© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2001] VSC 343
Supreme Court of Victoria
2001-09-21
Byrne J
Original judgment source is linked above.
[2001] VSC 343
Practice and Procedure - costs - trial of preliminary question aborted due to changes to defence - whether defendant should bear costs thrown away.
Statement of Claim "11. Between early April 1997 and the date of completion of the Works on 29 July 1997, Hudson Conway issued a total of 97 instructions to carry out additional works ("the variations").
PARTICULARS
Full particulars of each of the instructions and the variations are set out in Annexure 1 hereto. Note that, as identified in Annexure 1, a small number of instructions were issued after completion of the Works. The Plaintiff carried out such Works subsequent to the date of completion." Defence (21 September 1999) "11. Save that it admits that between April 1997 and the date of completion of the Works, Hudson Conway issued instructions to the Plaintiff to carry out additional works, it denies each and every allegation contained in paragraph 11. 11.1 Further, the Defendant says that the parties agreed the price of many of the variations referred to in Annexure 1 to the Statement of Claim.
PARTICULARS
The agreement was oral and was constituted by conversations at the site offices of Hudson Conway between John Holland on behalf of Hudson Conway and Ron Begbie and James Craige of the Plaintiff. Particulars of the variations, the corresponding amounts agreed and the corresponding dates on which the agreement was reached are set out in Schedule 1 hereto."
"1(a) In relation to the B2 Contract did the Plaintiff and the Defendant agree upon the price of any and if so which of the variations listed in Schedule 1 to the Defence, as pleaded by the Defendant in paragraph 11.1 thereof? (b) If yes to (a) above for each of the variations in respect of which a price was agreed did the Plaintiff and the Defendant agree that the Defendant would pay and the Plaintiff would accept the amount referred to in the column of the Schedule referred to in (a) above headed `Agreed Amount' or some other and if so what amount?"
"The proposed amendment is confined to pleading that all sums which our client contends have been agreed have also been paid by our client to your client and amends some of the Schedules. Where amendments have been made they have been appropriately marked up."
"11.1 Further, the Defendant says that the parties agreed the price of many of the variations referred to in Annexure 1 to the Statement of Claim, and the Defendant paid to the Plaintiff and the Plaintiff accepted the agreed amounts set out in Schedule 1 hereof.
PARTICULARS
The agreements were partly oral, partly in writing and partly to be implied. Insofar as the same were oral they were constituted by conversations at the site offices of Hudson Conway or on the telephone between John Holland on behalf of Hudson Conway and Ron Begbie and/or James Craige of the Plaintiff. Insofar as the same were in writing they were constituted by notations, comments, initials, signatures and dates written by John Holland on behalf of Hudson Conway on documents entitled Report on Contractor's Variation Notice on diverse dates most of which appear on the said documents. Insofar as the same were implied such implication arose from the following: (a) the notification to the Plaintiff of the adjustment to the agreed contract price made by the Defendant in respect of the relevant variation in Contract Price Adjustment Advice forms and/or Contract Price Adjustment forms, (both of which are hereinafter referred to as CPA's) copies of which were sent to the Plaintiff in the course of the contract;" (b) progress payment claims made by the Plaintiff, and progress payment certificates and cheques made by the Defendant to the Plaintiff from time to time reflecting assessments of work completed to date and calculated upon the adjusted contract price (as recorded in the CPA's) as at the date of the progress payment which reflected adjustments contained in the CPA's referred to in (a) above; (c) the acceptance of progress claim certificates and the presentation for payment of the cheques referred to in (b) above without complaint; (d) the delivering of the Defendant by the Plaintiff of its final claim under the contract which was premised upon and reflective of an acceptance by the Plaintiff of the contract price adjustments, progress payment certificates and payments referred to above. The agreement was oral and was constituted by conversations at the site offices of Hudson Conway between John Holland on behalf of Hudson Conway and Ron Begbie and James Craige of the Plaintiff. Particulars of the variations, the corresponding amounts agreed and the corresponding dates on which agreements were was reached are set out in Schedule 1 hereto."
On 14 November by consent leave was granted to amend the defence substantially in accordance with the proposed draft. It was not suggested that this amendment affected the imminent trial of the preliminary questions.
