Nursing Home Distribution Board
32. At about this stage of the work Joseph Scullino left the Main Switchboard area and went to the nursing home main distribution board, located approximately 84m to the north of the Main Switchboard. It was at this distribution board that Joseph Scullino proceeded to disconnect the sub main cables to be replaced and reconnect the sub main cables to be retained. These were the same cables that James Campanella was disconnecting at the Main Switchboard.
33. Before reconnecting the retained sub main at the main Switchboard, Joseph Scullino and Jae Chang tested this sub main to ensure that Joseph Scullino had made the correct disconnections and reconnections at the nursing home main distribution board.
34. Joseph Scullino and Jae Chang worked out which sub mains had to be reconnected to the sub main switch at the Main Switchboard, and instructed James Campanella which sub main cables were to be reconnected.
35. At about this time James Campanella joined Joseph Scullino, for a short time at the nursing home main distribution board, and then returned to the Main Switchboard.
The Incident
36. Joseph Scullino returned from the nursing home main distribution board and joined Jae Chang and James Campanella at the Main Switchboard.
37. At this point Tony Jang, another electrician employed by Mission Services Pty Ltd, arrived at the Main Switchboard. Tony and James proceeded to drill mounting holes in the Main Switchboard for an additional circuit breaker. Having completed drilling the mounting holes, Tony left the Main Switchboard area and went to another part of the site.
38. James Campanella and Jae Chang replaced the bus bar cover panel and the sub main switch "Sub main Control Nursing Home" escutcheon panel. (See Figure 3)
39. Jae Chang suggested that they pull the disconnected sub main cables out from underneath the Main Switchboard, while the power was still off.
40. The sub main cables to be pulled out were attached by cable ties to a cable tray, which ran down the back of the Cable Zone area. The sub main cables continued down through the Essential Services Distribution Board area and into the cable pit underneath the Main Switchboard (see Figures 3 and 4).
41. The Essential Services Distribution Board was located directly below the Cable Zone area. (See Figure 2) At the top of the Essential Services Distribution Board were two labels, one directly below the other, consisting of red background with white lettering. The top label stated "ESSENTIAL SERVICES DIST. BOARD". The label directly below stated "ALL SWITCHES ON THIS DIST BOARD ARE MAIN SWITCHES". (See Photographs 32, 33 & 34)
42. Two (2) metal floor plates in front of the left hand end of the Main Switchboard were removed to gain access to the pit underneath the Main Switchboard. (See Photographs 35 & 36)
43. No testing to determine whether the Essential Services Distribution Board was de energised was undertaken.
44. Jae Chang went down into the pit in front of the Essential Services Distribution Board and began removing cable ties to release the sub main cables.
45. James Campanella and Joseph Scullino walked over to the open Cable Zone panel area to cut the cable ties holding the sub mains to the back cable tray.
46. James Campanella had to straddle the pit where Jae Chang was working. Using his pliers or side cutters, James cut about four (4) cable ties off the back cable tray. Joseph Scullino was standing next to James Campanella. (See Photographs 29 & 30)
47. James Campanella grabbed hold of the sub main cables and tried to push them down. At the same time Jae Chang was down in the pit directly below, and pulling down on the same sub main cables, however the cables were not moving.
48. At this stage Joseph Scullino stepped over next to James Campanella, James Campanella moved to one side. James Campanella had both hands on the sub mains and Joseph Scullino had his right hand on the sub main cables and held onto the side of the switchboard with his left hand. Together they pushed down on the cables however the cables still would not move.
49. At this point Joseph Scullino leaned over and looked down inside the bottom of the Cable Zone area of the Main Switchboard. Joseph Scullino was able to see another cable tie down below the bottom of the Cable Zone area, behind the Essential Services Distribution Board.
50. Joseph Scullino reached into his back pocket and pulled out his pliers, reached down into the into the area below the Cable Zone area of the board to try and break the cable tie but was unable to break it.
51. James Campanella asked Joseph Scullino if he needed side cutters and Joseph Scullino said yes. James Campanella handed his own side cutters to Joseph Scullino.
52. Joseph Scullino held onto the outside board of the Cable Zone area of the Main Switchboard to get his balance and stood with one foot on the concrete floor and the other foot on the other side of the pit. Joseph Scullino reached down behind the Essential Services Distribution Board.
53. At approximately 3:10pm in reaching down behind the Essential Services Distribution Board Joseph Scullino came into contact with the live terminals of the bus bars supplying the Essential Services Distribution Board. Mr Scullino was electrocuted.
54. At the time of the incident James Campanella was standing behind Joseph Scullino.
55. Jae Chang, at the time of the incident was in the pit directly below Joseph Scullino.
56. Both James Campanella and Jae Chang pulled Joseph Scullino back off the Main Switchboard and onto the area outside the main switch room doors .
57. Jae Chang remained with Joseph Scullino and provided first aid whilst James Campanella went for help.
58. Nursing staff from John Paul Village arrived at the Main Switchboard site shortly after the incident and commenced CPR.
59. Nursing staff continued CPR until Ambulance officers arrived and took over, at approximately 3:35pm.
60. No adequate risk assessment was undertaken by the defendant of the work to be done in the vicinity of the Main Switchboard and the Essential Services Distribution Board.