Kavanagh -v- New South Wales Self Insurance Corporation [2024] NSWCATCD 14
[2024] NSWCATCD 14
At a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2023-11-01
Source
Original judgment source is linked above.
Judgment (10 paragraphs)
Background/Application
- The applicant is the owner of premises in Cocoparra Circuit, North Kellyville (Property); settlement of her purchase of the property from CN1 Pty Limited (CN1) occurring on 29 December 2021 following the entering into of a Contract for Sale of Land on 30 April 2021.
- Prior to the applicant's purchase of the property from CN1 the vendor had entered into a NSW Residential Building Contract for New Dwellings with Willoughby Homes Pty Limited (Builder) on 17 February 2021 for the construction by the builder of a two storey residential dwelling on the property (Building Contract).
- Some two weeks prior to the builder and CN1 entering into the building contract the respondent had, on 4 February 2021, had issued to CN1 a Policy of Insurance under Part 6 of the Home Building Act 1989(NSW) (Policy).
- Both the building contract and the policy are discussed in greater detail later in these Reasons. Two certificates were issued in respect of two lots comprising the North Kellyville property.
- In late July 2022 the builder, having commenced the building work for CN1 pursuant to the building contract prior to the applicant becoming the registered proprietor, became insolvent and did not thereafter attend the property or complete the works.
- On 2 August 2022 the applicant made a claim under the policy against the respondent in respect of incomplete building work, defective building work, defective design and legal (and other) costs.
- The respondent, having received the claim, accepted liability for defective work on 31 October 2022 but denied liability in respect of the claim for incomplete building work, relying upon clause 3.2 of the policy. The claim on the policy, and the respondents response to the claim, are discussed in more detail below.
- In response to a request by the applicant the respondent reviewed its decision in respect of the incomplete building work component of the claim. It informed the applicant on 24 February 2023 that it was maintaining its declinature of liability.