regulation); and (b) a reference to the EP&A Act in s 123 and s 124 is defined to include the EP&A Regulation (s 122); then the Court has power to determine whether the EP&A Regulation has been breached. The Applicant argued that the Court has jurisdiction on this basis separate to its jurisdiction based on a finding that there is a jurisdictional fact in issue. Authority for this argument was said to be based on the decision of Bignold J in Donnelly v Delta Gold Pty Ltd (2001) 113 LGERA 34 at 53.
Finding on argument 3 - manifest unreasonableness 32. It is necessary to resolve the meaning of the term "inconsistent" in cl 145(1)(a) of the EP&A Regulation before the reasonableness or otherwise of the Council's decision to grant a construction certificate can be determined. It is clear that "inconsistent" does not mean that a construction certificate must be identical to the development consent plans. Accordingly, the possibility of some variation between the terms of a development consent and the design and construction of the building is contemplated by the legislation.
The Applicant appeared to accept, based on Mr Urludag's evidence, that the "test" of whether a matter is inconsistent is whether the variation between the terms of a development consent and the design and construction of the building is such that a s 96 modification is necessary. If it is then, according to Mr Urludag, this suggests that a construction certificate cannot (in the absence of such a s 96 modification) be issued for the development because the design and construction of the development is not consistent with the development consent plans.
It is difficult to precisely qualify the meaning of "inconsistent". Each case will need to be decided on its own facts. A single minor difference between the construction certificate plans and the development consent plans is likely to be acceptable. Where there are a number of minor differences then the collective impact of these differences will need to be assessed to determine whether they combine to result in unacceptable inconsistency. A major difference is likely to give rise to an inconsistency. Whether a difference is major or minor and whether, in the case of a number of minor differences, the cumulative effect is a major difference will depend on the circumstances. Consideration of whether or not a s 96 modification is warranted is not of great assistance, as that threshold addresses a different statutory context. It may be that there will be a finding of inconsistency under cl 145(1)(a) before the necessity for a s 96 modification arises. I consider that provided the development consent and construction certificate plans are largely similar so that they depict substantially the same development they are not inconsistent.
Manifest unreasonableness is generally understood as referring to a decision which no rational decision maker could arrive at. The classic test for manifest unreasonableness was enunciated by Lord Greene MR in Associated Provincial Picture Houses Limited v Wednesbury Corporation (1948) 1 KB 223 at 234, namely whether the Council has "come to a conclusion so unreasonable that no reasonable authority could ever have come to it."
It is clear that this test will not be easily met. As Mason P stated in Weal v Bathurst City Council (2000) 111 LGERA 181, at 188: The test is stringent. When, "the ground of asserted unreasonableness is giving too much or too little weight to one consideration or another a court should proceed with caution... lest it exceed its supervisory role by reviewing the decision on its merits" ( Minister for Immigration and Multicultural Affairs v Eshetu (1999) 197 CLR 611 at 627 per Gleeson CJ and McHugh J, quoting Mason J in Minister for Aboriginal Affairs v Peko-Wallsend Ltd (1986) 162 CLR 24 at 42). The decision must amount to an abuse of power ( Attorney-General (NSW) v Quin (1990) 170 CLR 1 at 36) or be so devoid of plausible justification that no reasonable person could have taken that course ( Minister for Immigration and Ethnic Affairs v Teoh ( 1995) 183 CLR 273 at 290). See also Minister for Urban Affairs and Planning v Rosemount Estates Pty Ltd (1996) 91 LGERA 31.
