Leda Manorstead Pty Ltd v Secretary, Department of Planning and Environment
[2022] NSWCCA 220
At a glance
Source factsCourt
Court of Criminal Appeal (NSW)
Decision date
2022-09-15
Before
Brereton JA, Preston CJ, Chen J, Pepper J
Catchwords
- Gertos v Inner West Council [2016] NSWCCA 186 Gilmour v Environment Protection Authority
- Tableland Topdressing Pty Ltd v Environment Protection Authority (2002) 55 NSWLR 593
- [2002] NSWCCA 399 Grajewski v Director of Public Prosecutions (NSW) (2017) 270 A Crim R 33
- [2017] NSWCCA 251 Kyluk Pty Ltd v Chief Executive, Office of Environment and Heritage (2013) 298 ALR 532
Source
Original judgment source is linked above.
Catchwords
Judgment (12 paragraphs)
[This headnote is not to be read as part of the judgment] The appellant was convicted by the Land and Environment Court of three offences against s 125(1) of the Environmental Planning and Assessment Act 1979 (NSW) for carrying out development otherwise than in accordance with conditions of a Project Approval in contravention of the then applicable s 75D(2) of the Act. The primary judge found that the appellant breached condition 21A of the relevant Project Approval insofar as that condition required "bulk earthworks for the site" to be "limited to a maximum exposed disturbed area" of 5ha (later extended to 5.59ha) at any time. On appeal against two of the three convictions: Held, per Preston CJ of LEC at [118]; Brereton JA and Chen J agreeing at [1], [119], dismissing the appeal: As to the ultimate outcome: 1. Although the primary judge erred in one respect in the construction of condition 21A, the error does not occasion any substantial miscarriage of justice, and the appeal should be dismissed. That is because even on the correct construction, the unchallenged findings as to the extent of the maximum exposed disturbed area at any time - which was found to have been brought about by bulk earthworks performed in pursuance of the Project Approval - established that the appellant contravened condition 21A in any event: [10]-[12] (Brereton JA); [17], [73], [114]-[116] (Preston CJ of LEC). Gilmour v Environment Protection Authority; Tableland Topdressing Pty Ltd v Environment Protection Authority (2002) 55 NSWLR 593; [2002] NSWCCA 399; Geitonia Pty Ltd v Inner West Council; Gertos v Inner West Council [2016] NSWCCA 186, applied. As to the construction of "the site": 2. The primary judge erred in finding that "the site" of the bulk earthworks referred to in condition 21A(b) was not limited to the borrow areas in the identified precincts but extended to include the entire project site. The natural reading of condition 21A is that "the site" in 21A(b) refers back to the "bulk earthworks in the borrow areas within [the identified precincts]" in 21A(a): [3] (Brereton JA); [66] (Preston CJ of LEC). Condition 21A's relationship with other conditions, and the circumstances in and purpose for which it came to be inserted into the Project Approval, are indicia in further support of that construction: [65]-[72] (Preston CJ of LEC). As to the construction of "exposed disturbed area": 3. There is no warrant, having regard to the text, context or purpose of the phrase, to exclude from the "exposed disturbed area" areas that are also authorised to be disturbed by other development consents. The outcome required by condition 21A(b) is to achieve a factual state of affairs: not having a disturbed area exceeding 5.59ha at any time. It matters not why or how any disturbed area comes about; what matters is the existence and extent of the disturbed area, and whether it exceeds the prescribed limit: [87]-[88] (Preston CJ of LEC). 4. The mere existence of another development consent authorising bulk earthworks in the same area creates only the potential to disturb that area, which is an insufficient basis upon which to exclude such an area from the calculation: [90]-[92] (Preston CJ of LEC). Given the primary judge's unchallenged finding that the subject bulk earthworks were done in pursuance of the Project Approval, it matters not that there might have been some other consent or approval under which similar work could have been (but was not) done: [11] (Brereton JA).