Rock bolts form a crucial element of the ground support system at the intersection, the designers were the experts that were most capable of determining the outcome that a number of rock bolt installation failures may have had on the ground support system. As such, this information should have been relayed by TJH to the designers as a matter of the highest importance.
Communication
12The Agreed Facts record that TJH did not inform PB that rock bolts installed in the intersection were not properly tensioned and grouted. Nor did PB (consistent with PB's admission of guilt with regard to particular (b)) enquire of TJH whether rock bolts installed in the intersection had been properly tensioned and grouted. The consequence of the constructor's failure to inform PB and PB's failure to enquire was that PB was not aware of the defective installation of the rock bolts in the area of the intersection.
13Nor were the difficulties with installation made apparent to PB via some other source. The geological mapping and ground support determination data produced by the geologist following daily tunnel inspections, were supplied to Mr Lloyd, PB's senior tunnel engineer. Neither the mapping, nor the data, included any information about whether rock bolts had been properly tensioned and properly grouted.
Objective factors
14With regard to particulars (b) and (c) of the charge, PB's admission of guilt is confined to the failure to enquire about the rock bolts and to advise its designers about the installation of the rock bolts in the intersection. A document generated by PB in August 2004, entitled "Lane Cove Tunnel Final Design Report", discloses that part of the installed roof support devised by PB comprised CT rock bolts. The other component of the installed roof support was fibre reinforced shotcrete (shotcrete). The composite effects of both items were required for the full support of the tunnel and the intersection roof. PB produced a Specification (the Lane Cove Tunnel Rock Support Specification dated April 2005) which set out a number of requirements, including requirements for, "the installation, grouting and tensioning of the rock anchors, rock bolts and fan hangers".
15Although PB designed the construction sequence for the area of the intersection, it is important to emphasise that it has not been charged with any act or omission concerning the validity of the design, that is, the charge against PB does not allege any defect in, or inadequacy, or invalidity, of the design.
16Particular (d) is self-explanatory. The measures that should have been taken by reference to that particular was the withdrawal of Mr Lloyd from the area of the intersection and the prohibition of the other named employees from entering the intersection: see commentary on the particular in John Holland Pty Ltd v Industrial Court of New South Wales; Parsons Brinckerhoff (Australia) Pty Ltd v Industrial Court of New South Wales [2010] NSWCA 338; (2010) 202 IR 82 at [113] [114].
The risks
17The geological conditions prevailing at the intersection during the period of the charge have been set out in detail in the material extracted from the Agreed Facts.
18The risks to the safety of workers in the area of the intersection given the poor ground conditions were obvious and very serious. Moreover, PB was well-aware of the geological conditions prevailing in the area, as the Agreed Facts demonstrate. As the excavation advanced into the area of the intersection, Mr Leis, a principal designer for the area who was employed by PB, upgraded the ground support system to LCT G7 to take into account the deteriorating conditions. He produced a drawing (0059 Revision 1) dated 4 October 2005 for the modified ground support system. The drawing was expressed to provide tunnel support, taking into account the projected dyke in the intersection, as well as the span at the intersection.
19The risks were also reasonably foreseeable given the geological conditions encountered and identified in the area before the incident (namely bedrock comprising shale of low to very low strength, the occurrence of the dyke, and the highly fractured rock mass reflected in the intersecting joint plane sets and inclined fault structures).
20The geological mapping and ground support determination data, earlier adverted to in these sentencing reasons, revealed numerous identifiers or indicators of the presence of the risks at the intersection during the period of the charge. This material has been conveniently summarised by the prosecution in written submissions, and consists of the following:
(a) 27-10-05 - "overbreak in crown has continued", "projections indicate dyke affected ground conditions continue" and the ground classification was "LCT G7".
(b) 28-10-05 - "There continues to be a fault & jointing in the face Rock mass condition still poor-moderate" and the ground classification was "LCT G7/G8".
(c) 31-10-05 - "-... exposing dyke in left (back drive) - right wall shows 2 x joint sets (orthogonal) ...", the ground classification was "LCT G7/G8 (Backdrive)" or "LCT G7 (Updrive)".
