Keith v M & M Building Pty Ltd; M & M Building Pty Ltd v Keith
[2016] NSWCATCD 43
At a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2016-03-31
Source
Original judgment source is linked above.
Judgment (28 paragraphs)
INTRODUCTION
- Application HB 15/31711 was filed in the Tribunal by the homeowners on 4 May 2015. The application initially sought orders for work to be done to the approximate value of $200,000 together with orders for relief of payment of a sum allegedly owed to the builder. In addition to M & M Building Pty Ltd, the application also named Shaun Mowbray and Malcolm Blair as respondents. On 7 December 2015 the application was amended, on request of the homeowners and by order of the Tribunal, to seek orders for payment to the homeowners in the sum of $500,000.
- Although losses of some $630,000 had allegedly been suffered by the homeowners, their claim was limited to $500,000. In opening submissions on the first day of hearing the application was further amended to seek orders for $489,198.78 plus $1,740 for storage costs. In addition the homeowners sought orders for provision to them of receipts for various whitegoods purchased by the builder on their behalf.
- Application HB 15/66010 was filed by the builder on 10 December 2015. The builder's application was accompanied by Points of Claim in which the builder sought orders for payment to the builder of $13,516 allegedly outstanding under the contract including interest on the outstanding payments. In the builder's Points of Claim the allegedly unpaid tax invoices were listed and together amounted to $20,116. No explanation was given as to why the sum claimed was only $13,516 nor of how much of that sum was made up of interest arising under the terms of the contract. In addition the builder sought orders for unspecified amounts arising from allegedly wrongful termination of the contract by the homeowners.
- By consent of the parties and without any issue relating to costs being raised the names of Shaun Mowbray and Malcolm Blair were removed, by order of the Tribunal, as respondents on application HB 15/31711.
- The issue of how and in what circumstances the contract had terminated was hotly contested by the parties. The significance of that issue related to whether the homeowners' claim in respect of the allegedly incomplete work could be maintained. The builder's claim for damages arising from wrongful termination of the contract by the homeowners was never clearly articulated or pressed.