APPLICATION OF LAW TO FACTS-THE ISSUE OF JURISDICTION
- As discussed above, the starting point for the determination of the date of practical completion of the residential building work is the date of completion as defined in the contract. The Tribunal must determine if and when the builder's Notice of Practical Completion dated 1 April 2009 was served.
- Under Clause 40.1 (a) of the contract a notice is deemed serve if it is hand delivered to the other party; and under Clause 40.1 (b) of the contract the notice is deemed to be given if it is posted on the other party's known address "on the day following the day it was posted".
- The applicants do not recall the Notice of Practical Completion having been hand delivered to them by a representative of the builder, nor having received the document in the mail. The respondent had provided no evidence of how it asserts the document was served, other than the assertion from the bar table by Mr Vardas that the usual practice of the respondent was to send notices in the mail. Pursuant to Clause 40.1 (b) of the contract, the notice is served on the day following when it was posted, not the date it was actually received by the other party.
- However, there is documentary evidence to support a finding that the Notice of Practical Completion was served on the applicants. The Notice of Practical Completion sets out the time and date of the final inspection, and the date that the respondent asserts is the date of practical completion under the contract (8 April 2009). The document states that the respondent's "final progress claim is attached".
- The documents relied upon by the applicants contain a copy of the respondent's "Final Statement and "Summary of Account" dated 1 April 2009, which sets out the final progress payment claim. That document is signed by the applicants and dated 8 April 2009. The tax invoice of the respondent dated 8 April 2009 in the sum of $9,075.00 is signed by the applicants. There was no evidence by the applicants regarding how they received the final progress payment claim, and an inference is drawn that it was attached to the Notice of Practical Completion. The Tribunal is satisfied that the Notice of Practical Completion was received by the applicants on or before 8 April 2009, and that it was likely served by post on 1 April 2009.
- The Tribunal being satisfied that the respondent gave a Notice of Practical Completion in accordance with Clause 40 of the contract, the Tribunal must then consider Clause 26 of the contract.
- 1 April 2009 was a Wednesday, and 2 April 2009 was a Thursday. On the basis that the Notice of Practical Completion was served by post on 1 April 2009, its deemed date of service under Clause 40.1 (b) of the contract is 2 April 2009. The Notice of Practical Completion states that builder's assessment of the date of practical completion is 8 April 2009. 5 working days from 2 April 2009 is 9 April 2009. That day is one day after the date of the builder's assessment of practical completion in the notice, but still prior to 15 April 2009, which is the key date for the purpose of the 7 year statutory limitation period (the proceedings having been commenced on 15 April 2016).
- Clause 26.1 of the contract does not state that a Notice of Practical Completion is invalid if the date identified in the notice does not reflect 5 working days from the date it is served. Rather, it states that the notice must be given "at least 5 days prior to practical completion being reached". The respondent has complied with Clause 26.1 if it has served the notice in accordance with Clause 40, and the notice is served at least 5 working days prior to the date of practical completion.
- Under Clause 26.3 of the contract, the respondent and the applicants had a final site inspection with a representative of the respondent on 2 April 2009. The applicants signed a final inspection report on 2 April 2009 stating that they were satisfied that practical completion had occurred on that date pursuant to the contract, and "the defects and minor omissions set out in Annexure A do not prevent the building works from being reasonably capable of being used for their usual purpose". The applicants did not give the respondent a notice stating that they did not believe practical completion had occurred pursuant to Clause 26.3 (b) of the contract. As the final progress payment claim was not paid on 2 April 2009, then under Clause 26.6 (b) of the contract, the date of practical completion is "deemed to be the date of practical completion" contained in the respondent's Notice of Practical Completion (i.e. 8 April 2009).
- However, as the Tribunal is not satisfied that the respondent has proved that the Notice of Practical Completion was served pursuant to the provisions of Clause 40 of the contract on 1 April 2009, the date of practical completion in the Notice of Practical Completion (8 April 2009) does not reflect a date at least 5 working days from the date of service of the Notice of Practical Completion. Accordingly, the Tribunal is not satisfied that the respondent can rely upon Clause 26.6 (b) of the contract as deeming the date of practical completion to be 8 April 2009.
- Despite the respondent not being able to establish that pursuant to Clause 26.6 (b) of the contract the date of practical completion is 8 April 2009, the Tribunal must still determine the date of practical completion. The statutory definition in Section 3B (2) of the HB Act reflects the position at common law that the date of practical completion is the date upon which building work is complete and the premises are fit for occupation. The applicants acknowledged in writing on 2 April 2009 at the final site inspection that the premises were reasonably capable of occupation, other than minor defects and omissions that did not affect the date of practical completion. There is no evidence that the respondent attended the site after 2 April 2009 and performed work other than to remedy defects that did not affect the date the premises were reasonably capable of occupation. The fact that the applicants did not pay the final progress payment claim and obtain the keys to the property until 17 April 2009 is not the relevant date of practical completion. The Tribunal is satisfied that as of 2 April 2009 the building work was effectively complete and the premises fit for occupation, independent of the contractual provisions under Clause 26.6 of the contract.
- As the Tribunal is satisfied that practical completion occurred more than 7 years prior to 15 April 2016, the proceedings against the respondent have been commenced outside the limitation period and by reason of the operation of Sections 18E and 48K of the HB Act, the Tribunal has no jurisdiction in the matter.
- The applicants may perceive an injustice to have occurred because the Tribunal has no jurisdiction in this matter, and the oral evidence of the applicants and the emails between the parties clearly indicate that there has been a long history of water leaks from the upstairs balcony. However, the letter from Mr Hall of NSW Fair Trading to the applicants dated 16 July 2014 refers to the limitation period and the email from Mr Karan to the builder dated 22 October 2013 states that the builder should rectify defects "before your 7 years are up". The applicants were aware, or should reasonably have been aware, of the importance of the limitation period. The Tribunal has no power to extend the limitation period if the proceedings have been commenced out of time, irrespective of whether or not there has been defective work or that there have been a series of complaints to the builder since the construction of the residence regarding the issue of water leaking from the upstairs balcony.