"11.1 Further, the Defendant says that the parties agreed the price of many of the variations referred to in Annexure 1 to the Statement of Claim, and the Defendant paid to the Plaintiff and the Plaintiff accepted the agreed amounts set out in Schedule 1 hereof.
PARTICULARS
The agreements were partly oral, partly in writing and partly to be implied. Insofar as the same were oral they were constituted by conversations at the site offices of Hudson Conway or on the telephone between John Holland on behalf of Hudson Conway and Ron Begbie, Jim Paneras and/or James Craige of the Plaintiff. Insofar as the same were in writing they were constituted by notations, comments, initials, signatures and dates written by John Holland on behalf of Hudson Conway on documents entitled Report on Contractor's Variation Notice or Contract Price Adjustment Advice (both of which are hereinafter referred to as `assessment reports') on diverse dates most of which appear on the said documents. Insofar as the same were implied such implication arose from the following: (aa) the conduct of the Plaintiff in submitting a quotation, claim or invoice (which was paid in full by the Defendant) and the Plaintiff's conduct in accepting such payment without demur particulars of which are set out in Schedule 16 hereto (in relation to Schedule 1 items) or the conduct of the Plaintiff in submitting a claim in this proceeding (which had been paid in full by the Defendant) and the Plaintiff's conduct in accepting such payment without demur particulars of which are set out in Schedule 17 hereto (in relation to Schedule 1 items); (bb) the notations, comments, initials, signatures and dates written by John Holland on behalf of Hudson Conway on assessment reports on diverse dates most of which appear on the said documents made contemporaneously with or immediately subsequent to the oral agreement referred to above; (a) the notification to the Plaintiff of the adjustment to the agreed contract price made by the Defendant in respect of the relevant variation in Contract Price Adjustment Advice forms and/or Contract Price Adjustment forms, (both of which are hereinafter referred to as CPA's) copies of which were sent to the Plaintiff in the course of the contract; (b) progress payment claims made by the Plaintiff and progress payment certificates issued and cheques drawn by the Defendant in favour of the Plaintiff from time to time reflecting assessments of work completed to date and calculated upon the adjusted contract price (as recorded in the CPA's) as at the date of the progress payment which reflected adjustments contained in the CPA's referred to in (a) above; (c) the acceptance of progress claim certificates and the presentation for payment of the cheques referred to in (b) above without complaint; (d) the delivering to the Defendant by the Plaintiff of its final claim under the contract which was premised upon and reflective of an acceptance by the Plaintiff of the contract price adjustments, progress payment certificates and payments referred to above. The agreement was oral and was constituted by conversations at the site offices of Hudson Conway between John Holland on behalf of Hudson Conway and Ron Begbie and James Craige of the Plaintiff. Particulars of the variations, the corresponding amounts agreed and the corresponding dates on which agreements were was reached are set out in Schedule 1 hereto."
"133. Further or in the alternative the Plaintiff is estopped by its conduct from denying that it entered into each of the agreements referred to in paragraphs 11.1, 30.1, 46, 51, 57, 64, 70, 76, 82, 88, 93, 100, 106, 111, 117 and 123 in respect of those items for which it accepted payment from the Defendant in the sum claimed which are referred to in the respective Schedules to the said paragraphs.
PARTICULARS
The conduct of the Plaintiff relied upon is as follows: (a) the submission by it of a quotation, claim or invoice in respect of those claims set out in Schedule 16 in a particular sum and its conduct in accepting payment of such sum from the Defendant without demur; (b) the submission by it of a quotation, claim or invoice in respect of those claims set out in Schedule 17, the making of a claim in these proceedings for each such claim in a particular sum and its conduct in having accepted payment of such sum from the Defendant without demur;"
"11.1 Further, the Defendant says that the parties agreed the price of many of the variations referred to in Annexure 1 to the Statement of Claim, and the Defendant paid to the Plaintiff and the Plaintiff accepted the agreed amounts set out in Schedule 1 hereof.