(d) 01-11-05 - "ground conditions (sic) to be poor with low-med strength rock and dyke and multiple joint sets", the ground classification was "LCT G7/G8" and the estimated strength of the shale was "L-med".
21These matters reveal that PB was on notice of the risks in existence during the charge period.
22The risks could have been easily averted or avoided by the taking of three simple and obvious measures, alleged not to have been taken in particulars (b) to (d) of the charge (that is, enquiry of TJH followed by advice to PB employees, or withdrawal or prohibition of PB employees from the area of risk). Nor can there be any doubt that the risks to PB employees working in the area of the intersection (tunnel collapse and/or falling rock) could result in serious consequences, even fatal injuries. In this regard, the prosecution relies on a photograph taken after the incident forming part of the evidence which shows two persons standing in the MC5B tunnel next to what may be described as a large volume of collapsed debris situated on the floor of the MC5B.
23These factors compel the conclusion that the offence was objectively serious. Nevertheless, PB relies on a number of matters which it invites the Court to consider in assessing its culpability.
24First, it is asserted that the system of ground support which consisted of rock bolting followed by shotcreting proceeded upon the basis that the shotcrete was installed "very quickly" after the bolts were installed thereby making it impossible to observe from the floor of the tunnel whether the rocks were properly tensioned and properly grouted because the bolts themselves were effectively covered by the shotcrete.
25Accepting that to be the case, the difficulty I have with the submission is that PB by its plea has admitted that it omitted to enquire of TJH whether the rock bolts were properly tensioned and grouted. It is implicit in the allegation that the rock bolts were not properly tensioned and grouted (whether or not this was visible to the naked eye) and that an enquiry of TJH by PB would have (or should have) revealed those matters.
26Secondly, PB submitted that there was a contractual scheme, or system, in place which required TJH during the construction phase to provide requests for information (RFI) to PB on design issues and which required in turn that PB respond to such requests. According to PB, TJH made no such requests, which in the context of the charge represented a departure from the contractual scheme. TJH, according to PB, was aware of the problems with the tensioning and grouting of rock bolts and it was incumbent upon it to utilise the system in place.
27There is some force in this submission. The Agreed Facts confirm that part of the services to be provided by PB during the construction phase included PB providing responses to RFIs generated by TJH or design issues including design changes. Compliance with the system relied upon TJH making the requests. The Agreed Facts also confirm that TJH did not utilise the system in relation to the installation of the ground support in the area of the intersection (refer to Agreed Facts [47] reproduced in paragraph nine of these sentencing reasons). It was also an Agreed Fact that PB was not informed of the tensioning or grouting problems associated with the CT rock bolts prior to the incident from some other source. PB was unaware, according to the Agreed Facts, of the apparent difficulties encountered with the installation of the bolts.
28It follows from these matters that PB's failure to make the relevant enquiry of TJH may be considered by reference to the contractual scheme prevailing at the time of the offence which utilised the system of RFIs initiated by TJH and which required PB to provide an appropriate response. PB was entitled to rely on the integrity of this system, although it is not suggested by PB, nor could it be, that mere reliance on the system effectively discharged it from its obligation to make appropriate enquiry. By its plea, PB has admitted it had an obligation to enquire. PB failed in its obligation in circumstances where it was on notice of the relevant risks, and where steps were available to it to avert those risks. These findings confirm that the offence was objectively serious.
29The Agreed Facts also refer to a non-compliance/conformance procedure (NCR system) as a mechanism by which a CT rock bolt that failed installation could have been reported to TJH engineers or PB designers. According to the Agreed Facts, there are conflicting opinions about whether the NCR system should have been utilised to report failed rock bolt installations.
30According to Gregory Phillip Kotze, a consulting engineering geologist who was engaged by the prosecution to investigate the causes of the tunnel collapse and other associated matters, use of the NCR system was appropriate when the installation of rock bolts failed on more than one occasion. In his report, Mr Kotze said:
As a "one-off" or isolated incident, it would be appropriate for the bolt installer to ensure that a replacement bolt is successfully installed alongside the initial bolt site. Should it happen a second time however, or at another location, a technical "non-conformance" (or equivalent) should be raised.
