471 In my view, the application for an order for the payment of the milestone incentive payments, based on such grounds, must fail for the following reasons:
1. The premise for both contentions evaporates at the point that the Commission concludes that the strike was not based wholly upon a genuine occupational health and safety concern. Given this is the conclusion reached by the Commission for the fourth period, there is no basis, even putting the applicant's contentions at their highest, for the grant of the application on and from 27 September 2001. In any event, the discretionary factors warranting the rejection of the application during this period must apply with equal force to that aspect of it concerning milestone incentive payments.
2. It must be emphasised that the construction milestones (and the corresponding milestone incentive payments) constitute a significant component of modern building and construction awards. The awards provide incentive payments to stimulate compliance with construction milestones which coincide with the 'practical completion' dates contracted for various stages of a project (see clauses 4.1 and 4.2 of the award). Accordingly the awards lay down strict conditions for the receipt of milestone incentive payments; most noticeably that such payments are conditional upon and linked to the achievement of the construction milestone and strict adherence by unions and employees to the provisions of the award including the safety clause and the resolution of disputes clause (see clause 9.4.2). Here, the practical completion was not achieved by the employees for either milestone period. Thus, the conditions of the award for the payment were simply not met. In the absence of a determination by the Project Monitoring Committee to grant the payment under clause 9.4.4 despite this failure then no entitlement arises. I agree with the Intervenor that the absence of an entitlement for the provision is a significant reason against the grant of relief.
3. Further in this case there was no evidence that the unions made an application pursuant to clause 9.4.4 of the award for the grant of the payment based on extenuating circumstances or otherwise. I do not consider they can now properly seek relief from the Commission in the absence of engaging existing remedies under the award.
4. In any event, there is not sufficient evidence before the Commission to enable it to form the view that the Committee would have, if it had properly considered all the circumstances bearing upon the operation of clause 9.4.4 of the Award, made a determination that there were 'extenuating circumstances'. Mr Archibald's statement that the Committee may have approved payment for the final milestone period if it had met on 17 September is speculation and in any event, could not have comprehended within it the existence of a general stoppage at the site from 14 September.
5. I do not consider it as appropriate in the circumstances of this matter for the Commission to place itself in the shoes of the Project Monitoring Committee with a view to defacto deciding whether there were extenuating circumstances warranting the making of the milestone incentive payment. That Committee would no doubt take into account a variety of considerations, many of which are outside the purview of the Commission, having regard to the evidence in this case (most particularly, the Committee would have regard to the circumstances affecting all periods of work at the site during the two milestone periods and not just those periods associated with the strike).
6. The applicant submits that the milestone incentive payment should be granted because it was lost during a strike based on genuine occupational health and safety issues. I understand that submission to relate to the second of the applicant's contentions earlier mentioned and, therefore, stands separately to considerations concerning the operation of clause 9.4.4. True it is, the failure to reach the construction milestone was, to some extent, a consequence of the industrial action. However, it does not follow either as a matter of logic, or from the available evidence (or for that matter from any contention by the applicant), that the construction milestone was not reached solely, or even substantially, because of that factor. Mr Jansen did identify that his reasons for refusing the milestone incentive payment related to various aspects of the strike. However, Mr Archibald's evidence was to the effect that it was known by 14 September 2001 that the first construction milestone would not be reached and that it would require the exercise of some discretion by the Project Monitoring Committee to grant the payment. In fact, the first milestone period consisted substantially of a period of time before the commencement of the industrial action. It is not correct then to submit that the 'loss' of the benefit was, therefore, attributable to the strike (over occupational health and safety issues). There is no evidence to establish just what factors were involved in the failure to reach the milestone for 24 September, although it may be inferred from Mr Archibald's evidence that, for the most part, in the first milestone period, the delays were occasioned by factors other than the strike or occupational health and safety. These other considerations would, on the balance pf probabilities relate to other issues such as matters affecting productivity at the project.