10 The facts relate to C&A's "Alluvial Lands Project" which was located within its Hunter Valley Mine, approximately thirty kilometres north-west of Singleton. The objective was to enable alluvial lands to be mined, and, to that end, to prevent, by the construction of a four kilometre long cut-off wall and levee bank, the intrusion of water into the lands to be mined. The coal mining on alluvial lands had not been tried previously in Australia.
11 Subsection 39T(4) of the IR&D Act provides that a hearing of a proceeding before the AAT relating to a reviewable decision must take place in private. The AAT's Reasons were therefore expressed in such a way as to keep confidential the identity of C&A. Notwithstanding this, I find it convenient to relate the background facts by simply setting out the relevant paragraphs of the AAT's Reasons for Decision:
"2. It [C&A] carries out coal mining operations in the Hunter Valley. Its mining area included alluvial lands which contained many millions of tonnes of coal reserves. This alluvial area consisted of land below the one in one hundred year flood level and was composed of unconsolidated alluvial materials which were extremely permeable. These alluviums had direct contact with the Hunter River. Unless preventative measures were taken, it would have been impossible to mine the alluvial area because of the large inflows of water into the mining operation which might otherwise be expected.
3. The evidence was that coal mining on alluvial lands had been previously unknown in Australia. They had not been mined not only because of the technical difficulties associated with mining these areas, but also because of the possible environmental consequences that might follow unsuitable mining activities. Although there had been some mining of alluvial valley floors in the United States of America, the evidence was that none of those mines had been subject to a large hydraulic head from flooding which was a feature of the present site.
4. In order to mine the alluvial lands and exploit the available coal reserves, the applicant decided to construct a cut‑off wall and levee bank to prevent an ingress of sub‑surface waters and surface flood waters into the mining area. Extensive investigations were carried out leading to the design of the cut‑off wall which was eventually accepted. These investigations focussed on the physical characteristics of the alluviums, the geotechnical conditions within the alluviums along the length of the cut‑off wall, the maximum forces encountered in flooding and other sources of wall instability.
5. Soil‑bentonite technology was chosen as a means of preventing ground water flowing into the mining area. Put simply, soil‑bentonite technology involves the design and construction of a wall composed of bentonite and suitable soil and placing that wall in such a position as to block off the flow of unwanted waters. The evidence was that this technology had not previously been used in the coal mining industry, nor had it been used in the geological conditions that existed in the alluvial area, namely in the presence of dense soils, solid rock and coal. In particular, it had not been used in situations where there was a potential for large hydraulic heads from flooding as was the case in this proposed mine.
6. Detailed investigations were undertaken into the siting and height of a levee. The design proposed that the cut‑off wall be keyed into and be an integral part of the levee. Considerable emphasis was placed on designing the levee and cut‑off wall interface after laboratory studies into the settlement behaviour of a range of soil‑bentonite backfill mixes had been conducted. The combined levee and cut‑off wall structure were intended to act as a barrier to floods and ground water flows.
7. The applicant then undertook a program of monitoring the integrity of the wall and levee. The program is still ongoing and will continue during the life of the mine, estimated at 10 years. The monitoring and testing followed the de‑watering of the alluvial aquifer, that is to say the removal of water from the proposed work site. The evidence was that the development of a cut‑off wall and levee bank to allow alluvial lands to be mined had not been done on a significant scale, either in Australia or in any other part of the world.
8. A soil‑bentonite cut‑off wall involves the excavation of a relatively narrow trench which is continually topped up with a bentonite slurry. Bentonite is a form of clay. This slurry has properties including high swell, high water absorption and low permeability which prevent the trench from collapsing. Bentonite forms a weak structure when placed in solution, has self‑healing properties when broken and has the ability to form a filter cake.
9. De‑watering involved the sinking of bores on the river side of the mine. These were spaced on a grid pattern with intervals depending on local permeability. As with catch drains, the evidence was that there were difficulties with constructing a bore field that could cope with high river level conditions. There were also significant costs involved both in the construction and maintenance of the bore field, as well as high energy costs required to run the bore field pumps.