Rock bolting (and hence further excavations) should be suspended in that area and the matter should be communicated to both engineering and geological/geotechnical personnel for joint review as to the cause of the failure to achieve tension. That is, it should be established that the cause of the failure to achieve tension was either equipment malfunction or geological conditions in the roof. Any equipment malfunctions should then be rectified. Should the failure to achieve tension be deemed related to geological conditions in the roof, geological/geotechnical and engineering design personnel should confer.
31The system was of course reliant on the failure of rock bolt installations to be brought to the attention of the PB designers. On the available evidence this was not done.
32Systems of reporting problems or potential problems associated with the ground support were therefore available, but none were utilised with the result that PB was unaware of the difficulties experienced by the constructors (TJH) with the tensioning and grouting of the rock bolts. This serves to emphasise that PB's culpability is confined (by reference to the charge) largely to a failure to enquire in circumstances where it had received no notice or indication of any problems with the rock bolting process.
33In addition to these matters, it was an agreed fact that drawing 0059 Revision 1 prepared by Mr Leis for the ground support at the intersection was certified by LCTC to RTA as complying with the requirements for the LCT Project. URS, the independent verifier, also certified drawing 0059 Revision 1 as complying with the requirements for the Project. The drawing, as the Agreed Facts record, was prepared by Mr Leis to provide modified ground support at the intersection taking into account the deteriorating geological conditions in that area, in particular, the projected dyke and the span at the intersection.
34The foregoing matters in combination help put into perspective the objective seriousness of PB's offence. PB's failure to enquire occurred in circumstances where it was entitled to rely upon TJH's systems and where it endeavoured to work effectively within those systems for the construction and design of the intersection.
Deterrence
35General deterrence falls for application in this case, simply because it is incumbent upon employers to ensure that appropriate systems are in place so that workers are not being placed at risk of serous injuries from being struck by falling rock and/or tunnel collapse. There is a need to impose a penalty at a level that will draw to the attention of those operating in the tunnelling, excavation and construction industries the necessity of engaging in practices that conform to the requirements of the Act.
36Specific deterrence is also relevant although, for reasons which follow, its application should be limited to the fact that PB continues to operate in the engineering, tunnelling and construction industries, undertaking major transportation infrastructure projects which have included, and include, the Epping to Chatswood Rail Link in Sydney and the Hunter Expressway Alliance in New South Wales (currently the biggest highway project undertaken in this State).
37It was conceded by the prosecution that genuine attempts had been made by PB to develop systems and procedures before and during the charge period which were designed for the safety of employees. In an affidavit sworn by Robert Kenneth Cross employed by PB as a Group Commercial Executive, details of safety systems implemented since the incident are provided. They include the following matters:
Since October 2006, the Parsons Brinckerhoff OHS management system has been independently audited and certified by a third party certifying body to meet the requirements of AS/NZS4801 Occupational Health & Safety Management Systems. Initially, certification was undertaken by NATA Certification Services International (NCIS). Since October 2011, certification has been undertaken by Det Norske Veritas (DNV).
The commitment of Parsons Brinckerhoff to Occupational Health & Safety has been recognised in a number of awards:
(a) In 2009, the Queensland Major Contractor's Association (QMCA) Award for Project Safety Excellence was awarded to the Jilalan Coal Stream Alliance. Parsons Brinckerhoff was a member of the Jilalan Coal Stream Alliance, which was appointed to carry out the civil engineering and infrastructure works for the upgrade of the Jilalan Railyard in central Queensland.
(b) In 2009, Parsons Brinckerhoff received the Exxon Mobil 4 Year Injury Free Performance Award, in recognition of the safety performance of Parsons Brinckerhoff on a number of Exxon Mobil projects over a four year period.
(c) In 2011, the QMCA award for Project Safety Excellence was awarded to the Origin Alliance. Parsons Brinckerhoff was a member of the Origin Alliance, and provided a range of design and professional services in relation to the upgrade of the Ipswich Motorway.
38In addition, PB has no prior convictions. It commenced operations in 2000 and is primarily involved in developing and operating infrastructure around the world. The PB group of companies employs approximately 14,000 people. About 2,200 employees work for the company in Australia.
39The absence of prior convictions also defines the maximum penalty for the offence as $550,000.
