Laing v Carroll
[2004] FCA 1509
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2004-11-23
Before
Marshall J
Source
Original judgment source is linked above.
Judgment (55 paragraphs)
REASONS FOR JUDGMENT 1 The proceeding before the Court is an application pursuant to s 39B(1A) of the Judiciary Act 1903 (Cth) for a declaration that the respondent is required by s 83BH(4)(d) of the Workplace Relations Act 1996 ("the Act") to produce the documents described in the notice served upon him by the applicant on 10 October 2003. 2 The proceeding raises for consideration the question of whether the Court should exercise its discretion to grant the applicant declaratory relief or to refrain from so doing, having regard to the particular factual and legal circumstances applicable to the matter.
Factual background 3 Between 1951 and 1956, the Gas and Fuel Corporation of Victoria ("the Corporation") erected a high-pressure gasification plant at Morwell in the Latrobe Valley. The plant was designed to use local brown coal in the "Lurgi process" of gas production. The Corporation closed the plant in 1969, by which time it had outlived its utility, as a consequence of the discovery of natural gas in Bass Strait. In 1972 the Corporation sub-divided and sold most of the land at the Morwell gas works site ("the Morwell site"). The State of Victoria purchased the remainder (some 26 out of 48 lots). 4 In early 2002 the State decided to establish the Morwell Gasworks Remediation Project ("the project"). The Victorian Government Property Group ("the VGPG") is responsible for undertaking the project. 5 In or about May 2002 the VGPG decided to advertise for registrations of interest by demolition contractors in relation to demolition work associated with the project. Eight registrations of interest flowed from the advertisement. Able Demolitions and Excavations Pty Ltd ("Able") was one of the demolition contractors which forwarded a registration of interest to the VGPG. Able submitted its registration of interest on 12 June 2002. 6 After receipt of the registrations of interest, the VGPG engaged CMR Consultants (Australia) Pty Ltd ("CMR") to evaluate and select a short list of demolition contractors who would be invited to tender for work on the project. Able was not invited to tender. By letter dated 21 February 2003, CMR advised Able of its decision. The tenders, for those contractors on the short list, opened on 21 February 2003 and were to close on 30 April 2003. 7 The applicant is an employee of the Commonwealth within its Department of Employment and Workplace Relations. He is attached to the Interim Building Industry Taskforce ("the Taskforce") as an investigator. He is an authorised officer pursuant to s 83BG(1) of the Act. 8 On 11 March 2003, a solicitor acting on behalf of Able, contacted the Taskforce with respect to a complaint by Able concerning its exclusion from the short list of tenderers to perform work at the Morwell site. Able subsequently provided the applicant with further details about its complaint. In essence, it asserted that it was excluded from work on the Morwell site because it was not party to an enterprise agreement to which the Construction Forestry Mining and Energy Union ("the CFMEU") was a party. 9 After further investigation, the applicant formed the view that the State may have refused to allow Able to tender for work at the Morwell site because Able was party to a certified agreement under s 170LK of the Act, being an agreement with its employees alone. He further considered that the State may have breached s 298K(2)(d) of the Act by refusing to engage Able as an independent contractor for the prohibited reason referred to in s 298L(1)(h) of the Act, that is, that Able was entitled to the benefit of a certified agreement. 10 In April 2003, Mr John Howell was the person within the VGPG who had responsibility for the project. On 14 April 2003, the applicant wrote to Mr Howell requesting the provision of various categories of documents concerning the tender process. 11 On 23 April 2003, CMR wrote to each of the demolition contractors who had been asked to tender, advising them that in light of the applicant's investigations, and in order not to prejudice Able's position, the closing date for tenders would no longer be 30 April 2003. The letter said that the delay would take about six weeks, until the investigation had been completed. 12 By letter dated 7 May 2003, the applicant requested the VGPG's solicitors to arrange a time for him to inspect the documents referred to in his letter of 14 April 2003. 13 On 28 May 2003, CMR wrote again to the demolition contractors, advising them that tenders would not close at the end of the six week period previously referred to, as the applicant's investigation was continuing. They were informed that they would be given 14 days' notice of the final date for the closing of tenders.