"My clients regard themselves as entitled to terminate the contact [sic] forthwith and reserve their rights to take this action without any further notice should the matter not proceed satisfactorily."
12 On Friday 26 February 2010 the plaintiff responded to the defendants' proposal set out in [9] above. The plaintiff rejected the defendants' proposal and put a counter proposal.
13 Negotiations proceeded to and fro at a very leisurely pace. The plaintiff's solicitor put a further proposition to the defendants' solicitor on 5 July 2010 but the defendants on 8 July 2010 served a notice of termination of contract relying on the plaintiff's failure to complete on 12 February 2010. The plaintiff's solicitor rejected the notice of termination as invalid. The defendants on 9 July 2010 resold the land to Dandaloo Pty Limited at a slightly higher price. That contract was also advantageous to the defendants in that there was no agent and therefore no commission payable. These proceedings were commenced on 5 August 2010.
14 The plaintiff contends that there are six bases on which the contract was not validly terminated by the defendants and is therefore available to be specifically enforced in its favour.
(1) The defendants were not in a position to say with certainty that they were ready willing and able to perform the contract on 27 January 2010 when they served the notice to complete.
15 In this regard the defendants rely on what was said by Street CJ in Eq in Halkidis v Bugeia [1974] 1 NSWLR 423 at 427:
"The vendors were not in a position, had it become necessary so to do, to comply with certainty with their obligation to provide vacant possession on completion."
16 The plaintiff cites this passage as authority for the proposition that a party giving a notice to complete must be in a position to comply with certainty with its obligations on completion. There is no doubt that when a party gives notice to complete it must be ready, willing and able itself to complete at the specified time and that it bears the onus of establishing this proposition: see McNally v Waitzer [1981] 1 NSWLR 294 per Reynolds JA at 296. However, so far as I have been able to perceive, the words "with certainty" appear in the authorities only in the one instance cited above. In my view, the words "with certainty" are not part of the correct proposition: the relevant party certainly bears the onus of proof but has to show only on the balance of probabilities that it will be able to complete at the time fixed for completion.
17 The use by Street CJ in Eq of the words "with certainty" arises out of the circumstances of that case. There, there was a tenant entitled to notice if he was to be removed from the property. The tenant had indicated that he would leave, but no notice had been given to him. If he reneged on his agreement he would remain in the property on the day on which vacant possession needed to be given and there would be no way of removing him. It is for this reason that the learned Judge said that it was not shown "with certainty" that the plaintiff could give vacant possession on the relevant day.
18 That factual situation is different from the circumstances of this case. Here it is contended by the plaintiff that the defendants could not show as at 27 January 2010 that they could have the Kusic caveat removed by 12 February 2010. It is true that there was a dispute as to the amount owing under the Kusic mortgage and the situation was complicated by the fact that there was ultimately more than one claimant interested in the proceeds of the Kusic mortgage. However, Mr Jones, as liquidator of the first defendant, deposed that he was prepared to put up the maximum amount claimed to be owing in order to procure the removal of the caveat.
19 Although no application had been made to this Court as at 27 January 2010 for an order for the withdrawal of the caveat, such application could in the absence of agreement have been made to the Duty Judge in this Division and determined quickly. There is little if any doubt that this Court would, in face of the availability of monies to meet the Kusic claim, have in short order ordered the withdrawal of the caveat. If their destination were disputed, the Court would have ordered the monies to be placed somewhere secure and have given directions for the determination of any disputed questions. If the monies were available, and there is no dispute they were, it is highly probable that the removal of the caveat could have been procured.
20 In these circumstances, I am of the view that the defendants have established in the requisite way that as at 27 January 2010 they were ready, willing and able to complete the contract on 12 February 2010.
21 I should add that it would be a source of great inconvenience if parties were required to discharge encumbrances or obtain orders for the withdrawal of caveats before giving notices to complete if they can establish on the probabilities that they will be able to do so by the relevant time.
(2) The notice to complete was ineffective because the defendants were in breach of the contract at the time it was given.
22 The defendants were said to be in breach because they were not and would not be in a position to give good title because of the Kusic caveat. Attention was also drawn to the Jones caveat and the fact that transfers and a discharge of mortgage had not been prepared.
23 The situation as to the Kusic caveat is dealt with under heading (1) above. The Jones caveat could be withdrawn at any time and would be withdrawn by Mr Jones. Equally the relevant transfers and discharge of mortgage could easily be prepared before the time appointed for settlement on 12 February 2010.
24 There was no relevant breach of contract on the defendants' part by reason of which it should be held that the notice to complete was ineffective.
(3) The defendants intimated to the plaintiff that it need not complete on 12 February 2010 so that there was no breach on the plaintiff's part by its failure to do so.
25 It is said that this dispensation is to be inferred from the correspondence between the parties between 27 January and 12 February 2010. Reliance is placed particularly on the items of correspondence mentioned in [7] above and the lack of reference to settlement on 12 February 2010 noted in [8] above.
26 However, I am unable to derive from anything in this correspondence that the defendants intimated to the plaintiff that it need not complete the contract on 12 February 2010 as required by the notice or that it need not attend at that time. I am not prepared to hold that the defendants absolved the plaintiff from the requirement to complete on that day.
(4) The defendants were not on 12 February 2010 ready, willing and able to complete the contract on their part.
27 The plaintiff refers to what was said in Foran v Wight (1989) 168 CLR 385 per Mason CJ at 396 and per Brennan J at 417.
28 It relies on the fact that the caveats were still on the title as at that date; there were no executed transfers available; there was no discharge of mortgage; and there were no settlement sheets.
29 The defendants' response is that, true it is that, whilst both parties were subject to mutually dependent and concurrent obligations at that time, the defendants were entitled to rely on what was said by Brennan J in Foran v Wight ibid: