(c) Mr El Gendy did provide Mr Pearson with an OHS general construction induction certificate stating he had received five hours of general OHS construction training. Mr Pearson inducted Mr El Gendy on to the site by telling him some things that were translated into Arabic by Mr Hussein. Mr Hussein, however, does not speak English very well. Mr El Gendy recalls being told to wear safety shoes and a helmet and to not stand under the formwork as it was being taken down.
29 Evidence was called by the prosecutor in relation to these matters. At the conclusion of the evidence, the prosecution conceded that it had failed to prove the second matter. The evidence on the issue was that Colmerc had previously arranged for a crane and a loading platform to be delivered to the site on the Monday following the incident (20 November). Mr Mercer, said in his statement that he had spoken to Mr Smith, Mr Pearson and Mr Abdulmajeed and had made them aware that the mobile crane and a loading platform had been organised for Monday, 20 November. He said that it was understood during these conversations that the mobile crane and loading platform would be used to lift the formwork and frames from H1 East to H2 East. Mr Mercer also said that he was aware that the workers had commenced stripping and stacking the formwork, "ready for transportation via the platform". He could not say why they did not wait for the loading platform to be set up.
30 The evidence with regard to the first disputed fact was that the formwork and falsework were dismantled and then transported manually by the workers from H1 East to H1 West. No loading platform was available on 18 November 2006 to facilitate the movement of the items from H1 East to H2 East, although it was anticipated at least three days before the incident by Mr Mercer, and REI, that a loading platform would be made available for the task on the following Monday. There was no, or limited, available storage space for the material on H1 floor. Mr Mercer, in his evidence, said he was aware prior to 18 November 2006 that the formwork and falsework was to be stripped, and that the incident wall was in the process of being constructed in H1 West. With regard to available storage space he said that there were areas on the northern side and the extreme western side of the development for storage, although there were "logistic issues". I would observe, with regard to this evidence, that if this were the case, the workers were not directed to store the materials in those areas.
31 Mr Mercer, in submissions, referred to other means of moving the material beside manual transportation which were available on the day of the incident. The prosecutor, Inspector Patton, gave evidence in which he conceded that there were on site alternative and available means of transporting the materials on the day of the incident, such as pallets, trolleys and forklift trucks. I do not see, however, how these alternative means would have resolved the problem of storage space on H1 floor or prevented the depositing of the materials in H1 West in the vicinity of, and against, the incident wall.
32 I find, based on these matters, that the first disputed fact has been made out by the prosecutor beyond reasonable doubt.
33 With regard to the third disputed fact, it appears to consist largely of exculpatory material. There is an apparent concession that Mr El Gendy provided an OHS general construction induction certificate to Mr Pearson and that Mr Pearson inducted Mr El Gendy to the site. The only inculpatory material that I can identify is that Mr El Gendy's induction was undertaken with the assistance of a translator, Mr Hussein, of whom it was asserted, "does not speak English very well". I am, however, unable to locate any evidence of Mr Hussein's understanding of, or capacity to speak, English. In submissions, the prosecutor contended that it was, "open to ... to find ... it is more likely than not that Mr El Gendy was inducted by way of a method of some translated instruction being given to Mr El Gendy by Mr Pearson".
34 Given the unsatisfactory state of the evidence, the Court finds that the prosecutor has failed to prove the third disputed fact beyond reasonable doubt.
Other objective factors
35 The agreed facts were that the incident wall had been laid about 48 hours before it collapsed and was "green" at that time, that is, the mortar was still soft and had not reached its full strength. The risk to safety (the risk of the "green" wall collapsing with items stacked against it) was obvious given the workers' inexperience in the construction industry, their lack of adequate supervision and instruction and the absence of safe alternative means of transporting and storing the materials. The risk to safety for the same reasons was also foreseeable. Mr Mercer also knew that the formwork and falsework was being stripped (or to be stripped) at the same time as the incident wall in H1 West was being constructed. Mr Mercer had, however, made arrangements for the transportation of the materials from H1 East to H2 East after they were stripped by the workers. The loading platform and the crane were due to arrive at the site two days after the incident. Mr Mercer had communicated these matters to Mr Abdulmajeed and others. In his statement (about which he was cross examined), Mr Mercer said that he would not have contemplated (or agreed) that the employees of O & H Construction would carry the formwork and frames from H1 East to H1 West. Because of his earlier communication to Mr Abdulmajeed, he did not consider there was any need for him to issue an additional instruction that the formwork was not to be moved (by hand) to H1 West. Mr Mercer also directed the Court's attention to REI's SWMS dated 21 August 2006, which provided under the heading "Management and placement of material to construction levels":
All material movements between construction levels are to be facilitated by the builder.
