© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2004] NSWLEC 422
Land and Environment Court (NSW)
2004-08-02
Robert J, Pain J, Mr J, Ms J
Original judgment source is linked above.
Background 2. On 29 March 2004 I handed down a judgment in which I found that the Second Respondents had carried out works without consent and made orders: 1. declaring that the Second Respondents had carried out works without consent pursuant to the Environmental Planning and Assessment Act 1979 ( "the EP&A Act" ) in that: (a) no shutters have been installed on the eastern side of the front eastern balcony as provided for in the construction certificate plans; (b) the eastern end of the front eastern balcony has been extended to the eastern wall of the house whilst it is recessed 0.9 metres on the construction certificate plans; (c) the fascia boards on the eastern side have been altered from slimline effect to form a canopy over the front balcony. 2. requiring the Second Respondents to install shutters on the eastern side of the front eastern balcony as provided for in the construction certificate plans. 3. I reserved the question of costs in that judgment.
A brief history of the proceedings is necessary as the Applicant's claim has undergone a number of substantial alterations in the course of the proceedings. The Applicant commenced Class 4 proceedings in May 2002 and filed a Class 4 application ("the Application"). The Applicant filed Points of Claim on 11 June 2002 ("the June 2002 Points of Claim"). The claim, as pleaded in the June 2002 Points of Claim, related to the alleged invalidity of the development consent granted by the Council to the Second Respondents, alleged differences between the plans approved by the construction certificate and plans approved by the development consent, and alleged illegal work carried out by the Second Respondents. The Application stated that the Applicant sought a declaration that the development consent was invalid, a declaration that works had been carried out without consent and an order that the Second Respondents demolish certain works. In relation to the allegations of illegal work made in the June 2002 Points of Claim, the particulars to par 19 itemised ten separate matters which it was alleged were not in accordance with the development consent or the construction certificate.
The Applicant filed an amended Points of Claim on 2 October 2002 ("the October 2002 Points of Claim"). The October 2002 Points of Claim contained a number of amendments to the June 2002 Points of Claim including adding one further item to the particulars provided at par 19 of the June 2002 Points of Claim. An amended Class 4 application filed by the Applicant in December 2002 ("the Amended Application") also sought declarations as to the validity of the construction certificate.
On 9 April 2003 I determined, as a preliminary point of law, that s 101 of the EP&A Act prevented the Applicant from challenging the development consent. As a consequence of this judgment a substantial part of the Applicant's case could not proceed in the way it had been argued in the October 2002 Points of Claim and. A Second Amended Points of Claim was filed by the Applicant on 23 April 2003 ("the April 2003 Points of Claim"). The particulars given for par 19 of the April 2003 Points of Claim were amended from those contained in the October 2002 Points of Claim, with four deletions and eight new additions being made.
Meanwhile, the Second Respondents had lodged a s 96 application with the Council, seeking modifications to the development consent originally under challenge. They appealed to this Court against the Council's refusal of that s 96 application. On 2 July 2004 this Court determined that the Second Respondents' appeal should be upheld and the modifications allowed. It was therefore necessary for further amendments to be made to the April 2003 Points of Claim and on 29 July 2003 the Applicant filed further Amended Points of Claim ("the July 2003 Points of Claim). The July 2003 Points of Claim deleted some of the matters in relation to which orders and relief were sought in the April 2003 Points of Claim. The July 2003 Points of Claim also further amended the particulars set out at par 19 by adding one further matter, bringing the matters relied on as being illegal works to a total of 15. Because of the s 96 application only eight matters remained under par 19.
At the hearing the Applicant relied on the eight matters particularised at par 19 of the July 2003 Points of Claim. Of these, only one, the height of the swimming pool concourse, appeared in the original June 2002 Points of Claim filed by the Applicant. In my judgment of 29 March 2004 I held that the Applicant's challenge to the construction certificate was unsuccessful but I found that the Second Respondents had carried out illegal works in relation to three of the eight matters alleged by the Applicant and granted relief in relation to one of those, being the installation of shutters (see par 2 above which sets out the orders and declarations made by me on that occasion). The matters in relation to which the Applicant ultimately succeeded were added to the Applicant's case by the April 2003 Points of Claim.
The issues relating to the validity of the construction certificate occupied the bulk of the argument and evidence in the hearing before the Court.
The Applicant's Submissions 10. The Applicant disputed the Second Respondents' claim that they were entitled to their costs and argued, in the alternative, that the Second Respondents should pay the Applicant's costs associated with the illegal works or that the Second Respondents should pay sixty per cent of the Applicant's costs. The Applicant argued that there was no "usual rule" as to costs which has been formally adopted by this Court and referred to the decision of Enfield J in Re Sanchez (1994) 49 FCR 326 to support her argument that costs should be determined in light of all the circumstance of the case. Further, the Applicant relies on the decision of Ritter v Godfrey (1920) 2 KB 47 to argue that where, as here, an unsuccessful applicant has acted reasonably in commencing the proceedings and the successful respondents, by their actions, led the applicant to believe that she had a good cause of action, the respondents are not entitled to their costs.
The Second Respondents' Submissions 11. The Second Respondents argued that this Court's usual practice, being that costs should follow the event and the unsuccessful party should bear the successful party's costs, should be applied in relation to these proceedings. The Second Respondents relied on the judgment of McHugh J in Oshlack v Richmond River Council (1998) 193 CLR 72, as applied by the Court of Appeal in Maule v Liporoni & Anor [No. 2] (2002) 122 LGERA 216, to argue that discretion as to costs granted to the Court by s 69(2) of the Land and Environment Court Act 1979 is usually exercised in favour of the successful party unless the conduct of the successful party is such that it disentitles them from the beneficial exercise of the discretion on costs.
Finding 13. Under s 69(2) of the Land and Environment Court Act 1979 I have a broad discretion in deciding how costs should be awarded. The usual practice of this Court is that costs follow the event unless there is disentitling conduct on the part of the successful party. The Second Respondents have been largely successful in these proceedings but I have made orders against them in relation to a relatively small part of the case in terms of the time occupied during the course of the hearing by the claim of illegal work.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Lesnewski
Mosman Municipal Council & Anor
CITATION : Lesnewski v Mosman Municipal Council & Anor (No 2) [2004] NSWLEC 422 Helen Lesnewski PARTIES : Mosman Municipal Council Robert J Wright and Carol Wright FILE NUMBER(S) : (4)0085 of 2002 CORAM: Pain J KEY ISSUES: Costs :- Whether disentitling conduct by a successful Defendant - Whether Applicant entitled to any part of her costs. LEGISLATION CITED: Environmental Planning and Assessment Act 1979, s 101 Land and Environment Court Act 1979, s 69(2) Cretazzo v Lombardi (1975) 13 SASR 4; Maule v Liporoni & Anor [No. 2] (2002) 122 LGERA 216; CASES CITED: Oshlack v Richmond River Council (1998) 193 CLR 72; Re Sanchez (1994) 49 FCR 326; Ritter v Godfrey (1920) 2 KB 4 DATES OF HEARING: 30/07/2004 DATE OF JUDGMENT: 08/02/2004
(1975) 13 SASR 4
(2002) 122 LGERA 216
(1998) 193 CLR 72
(1994) 49 FCR 326