Other subjective factors
40The absence of prior convictions in circumstances where PB has been in operation in Australia since 2000 in industries recognised as inherently dangerous suggests that PB has a good industrial record. Other evidence referred to by Mr Cross in his affidavit demonstrates that PB is a good corporate citizen. This evidence includes the following:
In the period from October 2004 to date, Parsons Brinckerhoff has donated a total of approximately $508,000 to charities and community projects within Australia. Since October 2009, Parsons Brinckerhoff has committed to allocating at least 1% of all pre-tax profit to such charities and community organisations (based on 2009 financial results).
In 2009, Parsons Brinckerhoff committed to national partnerships with 3 organisations over a 3 year period. Those partners are Engineers without Borders, Engineering Aid Australia, and the Royal Flying Doctor Service. In 2010, Parsons Brinckerhoff added 2 new partners to its corporate responsibility program. Those new partners are Conservation Volunteers and RYDA-Rotary Youth Driver Awareness.
41PB also provides financial assistance to a wide variety of other community and charitable organisations such as the Cancer Council, The Smith Family, Red Cross and the Salvation Army.
42According to Mr Cross, in 2009 PB became a signatory to the United Nations Global Compact which comprises a set of 10 principles that address human rights, labour, the environment and anti-corruption. In 2010, PB became a signatory to the United Nations Women's Empowerment Principles which promote gender diversity and equality.
43The prosecution, in written submissions, concedes that the following subjective factors may also be taken into account in mitigation of the objective seriousness of the offence:
(i) PB entered a guilty plea at the earliest opportunity and the Court is entitled to discount the penalty by 25 per cent as reflecting the utilitarian value of the plea;
(ii) PB acknowledges responsibility for its failures;
(iii) PB co-operated with WorkCover.
44With regard to the early plea of guilty, the Court will discount the penalty by 25 per cent as reflecting the utilitarian value of the plea. The Court accepts that PB has exhibited contrition in relation to the circumstances of the offence by virtue of its acknowledgement of responsibility for the acts and omissions the subject of the particulars and because of the steps it has taken to ensure the safety of all employees and other persons associated with its areas of operation. The Court also takes into account PB's co-operation with the investigating authority. These matters, as well as its good industrial record and good corporate citizenship, will be taken into account in mitigation of penalty.
45The absence of prior convictions entitles PB to leniency normally extended to first-time offenders under the Act.
PB's role
46According to the prosecution, TJH was the principal contractor on the Project with all the attendant duties and responsibilities associated with that role (see Reg. 210 of the Occupational Health and Safety Regulation 2001 (now repealed)). PB, on the other hand, as a specialist contractor, was required to work within TJH's system. In these circumstances, the prosecution asserts, without any further details, that TJH was either more culpable or equally as culpable as PB in the circumstances of the offence.
47The Court finds it impossible to make any appropriate assessment of PB's role by reference to the role of TJH given the complete absence of detail provided by the prosecution and without the development of any further argument on the issue. Thiess and John Holland have been separately prosecuted and sentenced for offences based on evidence and on particulars that bear very little similarity to the offence to which PB pleaded guilty: Inspector Hamilton v Thiess Pty Ltd [ACN 010 221 486] [2012] NSWIRComm 26. Moreover, both Thiess and John Holland had prior convictions and faced a different maximum penalty of $825,000.
48In addition, PB has expressed caution with regard to the Court undertaking any assessment of the comparative roles of those entities prosecuted in relation to the tunnel collapse of 2 November 2005 (although it expressed support for the prosecution's first alternative that TJH was more culpable as the principal contractor). At various stages during the course of oral submissions, PB advised the Court that it may come to the view that it "does not need to determine relative culpability", particularly where the facts relied upon in the various proceedings are different and the facts relied upon in the present proceedings cannot be considered in isolation.
49Taking these matters into account the Court is unable to consider PB's role in the circumstances of the offence by reference to those entities also charged in relation to the incident.
Orders
50In IRC 1993 of 2007, the Court makes the following orders:
(1) Parsons Brinckerhoff Australia Pty Limited (the defendant) is convicted of the offence and fined $105,000 with a moiety to the prosecutor.
(2) The defendant is to pay the reasonable costs of the prosecutor as agreed or assessed.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated: 13 April 2012