10. The applicant's principal area of expenditure, for present purposes, was laid out in the construction of the cut‑off wall and levee bank. The slurry cut‑off wall trench was excavated using bentonite slurry trenching methods and was then back‑filled with a mixture of soil and bentonite to provide an impervious wall. Its maximum depth below the natural surface was approximately 30 metres.
11. Difficulties were encountered in the excavation because of the presence of a coal seam over a 1,150 metre length. This excavation was expected to be difficult because of the variety of hardness bands running through the seam. As it turned out, the contractor did experience considerable problems in this part of the work.
12. Eventually the construction was completed through the use of a combination of four hitherto uncombined, but nevertheless common engineering techniques. The machines and methods used were hydro‑fraises, long stick excavators with specially modified buckets which allow ripping of hard material at depth, large diameter drilling through the slurry and the use of blasting under the bentonite slurry.
13. In late 1994, the applicant applied to the respondent for an advance ruling on the whole project involving the mining of alluvial lands. At its meeting on 1 March 1995, the tax concession committee ('TCC') (a delegate of the respondent Board) gave an unfavourable opinion on the whole of the project on the grounds that the claimed activities did not comply with the definition of research and development activities as set out in section 73B of the Income Tax Assessment Act 1936.
14. ………………………………………………………………………………
15. ………………………………………………………………………………
16. ………………………………………………………………………………
17. A second application was lodged on behalf of the applicant for the 1994 calendar year. This project was considered to be the same project as outlined in the advance ruling which had been rejected in March 1995.
18. A third application for registration for the 1995 calendar year was received by the respondent Board on 1 July 1996. This application related to the same project, but by this time the respondent Board was prepared to take a different view. The claimed activities considered by the TCC were:
(1) Investigation and design of a suitable ground and flood water protection system that comprised:
(a) Overseas investigation of alluvial valley floor mining in USA.
(b) Assessment of various options that led to the choice of pursuing a Cut‑off Wall type to control ground water and minimise seepage.
(c) Research and design of a soil‑bentonite cut‑off wall.
(d) Investigations leading to a choice of levee bank design.
(e) Research and design of the levee bank and the interface join between the cut‑off wall and levee bank.
(2) Construction of the cut‑off wall and levee bank which includes instrumentation to measure performance of the wall and bank.
(3) Dewatering the alluvial mine site area to allow mining to commence.
(4) Blasting and mining a technically determined section (about 1000 metres) of the alluvial area adjacent to the cut‑off wall and levee bank.
19. At its meeting on 2 October 1996, the TCC decided that some activities (referred to as core activities) were covered by paragraph (a) of section 73B(1) and some (described as supporting activities) were covered by paragraph (b). Activities described above in paragraphs (1)(a), (b), (c), (d) and (e) involving the investigation and design of a water protection system were accepted as complying with the definition. The activities described above in paragraphs (2), (3) and (4), namely the construction, de‑watering and blasting stages of the project, were rejected. Activities 1(c), (d) and (e) were accepted as eligible core activities as they were systematic, investigative or experimental activities which involved innovation or technical risk and were carried on for the purpose of acquiring new knowledge or creating new or improved materials, products, devices, processes or services. The TCC determined that activities (1)(a) and (b) were not core activities but accepted that they did directly relate to the core activities and were therefore supporting activities.
20. The activities mentioned in paragraphs (2), (3) and (4) are those that are the subject of the present proceedings. They were rejected by the TCC as the respondent's delegate for the reason that the primary technical problems associated with the cut‑off wall would be solved by the design, development and testing activities [1(c), (d) and (e)], that these activities would lead to the specifications for the construction of the wall and that construction would not involve any systematic, investigative or experimental activities but rather the application of known bentonite techniques. The TCC further determined that the construction of the wall and levee, de‑watering of the aquifer and blasting would not be carried on for the dominant purpose of acquiring new knowledge or creating new or improved materials, products, devices, processes or services. Rather, it said, they were carried on for purposes associated with mining and so could not be considered to be core activities as they would not involve acquiring new knowledge of creating new or improved materials, products, devices, processes or services. The TCC also determined that they were not supporting activities."
12 The following diagrammatic representation of the soil bentonite cut‑off wall and levee bank is taken from the papers: