v. an allegation that excessive hours of labour had been invoiced in a situation where the alleged hours invoiced were as a direct result of JBKE's failure to design, manufacture, construct and erect the scope of work as represented within a commercially acceptable time and at commercially acceptable market rates for the scope of works the subject of their brief.
24 The adjudicator travelled in his reasons through each of these grounds presented in the payment schedule. It is inappropriate to repeat the whole of the reasons given in the determination but it is fair to say that a common theme comprised the lack of substantiation of the propositions put forward by the respondent. Again and again the adjudicator makes the point that there was insufficient specificity in the reasons given by the respondent in the payment schedule to permit the adjudicator to determine matters such as, what were the specific provisions of the contract that were allegedly breached, what the estimated cost of works said to be required by a contractual breaches would be, how the adjudicator could be satisfied that work of the claimant was defective in the aspects alleged, the lack of substantiation of the respondent's claims to withhold payment and similar. Indeed the adjudicator makes the point that even though the respondent had alleged that there was duplication in terms of invoices which it received in the adjudication response, it had not provided a single example of such.
25 Mr Flick during his address took the Court through the mass of documentary material included in the respective adjudication applications and to the mass of verification, inter alia by statutory declaration, in that regard.
26 The adjudication application contended that the "respondent's brick and block plant is fully operational and the respondent is benefiting from the claimant works". The claim for $ 510,485.83 was supported by:-