The formwork material is to be stacked on loading platforms and the builder will provide mobile cranes.
36 These matters operate to reduce, to some extent, Mr Mercer's culpability in the circumstances of the offence.
37 One further matter which may be considered in Mr Mercer's favour, which should be mentioned, concerns the issuing by WorkCover, prior to the incident, of 35 Improvement, Penalty and Prohibition Notices to Colmerc. The Notices focused principally on the failures of Colmerc to ensure persons working with formwork at the site were "ticketed", or otherwise properly certified or qualified, and failures to ensure site inductions were being undertaken. Mr Mercer said that, following the issue of the Notices, he raised the lack of formwork "tickets" and OHS site inductions with REI and that measures were taken which included the appointment of Mr Abdulmajeed by REI to supervise REI's activities and the labourers on the site. These measures ultimately were not successful in eliminating or obviating the risk to the safety of the O & H Construction employees on 18 November 2006, but they demonstrate that Mr Mercer at least had attempted, prior to the incident, to make some safety improvements, with regard to supervision of the workers at the site.
38 On the other hand, a number of simple and inexpensive steps could have been taken by Colmerc and Mr Mercer, which could have avoided the risk. These included the strict enforcement of the site attendance rules, ensuring that adequate SWMS were submitted by all the sub-contractors and ensuring appropriate barriers and signage were in place to prevent access to hazardous areas at the site, such as the area where the "green" wall was constructed.
39 The offence is also serious by reason of the likely or probable consequences which arose from its commission, realised in the collapse of the wall which caused serious injuries to Mr El Gendy. The injuries to Mr El Gendy could have, in the circumstances, been more serious.
40 General deterrence is also an important consideration. I adopt the observations on this issue made by me in Inspector John Patton v Romeo Elias Ibrahim and Others [2010] NSWIRComm 109 at [63]:
General deterrence must also be applied. The present set of circumstances reveals a most unsatisfactory approach to matters of safety at a construction site. Construction sites are, or can be, notoriously dangerous places for workers when they are not the beneficiaries of well-organised and promulgated systems, adequate instruction, information, training and supervision. The present matters are a timely illustration of what can go wrong when safety procedures are not properly addressed, devised or implemented. The importance of safety measures again needs to be emphasised to all employers and contractors who engage workers, particularly inexperienced workers, to perform work at a construction site.
41 Specific deterrence is also applicable. Mr Mercer informed the Court of his intention to continue to work in the construction industry.
42 Mr Mercer faces a maximum penalty of $55,000.
Subjective factors
43 The defendant entered a plea of guilty to the charge at the earliest or first reasonable opportunity. I propose, in these circumstances, to assess an appropriate penalty for the utilitarian value of the plea at 25 per cent.
44 As a separate consideration from the utilitarian value of the plea, the defendant is also entitled to leniency in recognition of the remorse shown by the plea of guilty.
45 The defendant also co-operated with WorkCover during the investigation and prosecution of the offence.
46 The absence of prior convictions also entitles Mr Mercer to leniency.
47 Mr Mercer also provided assistance to Mr El Gendy after the incident. The details are set out in his statement:
In the week following the incident, I made a number of telephone calls to Wollongong Hospital to ascertain how Mr El Gendy was. On Saturday, 25 November 2006, my family and I drove to Wollongong Hospital to see Mr El Gendy. We stayed there for about three quarters of an hour speaking with Mr El Gendy and his friend Atef Nasser. I had not met either of them before. At that time, Mr El Gendy was out of intensive care. Mr wife and I asked if him if there was anything we could do for him and his family. When I saw Mr El Gendy I was very distressed for him.
On Wednesday, 29 November 2006, I visited Mr El Gendy at Wollongong Hospital. I stayed with him for about three quarters of an hour. My wife had made up a gift of toiletries, chocolates and flowers which I gave to him. I enquired with the nursing staff about Mr El Gendy's progress.
On 6 December 2006, I went to visit Mr El Gendy again to be told that he had been discharged the day before. I spoke with Dr Tarek who gave me an update on Mr El Gendy's progress.
I found out Mr El Gendy was staying with his cousin in Punchbowl and on Sunday, 17 December 2006, I visited Mr El Gendy there. I took four of my children with me. We had afternoon tea. I spoke with his cousin Wassim. I stayed for about one hour and then left.
