Jabbcorp (NSW) Pty Limited v Strathfield Golf Club
[2020] NSWSC 1317
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2020-09-18
Before
Ball J
Catchwords
- [2008] HCA 57 Chartbrook Ltd v Persimmon Homes Ltd [2009] 1 AC 1101
Source
Original judgment source is linked above.
Catchwords
Judgment (11 paragraphs)
Introduction
- By a contract entered into on 23 December 2016, the plaintiff, Jabbcorp (NSW) Pty Limited, agreed to design and to construct for the Defendant, Strathfield Golf Club (the Club), a new clubhouse, access road and associated works for a total price of $23,400,730 (excluding GST) (the Contract Sum). In these proceedings, Jabbcorp seeks to recover certain amounts said to be owing under the contract. Originally, the amounts Jabbcorp sought to recover consisted of the following: 1. a total amount of $809,458 in respect of variation claims made by it under the contract. 2. sums totalling $97,326 for amounts withheld by the Club for work done (described by the parties as "back-charges"); 3. the sum of $82,500 retained by the Club as liquidated damages; and 4. a bank guarantee fee of $2,150.
- During the hearing, the parties resolved a number of issues between them, which was noted by the Court on 17 September 2020. The effect of the agreement is that: 1. The parties have compromised a number of variations and back-charges and the claim for the bank guarantee fee on the basis that (1) the Club will pay Jabbcorp the sum of $32,698.50 plus GST in respect of those claims and (2) if that amount is not paid within 14 days of the presentation of a tax invoice, the Club will consent to judgment being entered against it for the unpaid amount; 2. The parties have agreed that the question whether the Club is entitled to retain the remaining back-charges turns on the question whether the work the subject of those back-charges was excluded by para (u) of the definition of "Excluded Works" in cl 1 of the General Conditions of Contract (set out below).
- As a result, the following issues remain to be determined: 1. Whether Jabbcorp is entitled to recover the amount claimed in respect of the remaining variations. Those variations include NOV014 for an amount of $53,836 plus GST, NOV014A for $277,919.75 plus GST and NOV059 for $422,838 plus GST. In each of those cases, there is a question whether the work the subject of the variation was included in the Contract Sum or whether it was excluded by para (u) of the definition of Excluded Works. If it was excluded, there is a further question whether Jabbcorp has proved the amount it claims in respect of the variations. Jabbcorp also claims a refund of $25,180 plus GST in respect of variation NOV036. That variation was a rebate of $40,180 given by Jabbcorp in respect of work undertaken by the Club. Jabbcorp contends that it ought not to have included an amount of $25,180 in that rebate because the relevant work was not included in the Contract Sum since it, too, was excluded by para (u) of the definition of Excluded Works. 2. Whether the work in respect of the following back-charges was excluded by para (u) of the definition of Excluded Works: Back-charge Value (exclusive of GST) 1 Stairs and drainage $2,660 2 Zoysia $14,488 3 Zoysia $2,832 4 Lay Zoysia adjust stormwater $2,816 5 Irrigation $6,935 6 Retaining wall $9,250 7 Supply soil $3,000 8 Wilcher fees $2,500 10 Swale and pits $6,439 11 Extra fill $1,250