Lahey Constructions Pty Limited v Newbold Bulk Haulage Pty Limited
[2013] NSWSC 215
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2013-03-15
Before
Pembroke J
Source
Original judgment source is linked above.
Judgment (8 paragraphs)
Introduction 1This is an application by the plaintiff for a declaration that the adjudication determination dated 6 November 2012 made by the second defendant pursuant to the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) is void and should be quashed and set aside. 2The application arises in the context of a contract which effectively provided that the financial risk associated with Site Conditions that were materially adverse and unforeseen lay with the subcontractor, namely, the first defendant.
The Contract 3The contract incorporated the terms of the GC21 Subcontract, of which Clause 41 provided as follows: 41 Site Conditions .1 The Subcontractor agrees that it has no other entitlement arising out of or in connection with Site Conditions other than as referred to in this clause 41. .2 If the Contractor encounters, in the execution of Subcontract Works (including when obtaining Further Site Information), Site Conditions which are materially adverse in comparison to the Site Conditions which the Subcontractor should have reasonably foreseen at the Date of Subcontract, having regard to the warranty in clause 40.2, the Subcontractor must notify the Contractor in writing forthwith and in any event within 7 days of encountering these Site Conditions (and prior to making any related Subcontractor's Claim), giving full details of: .1 the Site Conditions encountered; .2 the manner in which they are said to be materially adverse (having regard to the warranty in clause 40.2), together with information supporting this contention; .3 the effect on the Subcontract Works; .4 subject to clause 41.8, the estimated additional cost (if any) of dealing with the Site Conditions encountered and the additional work and resources involved; .5 the delay (if any) to progress of the Subcontract Works; and .6 any other relevant matters. .8 Notwithstanding anything in clause 41, when specified in Contract Information Item 41 that the Subcontract is to bear the full risk of encountering and dealing with materially adverse Site Conditions: .1 the Subcontractor is not entitled to the costs of dealing with materially adverse Site Conditions; and .2 notwithstanding clause 54, if the Subcontractor is or will be delayed in reaching Completion as a result of dealing with materially adverse Site Conditions, the Subcontractor will not be entitled to an extension of time for Completion. .9 If a Variation is instructed or agreed as a result of Site Conditions, the parties' rights and obligations are not affected by clause 41.8. The Subcontract Information Item 41 was as follows: Site Conditions Is the Subcontractor to bear the full risk, including cost and time implications, of encountering and dealing with materially adverse Site Conditions? Yes. The definition of Site Conditions was as follows: Any physical conditions of the site (including sub-surface conditions, but excluding weather conditions or physical conditions which are a consequence of weather conditions) encountered in the execution of the Subcontract Works.