HEADNOTE
[This headnote is not to be read as part of the judgment]
This case concerns an attempt by the applicant, Hynash Constructions Pty Ltd (Hynash) to set-off an upfront payment, made under a construction contract, against a claimed amount under a payment claim for progress payment served on it by the respondent, BRP Industries Pty Ltd (BRP), in circumstances where Hynash failed to respond to the payment claim with a payment schedule.
In early 2022, Bathurst Regional Council engaged Hynash as head contractor for the Bathurst Stormwater Harvesting #3198 Project. On 22 December 2022, Hynash subcontracted part of the works to BRP. On 5 January 2023, Hynash made an upfront payment to BRP of 10% of the quotation, as required by the subcontract. The subcontract entitled Hynash, on termination of the contract, to reimbursement of any overpayment or other monetary benefits, including by set-off against any amount which it owed to BRP.
BRP started work on 30 October 2023. In January 2024, Hynash advised BRP that the works would not continue, as a result of which BRP on 13 March 2024 terminated the subcontract and served a payment claim on Hynash for $234,286.80, pursuant to s 13 of the Building and Construction Industry Security of Payments Act 1999 (NSW) (the Act). Hynash neither paid the payment claim, nor served on BRP a payment schedule pursuant to s 14 of the Act.
On 1 May 2024, BRP commenced proceedings in the District Court, seeking judgment for $234,286.80 plus interest and costs. Hynash's defence alleged that the upfront payment should be deducted from the claim. BRP applied for summary judgment. On 2 September 2024, Russell SC DCJ ordered judgment for BRP for the full amount, finding that s 15(4)(b)(ii) of the Act (which prohibited the raising of a defence in relation to matters arising under the construction contract) prohibited Hynash from arguing, in those proceedings, that the upfront payment reduced the 'unpaid portion of the claimed amount' recoverable by BRP.
Hynash seeks leave to appeal, on the basis that the upfront payment constituted a partial payment of the payment claim under s 15(2)(a)(i), rather than a defence prohibited under s 15(4)(b)(ii).
The Court held (Adamson JA, Bell CJ and Basten AJA agreeing with additional reasons), refusing leave to appeal, if required, and otherwise dismissing the appeal with costs:
(1) How, if at all, the upfront payment was to be apportioned in reduction of a payment claim was a question of construction of the contract which accordingly falls within the prohibition in s 15(4)(b)(ii) of the Act: at [1] (Bell CJ), at [36]-[38] (Adamson JA), [47] (Basten AJA).
(2) Hynash's construction of ss 15(2)(a) and 15(4)(b) is unsupported by the wording of those provisions and is inconsistent with the purpose of the Act: at [1] Bell CJ, at [39]-[42] (Adamson JA), [48]-[51] (Basten AJA).