Findings as to retrospectivity of Section 18E to pre-1 February 2012 building works
- The Tribunal has considered both the builders and the owner's submissions.
- The builder and the owner have identified the two contentious interpretations as a result of the 2014 Amendments to s 18E.
- The differing views of the owner and the builder respectively of the correct interpretation of the application of the retrospectivity of the 2014 Amendments is an issue that has not, so far as the Tribunal is aware, until now been the subject of any definitive findings of this Tribunal, except for Gray. Although the finding was made in Gray that the 2014 Amendments did not affect the 2011 Amendments, the decision is challenged by the builder on the basis that there were no detailed reasons to support the finding that the "major defects" regime introduced by the 2014 Amendments did not operate retrospectively before the 2011 Amendments.
- However, the builders contention is that, effectively, the 2014 Amendments, apply to all contracts retrospectively. That is, Cl 109, inserted by the 2011 Amendments, conflicts with Cl 121, inserted by the 2014 Amendments.
- Clause 121(1)(d) amends the HBA so that it applies to a loss, liability, claim or disputes that arose before the commencement of the amendment and therefore the amendments to section 18E apply to any loss, liability, claim or dispute prior to 1 February 2012.
- It is the builder's contention that this supports its claim that the limitation period of seven years for all defects no longer applies to building works undertaken on or before 31 January 2012 and instead there is a six year limitation period for structural defects and two years for all other defects.
- The effect of the 2014 Amendments being also to change and redefine "structural defect" as "major defect". The builder argues that the amendments have the effect that the change to the limitation period applies because the dispute arose before the commencement of the 2014 Amendments and Cl 121(1)(a) and (b) extends the operation of the amendments to building work commenced or completed before the commencement of the 2014 Amendments.
- The perceived conflict between the savings provisions of cl109 of the 2011 Amendments and the combined effect of cll120 and 121(1) of the 2014 Amendments must be examined to allow the Tribunal to make a finding as to interpreting the intent of the amendments.
- Clause 120 provides that Part 20 (Provisions consequent on enactment of Home Building Amendment Act 2014) prevails to the extent of any inconsistency with any other provision of Schedule 4.
- Clause 121(1) provides that the amendments made by the 2014 Amendments extend to a residential building work commenced or completed before the commencement of the amendment.
- The 2014 Amendments at [28] and [29] amended s 18E(1)(b) by replacing "structural defect (as defined in the regulations)" with "major defect" and inserted s18E(3) and (4), defining the term "major defect".
- By cl 121 the 2014 Amendments apply to all losses, liabilities, claims or disputes arising before the commencement of the 2014 Amendments in respect of residential building work commenced or completed before the commencement of the amendment.
- Clause 109 remains in the HBA. It was not repealed by the 2014 Amendments. The general rule in Kidman that statutes are assumed not to have retrospective operation was clearly stated by cl 109. It was open to Parliament to amend cl109. It did not. As submitted by the builder, Ss5 and 30(1) of the Interpretation Act provide that the effect of amendment or repeal of Acts and statutory rules do not apply where the contrary intention appears.
- Clause 105 in Part 19 (Provisions consequent on enactment of Home Building Amendment Act 2011) is in similar terms to cl120 in Part 20. It provides that Part 19 prevails to the extent of any inconsistency with any other provision of Schedule 4.
- Parliament did not repeal or amend Part 19 with the 2014 Amendments. Cl 105 and cl 120 regard must be had to their respective titles, that is, Part 19 relates to the 2011 Amendments and Part 20 relates to the 2014 Amendments. Without such an interpretation the cl105 and cl 120 create an ambiguity and conflict between them.
- The purposive test of statutory interpretation supports an interpretation that the 2014 Amendments dealt with the change of "structural defect" in s 18E(1)(b) to "major defect" and adding the definition of "major defect" as s 18E(3) and (4). Before the 2011 Amendments s18E did not distinguish between "structural defects" and "other defects". Part 20 c121 is intended to operate retrospectively from the date of the 2014 Amendments to the date of the 2011 Amendments.
- The Tribunal is satisfied there is no amendment to the limitation period and no conflict with Cl109. In the case of a loss, liability, claim or dispute arising up to 31 January 2012, the claim should be considered in terms of a defect and there is no effect on the seven year limitation period then, and still, applying for residential building work from the date it was completed, that is, September 2010.
- Clause 109 has the effect that the warranty period for residential building work in any contract entered into before 1 February 2012 (the commencement of the amendment) remains at seven years from the date of completion of the work.
- The 2014 Amendments did not repeal or amend Cl 109.
- The Tribunal is satisfied that the owner has brought his application within 7 years of the completion of the building work and that the Tribunal has jurisdiction to hear and determine the owners application.