© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2014] VCAT 380
Victorian Civil and Administrative Tribunal
2014-04-04
Original judgment source is linked above.
"External cladding: 75mm foam complete with acrylic topcoat and waterproof finish membrane. Complete system to be installed strictly in accordance with the manufacturer's recommendation."
"Staining, folds, splits, dents, open joints between panels, cracking and other distortions in wall cladding are defects if they are visible from a normal viewing position at ground level or an upper floor level."
It does not seem to me that this paragraph describes what has occurred in regard to this heat transference.
"If he had told me he was not happy, then I would have arranged for self levelling compound to easily fix the problems, but Peter was supervising this aspect of the work, as with other aspects of the work".
"With respect to the tiler, you gave me his phone number and you told me to ring him. I met him on site and I negotiated his rates and gave him his set out instructions. Thereafter, I gave him day to day instructions."
"The timing was a "debacle" as you put it. The tiler, recommended by you did only part of the job, was supervised by us, paid by us and on several occasions until finally, he refused to continue working due to the unfairness of the floors. It took at least a week to get you to grind them back to somewhere near level and another 3 days to clean up the disgusting mess of slurry you left on the window and door frames plus the glass and other abutting finishes."
"11.04 Floor and wall tiles where the Owner supplies and lays the tiles.
The Owner is responsible for checking the adequacy of the substrate before laying the tiles. Any failure of tiles, adhesive or grout, where the Owners supplies and lays the tiles, is the responsibility of the Owner."
"As the preparation of the background is normally carried out by others, the Tiler should not proceed unless he considers that the preparatory work is satisfactory."
Excessive noise transfer through the party wall
(a) a claim for economic loss or damage to property in an action for damages (whether in tort, in contract, under statute or otherwise) arising from a failure to take reasonable care; and
(b) a claim for damages for a contravention of section 18 of the Australian Consumer Law (Victoria).
(2) If a proceeding involves 2 or more apportionable claims arising out of different causes of action, liability for the apportionable claims is to be determined in accordance with this Part as if the claims were a single claim.
(3) A provision of this Part that gives protection from civil liability does not limit or otherwise affect any protection from liability given by any other provision of this Act or by another Act or law".
" (1) In any proceeding involving an apportionable claim -
(a) the liability of a defendant who is a concurrent wrongdoer in relation to that claim is limited to an amount reflecting that proportion of the loss or damage claimed that the court considers just having regard to the extent of the defendant's responsibility for the loss or damage; and
(b) judgment must not be given against the defendant for more than that amount in relation to that claim.
(2) If the proceeding involves both an apportionable claim and a claim that is not an apportionable claim -
(a) liability for the apportionable claim is to be determined in accordance with this Part; and
(b) liability for the other claim is to be determined in accordance with the legal rules, if any, that (apart from this Part) are relevant.
(3) In apportioning responsibility between defendants in the proceeding the court must not have regard to the comparative responsibility of any person who is not a party to the proceeding unless the person is not a party to the proceeding because the person is dead or, if the person is a corporation, the corporation has been wound-up."
"(1) A concurrent wrongdoer, in relation to a claim, is a person who is one of 2 or more persons whose acts or omissions caused, independently of each other or jointly, the loss or damage that is the subject of the claim."
"The Bank sues on a guarantee. It seeks, in effect, specific performance of the contract of guarantee. No question of failure to take reasonable care arises in that claim, or could possibly arise".
No question of any failure to take reasonable care arises for that claim.
Margin on sub-contractors paid directly by the Owners
The Builder's claim for GST on their contractor's invoices
The claim for the party wall and miscellaneous works
"We accept no responsibility for cost over-runs as the Contract entered into is on a cost plus basis and the majority of the repair work has been borne by our company, despite the fact that in our opinion a fair proportion of the problems have been caused by discrepancies in the plans provided by you."
"...there is not, nor has there been any costs incurred by you in this matter.":
Hyndman
Hurtob Homes Pty Ltd