On Sunday, 24 December 2006, I visited Mr El Gendy at Punchbowl. I gave him $2,000 towards getting through Christmas. I stayed there for an hour and half speaking with him and his cousin Wassim.
48 Mr Mercer and Colmerc also instituted an impressive number of post-incident safety measures which have been set out in the agreed facts:
Immediately after the incident, Mr Mercer called a toolbox talk with every worker on the site to inform them of the incident, WorkCover's investigation and to advise of improvement to procedures on site and to ensure every person signed on the attendance sheet every day.
On about 24 November 2006 Colmerc prepared and issued a SWMS for erecting & dismantling formwork near green blockwork/brickwork. Included in this SWMS was a requirement for bracing to be installed to all freestanding walls, and for a barrier to be placed in a 3m radius around the wall with appropriate signage to indicate it was a 'no go zone'.
Colmerc attempted to introduce a new system whereby no contractors could work in the immediate vicinity of formwork erection or dismantling. After the incident such areas were also designated as a 'no go zone', and were recorded on the daily attendance register at the front gate of the site for all to read as they signed in each day. Colmerc also enforced the daily signing of the site attendance register.
Colmerc engaged an independent auditor, Mel Crook & Associates Pty Ltd trading as MCA Business Education & Training to conduct audits on the site. Initially these were weekly for two months and then monthly after that. Mel Crook & Associates introduced a new OHS management plan for Colmerc, and reviewed the project management plan.
Letters were sent by Colmerc to all sub-contractors on the site reinforcing safety as a priority and advising of the incident.
Extra labour was employed by Colmerc to attend to urgent safety rectification work.
Additional safety inspections and walks through the site were conducted by Colmerc as well as providing more signage directing workers to two entry points, as well as inspecting the perimeter fence to stop workers accessing the site who had not undertaken the site induction.
A system of regular identify checks on site to ensure everyone has been inducted was introduced, as well as issuing site induction stickers for all workers to place on their hardhat.
Mel Crook & Associates gave extra training to all Colmerc's employees and there was increased supervision by Colmerc of the supervisors of the trades.
Following the incident O&H did not develop an SWMS or OHS management plan or safe work procedures for their work.
Following the incident REI were guided by the actions on site by Colmerc such as setting up 'no go zones'.
After the Improvement Notice No: 254462 was issued on 18 December 2006 to Colmerc the OHS consultation system on site was changed. The OHS safety committee was replaced with an OHS representative (Mr Pearson) and mandatory toolbox talks were required of all sub-contractors on site.
At the fortnightly contractors' meeting, OHS issues were raised, and those issues were expected to be disseminated to the employees of the subcontractors in the form of a toolbox meeting, and the records of toolbox talks were to be passed back to Colmerc.
49 Mr Mercer also demonstrated contrition as reflected in the post-incident remedial measures undertaken by him, and by Colmerc, and in his expressions of remorse for the injuries suffered by Mr El Gendy which are set out in his statement:
I was devastated by the occurrence of the incident and the injuries suffered by Mr El Gendy. I recognised from shortly after the incident that it was one which should never have happened for reasons explained later in this letter.
I deeply regret that the incident occurred and that Mr El Gendy suffered such serious injuries. Despite the fact that procedures and arrangements were in place which should have avoided the incident, I feel a personal sense of responsibility because the accident happened on a construction site for which I had overall responsibility. I took pride in running a safe site but following the incident, I realised that a lack of supervision of inexperienced workers and the failure by supervisors to comply with site arrangements, work systems and standard construction procedures were the major contributing factors and that it was my responsibility to ensure a higher level of adherence to these matters.
50 Mr Crook, the managing director of the independent auditing firm engaged by Mr Mercer after the incident also attested in a letter provided to the Court to Mr Mercer's, "integrity, excellent work ethic, honesty and commitment". This matter, together with the absence of prior convictions, shows that Mr Mercer is a person of good character.
51 All of these matters will be taken into account by the Court in mitigation of the penalty to be imposed.
Exercise of discretion under s 10
52 Mr Mercer made an application that the Court exercise its discretion under s 10 of the Crimes (Sentencing Procedure) Act 1999 (CSPA) and make an order pursuant to s 10(1) to dismiss the charge.