The relevant principles surrounding the test for manifest unreasonableness were set out by Lloyd J in Owen Haviland Pty Limited v North Sydney Council [1997] NSWLEC 39 (7 April 1997): In approaching this issue it is necessary to be mindful of the fact that an appeal is limited to a question of law. It is thus necessary to have regard to the principle that even perverse or unreasonable findings of fact do not constitute errors of law; and even if the reasons whereby a court or tribunal reached its conclusions of fact were demonstrably unsound this would not amount to an error of law ( Randwick Municipal Council v Manousaki (1988) 66 LGRA 330 at 333-334, per Clarke JA with whom Hope and McHugh JJA agreed). It is also necessary to be mindful of the need for an appellate court to proceed with caution, lest it exceed its supervisory role by reviewing the decision on its merits ( Minister for Aboriginal Affairs v Peko-Wallsend Limited (1986) 162 CLR 24 at 42, per Mason J). A mere preference by an appellate court for a different result will not suffice. Wednesbury unreasonableness must not be allowed to open the gate to judicial review of the merits of a decision or action taken within power ( Minister for Urban Affairs and Planning v Rosemount Estates Pty Limited (1996) 91 LGERA 31 at 42, per Sheller JA). The narrow issue of Wednesbury unreasonableness does not entitle me to form my own opinion as to the reasonableness of the decision under appeal and if I think it is unreasonable, though within the scope of the powers granted to the assessor, to declare it invalid. 38. The Applicant's onus of proof cannot be discharged by the calling of an expert witness to give his opinion on the question the Council's delegate had to consider under cl 145 of the EP&A Regulation. I do not accept that Mr Urludag's opinion is conclusive of the matter before me as to whether the Council acted with manifest unreasonableness in issuing the construction certificate. I do, however, accept that expert opinion may assist the Court in its deliberations as to whether a decision reached by a certifying authority to the effect that the design and construction of the building was not inconsistent with the development consent was manifestly unreasonable in line with the principles outlined above.
(b) the eastern balcony (matters 4, 5 and 7) 59. In relation to matter 4, the Second Respondents have stated that they will affix shutters when this matter has been resolved. The installation of these shutters will deal with the privacy impacts which the Applicant is concerned about in relation to this balcony.
(c) swimming pool (matters 1, 3 and 8) 66. The issue that is of most concern to the Applicant is the impact on the amenity of her home, particularly the kitchen area, as a result of the height of the Second Respondents' swimming pool and its close proximity to the boundary between the Applicant and the Second Respondents.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Lesnewski
Mosman Municipal Council & Anor
CITATION : Lesnewski v Mosman Municipal Council & Anor [2004] NSWLEC 99 APPLICANT Helen Lesnewski PARTIES : RESPONDENT Mosman Municipal Council Robert J Wright and Carol Wright FILE NUMBER(S) : (4)0085 of 2002 CORAM: Pain J KEY ISSUES: Judicial Review :- validity of construction certificate - whether decision to issue a construction certificate is a jurisdictional fact - inconsistency between development consent plans and construction certificate plans - onus of proof Judicial Review:- work done without development consent - discretion to grant relief LEGISLATION CITED: Environmental Planning and Assessment Act 1979 s 122, s 123, s 124 Environmental Planning and Assessment Regulation 2000 cl 145 ACR Trading Pty Limited & Anor v Fat-sel Pty Limited & Anor (1987) 11 NSWLR 67 ; Associated Provincial Picture Houses Limited v Wednesbury Corporation (1948) 1 KB 223 ; Attorney General of NSW v Quinn (1990) 170 CLR 1 ; Chambers v Maclean Shire Council (2003) 126 LGERA 7 ; Corporation of the City of Enfield v Development Assessment Commission (2000) 199 CLR 135; Donnelly v Delta Gold Pty Ltd (2001) 113 LGERA 34 ; Foley v Padley (1984) 154 CLR 349 ; CASES CITED: Hale v Parramatta City Council (1982) 47 LGRA 269; Jones v Dunkel (1958 - 1959) 101 CLR 298 ; Minister for Aboriginal Affairs v Peko-Wallsend Ltd (1986) 162 CLR 24; Owen Haviland Pty Limited v North Sydney Council [1997] NSWLEC 39 (7 April 1997); Terry George Androiotakis v Woollahra Municipal Council [1998] NSWLEC 137 (30 June 1998) ; Timbarra Protection Coalition Inc v Ross Mining NL (1999) 46 NSWLR 55 ; Transport Action Group Against Motorways Inc v Roads and Traffic Authority (1999) 104 LGERA 133 ; Warringah Shire Council v Sedevcic (1986) 63 LGRA 361, 10 NSWLR 335; Weal v Bathurst City Council (2000) 111 LGERA 181 DATES OF HEARING: 28/07/03, 29/07/03, 27/11/03, 28/11/03, 1/12/03 DATE OF JUDGMENT: 03/29/2004
[1997] NSWLEC 39
(1987) 11 NSWLR 67
(1990) 170 CLR 1
(2003) 126 LGERA 7
(2000) 199 CLR 135
(2001) 113 LGERA 34
(1984) 154 CLR 349
(1986) 162 CLR 24
(1999) 46 NSWLR 55
(1999) 104 LGERA 133
(2000) 111 LGERA 181
(1999) 197 CLR 611
(1996) 91 LGERA 31