PARTICULARS
The agreements were partly oral, partly in writing and partly to be implied. Insofar as the same were oral they were constituted by conversations at the site offices of Hudson Conway or on the telephone between John Holland on behalf of Hudson Conway and Ron Begbie, Jim Paneras and/or James Craige of the Plaintiff. Insofar as the same were in writing they were constituted by notations, comments, initials, signatures and dates written by John Holland on behalf of Hudson Conway on documents entitled Report on Contractor's Variation Notice or Contract Price Adjustment Advice (both of which are hereinafter referred to as `assessment reports') on diverse dates most of which appear on the said documents. Insofar as the same were implied such implication arose from the following: (aa) the conduct of the Plaintiff in submitting a quotation, claim or invoice which was paid in a lesser sum by the Defendant and the Plaintiff's conduct in accepting such payment without demur particulars of which are set out in Schedule 16 hereto (in relation to Schedule 1 items); (a) the notification to the Plaintiff of the adjustment to the agreed contract price made by the Defendant in respect of the relevant variation in Contract Price Adjustment Advice forms and/or Contract Price Adjustment forms, ( both of which are hereinafter referred to as CPA's) copies of which were sent to the Plaintiff in the course of the contract; (b) progress payment claims made by the Plaintiff and progress payment certificates issued and cheques drawn by the Defendant in favour of the Plaintiff from time to time reflecting assessments of work completed to date and calculated upon the adjusted contract price (as recorded in the CPA's) as at the date of the progress payment which reflected adjustments contained in the CPA's referred to in (a) above; (c) the acceptance of progress claim certificates and the presentation for payment of the cheques referred to in (b) above without complaint; (d) the delivering to the Defendant by the Plaintiff of its final claim under the contract which was premised upon and reflective of an acceptance by the Plaintiff of the contract price adjustments, progress payment certificates and payments referred to above. The agreement was oral and was constituted by conversations at the site offices of Hudson Conway between John Holland on behalf of Hudson Conway and Ron Begbie and James Craige of the Plaintiff. Particulars of the variations, the corresponding amounts agreed and the corresponding dates on which agreements were was reached are set out in Schedule 1 hereto."
(a) After Kennedy Taylor submitted its variation claims the parties negotiated and settled them at meetings between Mr Holland on behalf of the agent of Crown and Mr Begbie and Mr Paneras and Mr Craige on behalf of Kennedy Taylor on specified dates in 1997.
(b) In the case of certain variations, the Crown witnesses had no recollection of agreeing the amount payable but agreement was to be inferred from the fact that the parties met and that Mr Holland, the Hudson Conway representative, noted a sum beside the variation on his list. This sum was paid and accepted by Kennedy Taylor.
(c) In the case of certain variation claims an analysis of them shows that they are duplications of other claims which have been agreed and paid.
(d) After Kennedy Taylor submitted its variation claims some were paid in full by Crown and the payments were accepted by Kennedy Taylor. Kennedy Taylor's present variation claims included enlarged claims which had previously been paid in this way. These enlarged claims should be dismissed because the earlier payment and acceptance determined this matter.
(e) After Kennedy Taylor submitted variation claims some were assessed by Crown or its consultants and the amount so assessed, being less than the amount claimed, was paid by Crown and accepted by Kennedy Taylor. Kennedy Taylor's present claims included claims which had previously been part paid in this way. Again, it is said that the payment and acceptance determined the entitlement of Kennedy Taylor.
(f) In August 1997 Mr Holland on behalf of Crown and Mr Begbie on behalf of Kennedy Taylor agreed that variations should be paid at rates set out in a certain price measurement document plus a 75% loading to compensate Kennedy Taylor for the difficulty of the work. Certain of the variation claims in which a greater difficulty factor loading was sought by Kennedy Taylor were reduced by Mr Holland to reflect the August 1997 agreement and Crown paid the reduced sum. Another change to the Kennedy Taylor variation claims which Mr Holland consistently and unilaterally adopted was the refusal to pay the sum of $50, $60 or $100 for drawings, manuals or references provided by Kennedy Taylor. He did this because he said these items were included in the original contract work and he had previously agreed this with Kennedy Taylor. These reductions, likewise, were not discussed and agreed with Kennedy Taylor as the claims were processed, but Crown consistently paid and Kennedy Taylor accepted the reduced payments and were accordingly bound by this.
[5] I ignore as inconsequential for this purpose, the fact that a further representative of Kennedy Taylor, Mr Paneras, is said to have participated in the negotiations.
[6] See Jacobson v Ross [1995] VicRp 24; [1995] 1 VR 337.
Kennedy Taylor (Vic) P/L
Crown Ltd [2001] VSC 343