53 A number of factors were relied upon by Mr Mercer in support of the application which include the subjective factors which have already been taken into account in these proceedings in his favour. Mr Mercer also asked the Court to take into account on the application the fact that the incident would not have occurred if the formwork and frames had been moved using a mobile crane, which had been organised by him to be on site on Monday, 20 November 2006. This latter factor has also been taken into account in Mr Mercer's favour in these proceedings.
54 An order under s 10 of the CSPA is only made in exceptional circumstances: see for example WorkCover Authority of New South Wales (Inspector Downie) v Menzies Property Services Pty Ltd (2004) 136 IR 449 at [45] [50]. In my view, the circumstances which gave rise to the offence are such that it would be an inappropriate exercise of the Court's discretion to grant Mr Mercer's application. There can be no doubt that Mr Mercer is a person of good character for reasons earlier stated, but the fact remains that the offence under s 8(1) was objectively serious. The Court has also acknowledged Mr Mercer's sincere expression of regret for the injuries sustained by Mr El Gendy. None of these matters, however, are sufficiently persuasive to attract the Court's discretion in order to grant the application under s 10(1). The finding that an offence is objectively serious, of itself would normally preclude the application being granted.
Capacity to pay a fine
55 In the alternative, Mr Mercer submitted that any penalty imposed upon him should be nominal or at the lower end of the scale because he had a limited capacity to pay a fine.
56 The information provided by Mr Mercer in support of the submission was set out by him in his statement:
Colmerc was wound up by creditors and a liquidator of it was appointed in September 2008. Colys Developments Pty Ltd, the developer of Kiama Blue, was unable to fund the remaining construction work and owed Colmerc $1,603,201. In turn, Colmerc was unable to pay debts of $726,204 to its sub-contractors and others. The funders of Colys Developments took over the project and engaged another builder to complete it.
The winding up of Colmerc was unrelated to the incident and was inevitable as a result of the debts owed by it.
As a consequence of the insolvency of Colmerc, I lost my source of income and had a substantial amount of indebtedness. To avoid bankruptcy, I was forced to negotiate with some of my creditors. My current debts are as follows:
AMOUNT PAYABLE TO
$47,360 Cleary Bros (Bombo) Pty Ltd
$15,612 Australian Temporary Fencing Pty Ltd.
$57,696 Airspec Pty Ltd
$ 1,237 Andrew Hartcher
$69,980 Colzeg Pty Ltd
$27,790 Kiama Supply Co Pty Ltd
$22,345 Sutherland Shire Montessori School
$ 7,762 GE Credit Line
$ 9,022 HSBC
$ 3,171 CBA
$ 1,329 ANZ
$39,600 HS Creek
$50,160 JS Mercer
$ 293 State Debt Recovery Office
$ 530 AMEX
My only assets are household items and a limited number of tools of trade with an approximate value of between $5,000 and $8,000.
From late 2008, I worked as a sub-contractor to Sahara Projects Pty Ltd which trades as MCD Projects and is a small company undertaking new construction and property maintenance. Payments I received from MCD Projects were barely sufficient to meet the monthly commitments to my creditors and to make a contribution towards the rent for our accommodation being paid by my wife and housekeeping expenses.
In late December 2009, MCD Projects ceased using my services as a sub-contractor. Since mid January 2010, I have been receiving unemployment benefits from Centrelink in the amount of $411 per fortnight. I currently have no other source of income.
57 The prosecutor contended on the issue that the evidence relied upon by Mr Mercer was insufficient to allow the Court to impose a low fine on the basis of financial incapacity and, in any event, the relevant case law requires that where an offence is objectively serious, the penalty imposed should reflect this.
58 Mr Mercer may not have provided supporting documentation in the form of financial records, but he voluntarily gave evidence and was cross-examined about the contents of his statement in some detail, including matters relevant to his financial position. He confirmed, for example, that a company, Mercer Management Services Pty Ltd, a shareholder of Sahara Projects Pty Limited was not a company in which he had any financial interest. He also explained that Sahara Projects Pty Limited was a company owned by his wife, but that his wife had resigned as a director and they have since separated. He confirmed that he was unemployed and seeking work in the construction industry.
59 I have no reason to doubt the reliability and accuracy of Mr Mercer's evidence. He was impressive when giving his evidence and readily acknowledged his responsibilities as a director of Colmerc for the safety of all the workers at the site, including those workers present at the site on 18 November 2006.
60 I therefore intend to take into account on sentence Mr Mercer's limited capacity to pay a fine, although the fine imposed will not be nominal and will reflect the objective seriousness of the offence.
Mr Mercer's role